Current progress with the actions in the draft Freight Action Plan for Kent

Decided Executive 3 papers

Environment, Highways and Waste Cabinet Committee decided this item on Friday 11 May 2012. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

RESOLVED that the progress with the actions in the draft Freight Action Plan for Kent, be endorsed.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Environment, Highways and Waste Cabinet Committee, 4 pages

Summary

This report sets out the progress with current actions from the draft Freight Action Plan for Kent, including the development of a Lorry Watch Scheme, the Government’s recent Sat Nav summit, and the commissioning of a lorry journey planner to sit on the kent.gov.uk website.

Recommendation

Members of the Cabinet Committee are asked to consider and endorse the progress with the actions in the draft Freight Action Plan for Kent. ___________________________________________________________________

1. Introduction

This report sets out to provide an update to Members on the current situation regarding the development of a Freight Action Plan for Kent. The Plan identifies the issues facing the County in relation to road freight, develops a series of objectives and outlines a number of key actions.

Financial implications

The Kent Lorry Watch scheme identified in the plan is currently being developed (see section 4). This has implications for officer time and will form part of a business case for creating the role of a Freight Officer.

3. Bold Steps for Kent and Policy Framework

The action points in the draft Freight Action Plan for Kent contribute towards all three of the key priorities in Bold Steps for Kent.

1. To help the Kent economy grow

The plan recognises the importance of the economic growth of the county and seeks to: • Work with the freight industry to seek ways of keeping goods for business moving efficiently whilst minimising the impact upon our communities • Provide information to the haulage industry to help them plan their journeys

2. To put the citizen in control

The plan identifies the impact that the freight industry has on the community and seeks to involve and empower them by:

• Developing a community Lorry watch initiative • Provide a method of recording problems as they occur • Work with the community and freight industry in raising the awareness of decisions that individuals make when ordering goods

3. To tackle disadvantage

The plan identifies the problems faced by the community and sets out the objectives to:

• Improving air quality • Reducing the instances of lorries becoming stuck • Ensure lorries are kept away from residential areas

4. The Plan

The Freight Action Plan is a strategic plan that identifies the problems faced in Kent caused by the impact of road freight. The document focuses on road haulage because KCC, as the Highway Authority, has the greatest influence on this mode. Further, the majority of community concerns are around HGVs. The Plan identifies the following main issues:

• Operation Stack • Overnight lorry parking • Ensuring HGV traffic uses the strategic road network • Addressing problems caused by lorry traffic in communities • Using KCC’s planning powers to reduce the impact of freight • Encouraging sustainable freight distribution

Within each of the objectives a number of actions have been devised to contribute towards the mitigation of the impacts of road haulage in Kent. An update on some of these is given below.

Kent Lorry Watch

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Current progress with the actions in the draft Freight Action Plan for KentReport 4 pages DownloadRead as text
PDF
Item D5: appendix 1 Freight Action PlanAppendix 33 pages Download
PDF
Item D5: appendix 2: E I AAppendix 11 pages Download

At this meeting

Whole meeting

More from Kent Environment, Highways and Waste Cabinet Committee

All decisions
MeetingDecisionOutcome
21 Jan 2014 Minutes of the meeting on 13 December 2013RESOLVED that:- (a) a clarification note be prepared by [name removed] and circulated to all Members; and (b) the Min... Decided Open
21 Jan 2014 Fee & charges for Highways & Transportation 2014/15 - Decision No 14/00006RESOLVED that, subject to no increase in the fees for Minibus Driver training and reassessment, the proposed adjustme... Noted Open
21 Jan 2014 Budget Consultation and Provisional Local Government Finance SettlementRESOLVED that the feedback from consultation be noted. Noted Open
21 Jan 2014 Environment, Highways & Waste Cabinet Committee Draft Programme of WorkRESOLVED that the draft programme of work for Environment, Highways and Waste, be noted. Noted Open
13 Dec 2013 Meeting Dates 2014RESOLVED that the following dates for meetings of the Cabinet Committee in 2014, commencing at 10.00am, be agreed:- T... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies