KENT COUNTY COUNCIL
FLOOD RISK MANAGEMENT COMMITTEE MINUTES of a meeting of the Flood Risk Management Committee held in the Medway Room, Sessions House, County Hall, Maidstone on Monday, 25 October 2010.
PRESENT: [name removed] (Chairman), [name removed], [name removed], [name removed], [name removed] (Substitute for [name removed]) and [name removed]: [name removed] (Flood Risk Management Officer), [name removed] (Assistant Head of Emergency Planning) and [name removed] (Democratic Services Officer)
UNRESTRICTED ITEMS
20. Membership (Item 1)
The Committee noted that [name removed] had replaced [name removed].
21. Minutes of the meeting on 29 July 2010 (Item 3)
RESOLVED that the Minutes of the meeting held on 29 July 2010 are correctly recorded and that they be signed by the Chairman.
22. Sustainable Drainage Systems (SUDS) (Item 4)
(1) [name removed], the Flood Risk Management Officer began his presentation by explaining that “SUDS” stood for “Sustainable Drainage Systems”. The “U” no longer stood for “Urban.”
(2) SUDS were designed to mimic a natural process for managing water runoff, thereby minimising discharge rates and volume whilst providing better water quality.
(3) The main benefit of SUDS was that they avoided the use of conventional gravity sewers to discharge water, which could lead to flooding. This could happen if the sewer system was extended whilst the existing sewers were not upgraded. A particular concern was that if the sewers discharged into a combined sewer, any flooding would also involve effluent.
(4) Many combined sewers had been laid under roads in the late 19th and early th 20 Centuries. They may have been built to cater for 1 in 30 year storms, discharging into rivers if an event exceeded this design capacity.
(5) [name removed] then described the various forms of SUDS Techniques. An important source control technique involved green roofs. These contained a thin layer of soil
18 which was able to absorb rainfall (which evaporated at a later stage). A further benefit of this technique was that it provided better insulation for the property.
(6) Rainwater harvesting involved storing roof water in tanks for use as garden water and lavatory flushing. This water could not, however be used for washing or drinking.
(7) Swale filter grids were vegetated surface features that drained water evenly off impermeable areas such as road surfaces. This water could be stored or else released to slowly infiltrate the ground.
(8) Permeable paving (whether brick work with gaps between them or a gravel surface) enabled water to filter through to a storage point below the surface from where it could discharge to a local water course or sewer or infiltrate the ground below.
(9) Infiltration techniques enabled water to be collected and disposed of by using the natural properties of local soil. Features of these techniques were soakaways, detention basins (which dried out), detention ponds (which could support wildlife and discharged slowly after the rain had stopped falling). Another form of infiltration technique was underground storage. This involved collecting water in large perforated pipes or in stormcells. It was essential to ensure that the water collection process was properly filtered as the danger was that the system could become blocked through the accumulation of silt.
(10) Surface water was sometimes drained from houses into a soakway. This was not an appropriate technique for clay surfaces.
(11) [name removed] asked why the drainage systems were sometimes vulnerable to 1 in 1 year storms. [name removed] replied that at the time that a sewer had originally been laid, it might well have been designed to cope with a 1 in 25 year flood event. As the town expanded, the system’s capacity became steadily reduced to the point where it could cope with only a 1 in 5 year event or less.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the meeting on 25 October 2010Minutes | 5 pages | DownloadRead as text |
Follow Kent Flood Risk and Water Management Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Jun 2026 | Minutes of the meeting on 04.03.26RESOLVED that the minutes of the meeting held on 4 March 2026 were an accurate record and that they be signed by the ... | Decided | Open |
| 4 Mar 2026 | Minutes of the meeting on 29.10.2025RESOLVED that the minutes of the meeting held on 29 October 2025 were an accurate record and that they be signed by t... | Decided | Open |
| 4 Mar 2026 | KCC Severe Weather Response Activity ReportRESOLVED to note the verbal update on | Noted | Open |
| 4 Mar 2026 | Met Office- Introduction PresentationRESOLVED to note the Met Office Presentation | Noted | Open |
| 4 Mar 2026 | SGN - Introduction and Water Ingress into the Gas Network PresentationRESOLVED to note the Southern Gas Network (SGN) presentation | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.