Kent County Council
Policy and Resources Cabinet Committee, Tuesday 8 January 2013 at 10.00am

Enterprise Resource Planning Programme

Agreed Executive 1 paper

Policy and Resources Cabinet Committee agreed this item on Tuesday 8 January 2013. Below is the council's own wording, with the papers it was decided on.

Item74

Resolved

It was agreed that members of the Committee would be supplied with information about the recommendations from the LEAN-type review of the HR service including any recommendations that had not been implemented with the reasons. (3) RESOLVED that the progress to date on the phase 2 work streams for the Enterprise Resource Planning Programme and the comments made by Members be noted.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Policy and Resources Cabinet Committee, 4 pages

From: Roger Gough, Cabinet Member for Business Strategy, Performance and Health Reform

David Cockburn, Corporate Director for Business Strategy and Support

To: Policy and Resources Cabinet Committee

Date: 8 January 2013

Subject: Enterprise Resource Planning Programme

Classification: Unrestricted.

Summary: This report provides an update on the first phase of the Enterprise Resource Planning (ERP) programme and highlights the scope of phase two. ERP is a KCC wide programme that is changing the way KCC does “business” and as such affects all KCC staff and Members. The majority of the development is in Oracle, with the aim of maximising the return on the significant investment that KCC has made in Oracle products over the past decade. Simplifying the standard business processes and tools has already supported savings in Finance and HR and will enable further savings and efficiencies to be delivered.

Recommendation: The P&R Cabinet Committee is asked to note and comment on progress to date and the phase 2 work streams

1. Introduction

1 (1) The Enterprise Resource Planning (ERP) Programme is a series of work streams, broken down over two phases that is transforming the way business is conducted within KCC. The aim of the programme is to pull together all of the data sources that currently support staffing and budgetary control and deliver an accurate, single version of finance and HR information using Oracle; and to simplify, improve and make consistent our purchasing processes, again using Oracle. The programme will also address how we develop our business intelligence including integration through Oracle of performance measurement / activity with finance and HR information, to enable better, more informed decisions. 2 Phase 1 improvements

2(1) The ERP programme is complex and covers a number of areas. It is being delivered in two phases, with phase 1 progress highlighted in paragraphs 2(2) to 2(12) below:

2(2) Prior to the ERP programme, HR had already delivered a major programme of implementing employee and manager self-service and has to date, successfully introduced on-line total contribution pay, travel expenses, sickness recording, updating personal information such as change bank details, and facilities to print and view payslips and P60’s. These developments have delivered significant back-office savings.

2(3) ERP has continued to build on this work and further self-service is now available, with employees able to make claims on-line for all payments e.g. additional hours

2(4) A LEAN-type review of the HR Service has been carried out and the Section is currently implementing several of the recommendations.

2(5) A new system (Collaborative Planning) has been introduced which simplifies, makes consistent and automates the budget monitoring process. This has been rolled-out to about 60% of budget managers. It provides on-line forecasting/profiling of spend by budget managers and provides senior managers with comprehensive and transparent financial information about their Services.

2(6) The implementation of a solution to control the financial monitoring and budgeting process was originally scheduled for phase 2 of the programme but was brought forward in order to support the significant reduction in finance staff from April 2012. .

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enterprise Resource Planning ProgrammeReport 4 pages DownloadRead as text

More from Kent Policy and Resources Cabinet Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Minutes of the meeting held on 6 May 2026RESOLVED that the minutes of the meeting held on 6 May 2026 were a correct record and that they be signed by the Chai... Decided Open
2 Jul 2026 Local Outcomes FrameworkRESOLVED that the report be noted. Noted Open
2 Jul 2026 Budget Planning Process 2027-28 and Medium-Term Financial Plan (MTFP) UpdateRESOLVED that the report be noted. Noted Open
2 Jul 2026 26/00032 - Adoption of the KCC Winning for Kent: Procurement with Purpose Policy 2026-2028RESOLVED that the Cabinet Committee endorses the proposed decision to: (a) Approve the adoption and implementation of... Approved Open
2 Jul 2026 Work ProgrammeRESOLVED that the work programme be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies