RESOLVED that:- (a) permission be granted to the proposal subject to conditions including conditions covering the standard time condition; and the development being completed in accordance with the approved plans; and (b) the applicants be advised by Informative of the Committee’s view of the need to ensure that the poly-tunnel is kept in good repair.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Planning Applications Committee, 9 pages
Background
2. Milestone School is designated for children with Special Educational Needs, and includes those with Profound and Multiple Learning Difficulties. The children range in age from 2 to 19 years old and the school is divided into Key Stage 1 and 2, Key Stage 3 and 4, and Further Education departments. In total, Milestone School provides 223 full-time school places.
3. Recent developments on site include a large extension to the school buildings to provide additional Key Stage 1 and 2 accommodation, an extension to the car park and the provision of a new play area. In 2008, two mobile classrooms were granted temporary planning permission to be sited on the school playing fields, for use during extension works at the school. However, these buildings were not installed on site and the permission has since expired. There are two large temporary modular buildings to the north and east of the site which provide accommodation for the post-16 year old pupils.
D3.1 Item D3 Poly-tunnel greenhouse and a double-garage – SE/10/1416
D3.2 Item D3 Poly-tunnel greenhouse and a double-garage – SE/10/1416
D3.3 Item D3 Poly-tunnel greenhouse and a double-garage – SE/10/1416
Proposal
4. This application proposes the installation of a 12.8m by 9.76m twin greenhouse. The structure will be vertical sided, with a double-arched polythene roof, and sliding doors and vents. The greenhouse walls are proposed to be 2.3m from ground to eaves, with a maximum roof height of 3.7m at the peak of the ‘tunnel’. The proposed garage would measure 2.29m in height, covering a floor space of 37sq.m, with a pebble-dashed finish and steel roll shutter doors.
5. The proposed buildings are to be located in the south east corner of the school site, adjacent to an existing vegetable garden and outdoor education area, with raised vegetable plots, a chicken run and planting. The area lies adjacent to an existing car park, with the playing fields to the north, and a hedgerow boundary to farmland to the east. The nearest residential properties are 70m to the south, with woodland in between.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
15Proposal SE/10/1416 - Multispan green house and roof garage at The Milestone School, Ash Road, New Ash Green; Governors of The Milestone SchoolThis decision
Minutes of the Meeting Held on 17.6.2026RESOLVED that the minutes of the meeting held on 17 June 2026 were correctly recorded and that they be signed by the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.