Resolved
RESOLVED that the report be noted.
Environment, Highways and Waste Cabinet Committee noted this item on Thursday 15 November 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the report be noted.
Decision No 12/01935
From: Bryan Sweetland, Cabinet Member – Environment, Highways & Waste John Burr, Director of Highways & Transportation
To: Environment, Highways & Waste Cabinet Committee
Date: 15 November 2012
Subject: Technical & Environmental Service Contract (TESC) update
Classification: Unrestricted
Summary: This paper is the latest Member update on the TESC procurement process and follows on from previous Policy Overview and Scrutiny Committee (POSC) updates, Informal Members Group (IMG) discussions and a paper to the Environment, Highways and Waste (EHW) Cabinet Committee in September.
Recommendations: Members are asked to note the recent procurement progress and next steps that will identify the preferred bidder leading to the award of the new contract.
1. Introduction
A previous update paper was submitted to the EHW Cabinet Committee on 20 September 2012, explaining how the now decommissioned Policy Overview and Scrutiny Committee (POSC) decided on 14 March 2012 not to extend the current Jacobs contract beyond 31 March 2013. The paper of 20 September outlined the procurement timeline and progress to date. The EHW Cabinet Committee agreed that a robust procurement process continues to progress.
2. The “Paw-Print” Model
As previously explained, the Paw-Print detailed below, is used to illustrate how the Technical and Environmental Services Contract (TESC) will be comprised of a Core Services contract for the majority of the professional services, with some smaller specialist contracts (“toes”) and internalised services. The Paw-Print approach gives better flexibility in the procurement of services and greater choices without significant additional procurement costs.
The core represents about 80% of the contract value. The “toes” represent three smaller specialist contracts and internalisation as listed below: 1. Road Condition Surveys 2. Materials Testing and Coring 3. Waste Management 4. Internalisation of various H&T functions (including Arboriculture and Structures).
3. Recent Progress Core Contract
1. Pre-Qualification: An Official Journal of the European Union (OJEU) notice and Pre Qualification Questionnaire (PQQ) were published on 13 July 2012. The closing date for bidders to return PQQ’s was 22 August 2012. The completed PQQ’s were then evaluated and the following five companies were invited to submit a full tender – AECOM, Amey, Atkins, Capita Symonds, Parsons Brinckerhoff.
2. Invitation to Tender (ITT): On 24 September 2012, an Invitation to Tender (ITT) was issued to the five shortlisted bidders and the unsuccessful applicants were notified. The five bidders have until the close of play on 6 November 2012 to submit their final tenders. As a part of this process, a Bidders Day was held on 11 October where the potential providers met KCC representatives (Officers and Members) to discuss the TESC requirements in more detail. The Elected Members panel of David Brazier and Roy Bullock both agreed that this was a useful and informative event.
4. Next Steps Core Contract 1. Bidders Presentations: Presentations take place on 20 November and a small group of Members will be asked to sit on the assessment panel which scores the bidders based on their presentation and subsequent question and answer sessions.
2. Preferred Bidder Identified: By the end of November, the preferred bidder will be identified and a report prepared for the Commissioning and Procurement Board. The Board will meet on 12 December where they will be informed of the preferred bidder. There will then be a mandatory standstill period of at least ten calendar days (this is a requirement for all contracts tendered via the OJEU) before the Corporate Director; Enterprise & Environment signs off the award of contract.
3. Mobilisation: Mobilisation must have commenced by early January 2013 to allow both KCC and the new provider sufficient time to start the new contract on 1 April 2013.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Technical & Environmental Services Contract (TESC): Decision No.12/01935Decisions | 3 pages | DownloadRead as text |
Follow Environment, Highways and Waste Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Jan 2014 | Minutes of the meeting on 13 December 2013RESOLVED that:- (a) a clarification note be prepared by [name removed] and circulated to all Members; and (b) the Min... | Decided | Open |
| 21 Jan 2014 | Fee & charges for Highways & Transportation 2014/15 - Decision No 14/00006RESOLVED that, subject to no increase in the fees for Minibus Driver training and reassessment, the proposed adjustme... | Noted | Open |
| 21 Jan 2014 | Budget Consultation and Provisional Local Government Finance SettlementRESOLVED that the feedback from consultation be noted. | Noted | Open |
| 21 Jan 2014 | Environment, Highways & Waste Cabinet Committee Draft Programme of WorkRESOLVED that the draft programme of work for Environment, Highways and Waste, be noted. | Noted | Open |
| 13 Dec 2013 | Meeting Dates 2014RESOLVED that the following dates for meetings of the Cabinet Committee in 2014, commencing at 10.00am, be agreed:- T... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.