Corporate Policy Overview and Scrutiny Committee agreed this item on Wednesday 11 January 2012. Below is the council's own wording, with the papers it was decided on.
It was agreed that the outcome of the meeting on 11 January 2012 between [name removed], [name removed] and [name removed] to agree the savings that [name removed] needed to achieve would be circulated to Members of the Committee. · [name removed] stated that in relation to engaging with Small and Medium Enterprises ( SME’s ) in Kent his team was being as proactive as possible within their available resources, this included working though Chambers of Trade and similar organisations. · In relation to where possible savings could be achieved in Social Care, [name removed] replied that savings could be achieved by for example using a team of social care specialists to procure services for the needs of the child rather than this being done by individual social workers. The team would ... view the full minutes text for item 153.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Corporate Policy Overview and Scrutiny Committee, 3 pages
By: John Simmonds, Cabinet Member for Finance and Business Support Andy Wood, Corporate Director of Finance and Procurement To: Corporate Policy Overview & Scrutiny Committee, 11 January 2011 Subject: Procurement Practice Classification: Unrestricted
Summary: This report provides information for Members of the Policy Overview & Scrutiny Committee on the improvements that have commenced in Procurement and how this will be taken forward in the next year.
Introduction
1. The Council has recognised that there was potential to improve the way it procures goods and services. As a result a new role of Head of Procurement was introduced and Henry Swan started in this role on 5th September 2011.
2. The strategy to deliver better procurement consists of four streams:
• Improving procurement resource and centralising the team • Reviewing and implementing clear processes for procurement • Setting clear Governance, including setting strategies for all categories of procurement • Implementing IT systems to support improved procurement
Performance Review So Far
Resources
3. In order to deliver the improvement in procurement that is required, we need to develop a structure that is capable of delivering better procurement for KCC.
4. Recruitment has been taking place and many posts have now been filled with just four left to recruit as at 16th December 2011. The majority of team will be in place by 1st February 2012.
5. The structure is as appendix A.
Processes
6. Clear processes for all procurement drawn up and implemented across the Council, published on the updated intranet and training developed to support roll out as required. Updating of intranet has commenced and new processes will be added in the form of “How to Buy Guides” and the Statement of Required Practice (SORP). 7. The new processes focus on better planning through utilisation on Category Plans (appendix B) and Procurement Plans (appendix C), the first of these are now being developed for Facilities Management and various procurements for FSC.
8. New processes are supported by and linked to the IT Systems introduction described below.
Governance
9. Clear governance of procurement is required to ensure that all procurement is carried out in a planned way making use of the opportunities across KCC and not just being Directorate led.
10. A Procurement Board has been set up to approve:
• Procurement Priorities • Strategy Plans • High Value or High Risk Procurement Plans • Updates on progress against above plans • Make, Buy, Sell Decisions
11. Delegated authorities are to be updated and clearly articulated, work has commenced on this with Legal and Democratic Services
Systems
12. To comply with Transparency Guidance and to manage our Contracts better all opportunities over £50k will be published on an externally visible portal (Currently SE Business Portal) and all subsequently awarded contracts will be listed on the same Portal. All current contracts over £50k will also be added to the Portal.
13. We are now ready to upload more than a thousand current contracts on to the portal which will move us to having a large proportion uploaded with the target of getting all contracts listed by end of March.
14. We currently are reviewing and developing processes and detailed approval structures to commence roll out of i-Proc across the Council
15. The roll out of i-proc and ERP is continuing and will give visibility and control of purchasing, give commitment accounting and improve the procure to pay process. This will reduce transaction costs and increase compliance to agreements. Targets for the Next Year
Savings 2012/13 £6 million 2013/14 £7 million Above subject to review based on further detailed investigation
Governance Procurement Board in place by End January 2012 Constitution and guidance updated End January 2012 Processes New processes in place, clearly defined and communicated end of March 2012
Systems All contracts advertised and recorded on central portal accessible to all end March 2012
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Policy Overview and Scrutiny Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.