Customer and Communities Policy Overview and Scrutiny Committee noted this item on Thursday 15 September 2011. Below is the council's own wording, with the papers it was decided on.

Item24

Resolved

RESOLVED that the projected outturn figures for the directorate for 2011/12 based on the latest monitoring report to the Cabinet be noted.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Customer and Communities Policy Overview and Scrutiny Committee, 4 pages

Background

2.1Policy Overview and Scrutiny Committees (POSCs) consider priorities for the Medium Term Plan (MTP) at their November meetings and the draft MTP and annual budget at their January meetings. To inform discussion, three reports are presented to the Committee on a regular basis:

a) Budget Monitoring reports

A quarterly budget monitoring report is presented to Cabinet, usually in September, December and March and the Customer and Communities’ annex to those reports is on the agenda of this Committee at the next available meeting. This keeps Members informed about current trends, pressures and management actions in advance of budget setting.

The approved A-Z of budgets have be realigned for the first quarter's budget monitoring to reflect the new portfolio responsibilities and new directorate structures to give a new starting point for the year

b) Performance reports

Reports are also brought to POSCs throughout the year advising Members of performance against national indicators, KCC priorities, operational business activity and any external inspection reports.

c) Outturn report

The outturn report in July summarises financial and performance information for the preceding year. 3 Quarterly monitoring report

3.1Attached as an annexe to this report - for the first time in 2011/12 for the members of this POSC - is the full monitoring report for the first quarter of 2011/12 in relation to the Customer and Communities portfolio.

The salient issues from this report are highlighted and summarised below.

3.2Revenue

3.2.1 At the July POSC, members were orally updated on progress against 2011/12 savings targets and the current monitoring position.

A balanced position was to be delivered as part of the Exception monitoring report, however it was confirmed that two of the savings targets (Communications and the Contact Centre) were not progressing as expected, with the quantum to be confirmed in the full quarterly monitoring report.

3.2.1.1 The quarterly monitoring report shows the directorate is forecasting a net overspend – for the first time in recent years – of £0.8m, which comprises pressures/overspends of £1.25m and part compensating underspends of £0.45m

3.2.2 The main components of the net overspend of £0.8m are outlined below:

Shortfall against, and/or acceleration of, 2011/12 MTFP savings:

• Contact Centre +£0.64m

The service was to deliver £406k of savings in the current year, with solutions to half of these being met for 11/12. Management action is being devised in order fully mitigate this pressure but the ability to deliver the savings has been affected by grant reductions which has reduced the funding base for some of the services delivered by the Contact Centre.

In addition to the pressure above, the service has also experienced a significant increase (in the region of 20%) of call volumes, which is primarily due to the current economic climate.

This has meant that the service has been unable to respond to its required answer rate of 80% of calls within 20 seconds (“80/20”). In order to achieve this performance indicator, an estimated 24 FTE would need to be employed at a full year cost of £600k (part year effect £450k).

Therefore the £450k part year effect of call volume pressure, as well as the £200k pressure in relation to savings targets not progressing as expected, comprises the £640k projected overspend.

Avenues are being explored with regard to funding the additional resource required, as well as relaxing the performance indicators. • Communications, Media Relations and Engagement +£0.60m

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial MonitoringReport 4 pages DownloadRead as text
PDF
Item B8: Appendix to Financial Monitoring ReportAppendix 13 pages Download

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. Financial MonitoringThis decision
  2. Covid-19 Financial MonitoringNoted
  3. Covid-19 Financial MonitoringNoted
  4. Covid-19 Financial MonitoringNoted
  5. Covid-19 Financial MonitoringNoted
  6. Financial Monitoring 2017-18Noted

More from Kent Customer and Communities Policy Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
21 Mar 2012 Minutes - 20 January 2011RESOLVED that the minutes of the meeting held on 20 January 2012 are correctly recorded and that they be signed by th... Decided Open
21 Mar 2012 Community Budgets - Gaining TractionRESOLVED that the report and comments made by Members be noted. Noted Open
21 Mar 2012 Transforming the Business - Service Improvement - Customer and CommunitiesRESOLVED that the presentation be noted Noted Open
21 Mar 2012 Youth Service Transformation - verbal updateRESOLVED that the update and the comments made by Members be noted. (Post meeting note: A meeting of the Communities ... Noted Open
21 Mar 2012 Update on the London 2012 Olympic and Paralympic Games including the Kent School GamesRESOLVED that the update and comments made by Members be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies