Resolved
RESOLVED that the projected outturn figures for the directorate for 2011/12, based on the monitoring report to Cabinet on 19 March 2012 be noted.
Customer and Communities Policy Overview and Scrutiny Committee noted this item on Wednesday 21 March 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the projected outturn figures for the directorate for 2011/12, based on the monitoring report to Cabinet on 19 March 2012 be noted.
To: Customer and Communities Policy Overview and Scrutiny Committee
By: Mike Hill, Cabinet Member for Customer & Communities Services Amanda Honey, Managing Director for Customer & Communities
Date: 21 March 2012
Subject: Financial Monitoring 2011/12
Classification: Unrestricted
Summary: Members of the POSC are asked to note the latest projected outturn figures for the directorate for 2011/12 based on the monitoring report to Cabinet on 19 March 2012.
For Information and Comment
1. Introduction 1.1 This is a regular report to this Committee on the forecast outturn against budget for the Customer & Communities’ portfolio.
2. Background 2.1 Policy Overview and Scrutiny Committees (POSCs) consider priorities for the Medium Term Plan (MTP) at their November meetings and the draft MTP and annual budget at their January meetings. Two reports are presented to the Committee on a regular basis to inform discussions:
a) Budget Monitoring Reports Quarterly budget monitoring reports are presented to Cabinet usually in September, December and March. The Customer & Communities’ annex to these reports is reported to the POSC at the earliest opportunity and keeps Members informed about current trends, pressures and management actions in advance of budget setting. In the intervening months, an exception report is presented.
The approved A-Z of budgets has been realigned for the first quarter's budget monitoring to reflect the new portfolio responsibilities and new directorate structures to give a new starting point for the year.
b) Outturn Report The outturn report in July summarises financial and performance information for the preceding year.
3 Quarterly Monitoring Report 3.1 Attached is the full monitoring report for the third quarter in 2011-12 which reflects the latest forecast outturn position based on December’s actual spend to date.
The salient points from this report are highlighted below, together with any movement from the position reported at the January meeting which was based on the forecast outturn as at September. 3.2 Revenue 3.2.1 Members were informed in the January meeting’s papers that the directorate was forecasting a net overspend of £0.13m, a favourable movement of £0.29m when compared to the £0.42m pressure reported at the November meeting.
3.2.2 At the meeting, members were informed (orally) that the latest exception report – which had not been presented to Cabinet when papers were distributed – showed a much improved position of a £373k underspend. Services had reviewed their expenditure and curtailed non-essential spend in line with senior management instruction.
3.2.3 In the latest report to Cabinet, I am pleased to report the directorate has been able to increase the forecast underspend and is now reporting an estimated underspend of £5.05m, a movement of £5.18m.
3.2.4 The majority of this movement relates to delay in the launch of the two Big Society programme themes, from Quarter 4 in 2011/12 to Quarter 1 in 2012/13, which alone accounts for £4m.
The remainder (£1.18m) of the movement is outlined below and is as a result of further acceleration of 2012/13 savings, curtailment of non-essential spend and re-profiling of expenditure.
3.2.5 The key movements in the directorate’s position are outlined below:
Big Society: £0m to -£4.00m: a movement of -£4.00m • The Big Society Fund has two themes, the first to encourage Youth Employment, with the second to establish a loan fund to encourage and support social enterprises.
• A sum of £2m had been set aside to pump prime the Kent Employment Programme to encourage businesses to recruit long-term unemployed young people. The project will launch at the turn of the year with the majority of the budget to be spent in 2012/13, which has been re-phased accordingly.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Monitoring 2011-12Report | 21 pages | DownloadRead as text |
Follow Customer and Communities Policy Overview and Scrutiny Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2012 | Minutes - 20 January 2011RESOLVED that the minutes of the meeting held on 20 January 2012 are correctly recorded and that they be signed by th... | Decided | Open |
| 21 Mar 2012 | Community Budgets - Gaining TractionRESOLVED that the report and comments made by Members be noted. | Noted | Open |
| 21 Mar 2012 | Transforming the Business - Service Improvement - Customer and CommunitiesRESOLVED that the presentation be noted | Noted | Open |
| 21 Mar 2012 | Youth Service Transformation - verbal updateRESOLVED that the update and the comments made by Members be noted. (Post meeting note: A meeting of the Communities ... | Noted | Open |
| 21 Mar 2012 | Update on the London 2012 Olympic and Paralympic Games including the Kent School GamesRESOLVED that the update and comments made by Members be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.