Resolved
RESOLVED that the minutes of the meeting held on 23 July 2012 are correctly recorded and that they be signed by the Chairman.
Kent Flood Risk and Water Management Committee decided this item on Monday 19 November 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the minutes of the meeting held on 23 July 2012 are correctly recorded and that they be signed by the Chairman.
KENT COUNTY COUNCIL
KENT FLOOD RISK MANAGEMENT COMMITTEE MINUTES of a meeting of the Kent Flood Risk Management Committee held in the Romney Marsh Internal Drainage Board, New Hall, New Hall Close, Dymchurch, Kent TN29 0LF on Monday, 23 July 2012.
PRESENT: [name removed] (Chairman), [name removed], [name removed], [name removed], [name removed] and [name removed]: [name removed] (Ashford BC), [name removed] (Tonbridge and Malling BC), [name removed] (Sevenoaks DC) and [name removed] (River Stour IDB)
IN ATTENDANCE: [name removed] (Senior Emergency Planning Officer), [name removed] (Emergency Planning Assistant), [name removed] (Environment Agency), [name removed] (Romney Marsh IDB), [name removed] (Romney Marsh IDB) (Assistant Engineer) and [name removed] (Democratic Services Officer)
UNRESTRICTED ITEMS
7. Minutes of the meeting on 16 March 2012 (Item 3)
(1) With reference to Minute 2 (6), the Committee accepted [name removed] offer to contact the Environment Agency in order to provide an indicative priority ranking for Flood Defence Grants.
(2) RESOLVED that the Minutes of the meeting held on 16 March 2012 are correctly recorded and that they be signed by the Chairman.
8. Local Flood Risk Management Strategy (Item 4)
(1) [name removed] introduced the report. He said that work on the production of the draft Local Flood Risk Management Strategy was well underway, having been discussed in detail at the last meeting of the Kent Flood Partnership.
(2) [name removed] continued by saying that the Strategy would be an overarching, holistic document. The aim of those preparing the document was that it should be as pragmatic as possible whilst ensuring that all the various agencies worked effectively together.
(3) [name removed] asked to what extent the Committee could be held to account if the aims of the Strategy were not achieved. [name removed] replied that the responsibilities of the Lead Flood Authority were set out in the Flood and Water Management Act 2010. In terms of liability, the legal test would be “reasonableness”, as it was for all local government functions.
5 (4) [name removed] agreed that it would be wise not to proceed with a very detailed draft. He believed that the review period should be two years rather than the three envisaged. He also asked for the inclusion of the total number of organisations affected by Water Legislation. [name removed] replied that the Kent Flood Partnership had discussed similar concerns. He suggested that a “light touch” bi-annual review would be appropriate and agreed that the roles and responsibilities of key partners would be factored in to the Strategy.
(5) The Committee agreed that it would have sight of the Strategy before publication. It was agreed that the most appropriate approach would be for its Members to be sent an electronic version beforehand so that they could comment. In the event that Members had more fundamental concerns, there might need to be a special meeting of the Committee to consider the matter.
(6) The Chairman asked that any Member who, on receipt of the pre-publication draft, wished for a special meeting of the Committee to contact him at the earliest opportunity.
(7) RESOLVED that:-
(a) the report be noted; and
(b) a pre-publication draft of the Draft Local Flood Risk Management Strategy be circulated electronically at the earliest opportunity to all Members of the Committee in order to enable them to comment upon it and, if necessary, for a special meeting to be arranged before publication.
9. Presentation from the Environment Agency (Item 5)
(1) Members of the Committee had visited the flood defences at Robertsbridge before the meeting (including an exercise with the flood alleviation scheme in partial operation). This had been followed by a visit to the Woodside Pumping Station, which was in the process of being repaired.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the meeting on 23 July 2012Minutes | 5 pages | DownloadRead as text |
Follow Kent Flood Risk and Water Management Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Jun 2026 | Minutes of the meeting on 04.03.26RESOLVED that the minutes of the meeting held on 4 March 2026 were an accurate record and that they be signed by the ... | Decided | Open |
| 4 Mar 2026 | Minutes of the meeting on 29.10.2025RESOLVED that the minutes of the meeting held on 29 October 2025 were an accurate record and that they be signed by t... | Decided | Open |
| 4 Mar 2026 | KCC Severe Weather Response Activity ReportRESOLVED to note the verbal update on | Noted | Open |
| 4 Mar 2026 | Met Office- Introduction PresentationRESOLVED to note the Met Office Presentation | Noted | Open |
| 4 Mar 2026 | SGN - Introduction and Water Ingress into the Gas Network PresentationRESOLVED to note the Southern Gas Network (SGN) presentation | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.