Application TM/12/983 (KCC/TM/0075/2012) - Aggregate Recycling Facility and Concrete Batching Plant, together with amendments to the currently approved quarry restoration plans at Ham Hill Quarry, Snodland; Tarmac Ltd
ApprovedPlanning1 paper
Planning Applications Committee approved this item on Tuesday 6 November 2012. Below is the council's own wording, with the papers it was decided on.
RESOLVED that:- (a) permission be granted to the application subject conditions, including conditions covering a 5 year implementation period; the development being carried out in accordance with the permitted details; a limit of 100,000 tonnes per annum being stored and processed within the aggregate recycling facility; a limit of 30,000 cubic metres of concrete production per annum associated with the concrete batching plant; details/specification of the acoustic fence being submitted for approval; erection of the acoustic fence prior to the commencement of development and its maintenance in perpetuity for the life of the permitted operations; ecological mitigation being implemented (as detailed in the application) when constructing the acoustic fence; day-time noise from site operations being limited to 55 dB LAeq , 1 hr; night-time working being permitted for a trial period of two years with night-time noise from site operations being limited to 50 dB LAmax ; all vehicles on site using broadband reversing alarms during night-time periods; no audible tanoy /PA system being used during night-time periods; a scheme of noise ... view the full minutes text for item 61.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Planning Applications Committee, 41 pages
SECTION C MINERALS AND WASTE DISPOSAL
Background Documents – the deposited documents, views and representations received as referred to in the reports and included in the development proposals dossier for each case also as might be additionally indicated. Item C1 Aggregate recycling facility, concrete batching plant and amendments to quarry restoration provisions at Ham Hill Quarry, Snodland – TM/12/983 (KCC/TM/0075/2012)
A report by Head of Planning Applications Group to Planning Applications Committee on 6 November 2012.
Application by Tarmac Limited for an aggregate recycling facility and concrete batching plant, together with amendments to the currently approved quarry restoration provisions at Ham Hill Quarry, Snodland – TM/12/983 (KCC/TM/0075/2012).
Recommendation: Planning permission be granted, subject to conditions.
Local Member: [name removed]: Unrestricted
Site Description and Background
1. Ham Hill Quarry lies on the western side of the Medway Valley immediately to the southwest of Snodland and 8km northwest of Maidstone (see “Site Location Plan” page C1.2). It is accessed via Hays Road, a private cul-de-sac servicing Tarmac’s depot operated by its National Contracting business, Tarmac’s existing asphalt plant and a Tesco distribution centre, which joins the A228 Malling Road some 700 metres south west. Junction 2 of the M2 lies approximately 7.5 kilometres to the north, whilst Junction 4 of the M20 lies some 1.5 kilometres to the south. The site lies just outside and to the east of the North Downs Area of Outstanding Natural Beauty.
2. Ham Hill Quarry hosts a number of uses, including mineral workings with associated restored and undisturbed areas and soil storage; an asphalt plant producing coated road stone; the storage of asphalt road planings and a depot for Tarmac’s National Contracting business. Public footpath (MR75A) runs through part of the restored quarry site leading from Hollow Lane past the National Contracting Depot, asphalt plant, vehicular site entrance and south-west onto Sandy Lane. Overhead power lines pass across the north-eastern corner of the site and the Pluto Oil pipeline lies underground, transversing the western and northern boundary’s of the site.
3. Mineral extraction commenced at Ham Hill during the 1960s, with a planning permission granted to extract silica sand in 1962 (reference MK/4/62/281). This permission established the site as a sand quarry, required progressive restoration to agriculture and made provision for a dedicated access joining the highway at the southern end of Hollow Lane. An extension to the quarry was granted in 1985 (reference TM/85/8) which allowed additional mineral to be extracted into the area now subject to this application. Temporary planning permission was granted for an asphalt plant at the site in 1985 (reference TM/85/9) which required the plant to be removed once the adjoining sand quarry reserves were fully extracted. Planning permission TM/85/8 was varied in 1999 enabling the importation of asphalt road planings from local road maintenance and storage of up to 5000 tonnes within a defined 1000 square metre area. This variation did not allow for any treatment or processing of road planings and was required to cease upon completion of mineral extraction.
C1.1 Item C1 Aggregate recycling facility, concrete batching plant and amendments to restoration provisions at Ham Hill Quarry, Snodland – TM/12/983
Site Location Plan
Ham Hill Quarry Hays Road (shown dashed)
Tesco Distribution Centre
Ham Hill Roundabout
A228
M20 Junction 4
Figure 1 – Site Location Plan Produced using KentView by initials on Tuesday, 19 June 2012 at 08:26
Application TM/12/983 (KCC/TM/0075/2012): Aggregate Recycling Facility and Concrete Batching Plant, together with amendments to the currently approved quarry restoration plans at Ham Hill Quarry, Snodland; Tarmac LtdPlan
61Application TM/12/983 (KCC/TM/0075/2012) - Aggregate Recycling Facility and Concrete Batching Plant, together with amendments to the currently approved quarry restoration plans at Ham Hill Quarry, Snodland; Tarmac LtdThis decision
Application TM/12/983 (KCC/TM/0075/2012) - Aggregate Recycling Facility and Concrete Batching Plant, together with amendments to the currently approved quarry restoration plans at Ham Hill Quarry, Snodland; Tarmac LtdThis decision
Minutes of the Meeting Held on 17.6.2026RESOLVED that the minutes of the meeting held on 17 June 2026 were correctly recorded and that they be signed by the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.