Quarter 2 Performance Management Report

Agreed Committee 1 paper

Supporting People In Kent Commissioning Body agreed this item on Wednesday 23 January 2013. Below is the council's own wording, with the papers it was decided on.

Item60

Resolved

Agreed thatthe report be noted.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Supporting People In Kent Commissioning Body, 6 pages

Recommendation No

By: Angela Slaven, Customer and Communities Directorate, Director - Service Improvement

To: Supporting People Commissioning Body, 23 January 2013

Subject: Quarter 2 Performance Management

Classification: Unrestricted

Summary This report highlights the aspects of performance management within the Supporting People programme. Targets for the key performance indicators have been missed in quarter 2, though a greater number of people have achieved independent living than in the previous quarter. The programme has funded 8955 contracted household units relating to community alarms. Its HIA services has supported 2176 vulnerable people to Housing related support services have been delivered to over 9802 vulnerable people within sheltered, supported and floating support services.

1. Introduction

(1) This report contains performance information relating Quarter 2 of 2012/13.

(2) Data is provided on the revised targets agreed by the Commissioning Body for Key Performance Indicators 1 and 2 in 2012/13.

2. Context

(1) An analysis of the currently commissioned services and the cost is supplied in Appendix 1.

(2) Quarter 2 covers the period of preparation for the mobilisation of the newly commissioned floating support services.

3. Key Features (1) Since the last report the providers’ achievements are as follows:-

• Providers of sheltered, supported accommodation and floating support services have supported just over 9,800 people towards attaining or maintaining independence during quarter 2. • The number of people who achieved independence has increased substantially from 501 in quarter 1 to 892 in quarter 2 (Appendix 3) • The number of people who moved from temporary living arrangements also increased from 335 in quarter 1 to 409 in quarter 2. (Appendix 3)

(2) The revised key performance indicator target of 98.2% for Long Term Accommodation and Floating support (KPI1) has been missed (Appendix 2)

(3) The revised key performance indicator target of 80% set for short term services (KPI2) has also been narrowly missed. (Appendix 2)

(4) The fall in reported performance is in part due to data cleansing conducted by the Commissioned Service Team to improve future reporting. Commissioned Services have run four free training events in December for providers in order that data quality is improved. It is anticipated that this will result in more accurate performance reporting in the future.

4. Conclusion (1) A greater number of people in sheltered housing, floating support and supported accommodation have achieved and maintained independence. However, the targets for both Key Performance Indicators 1 and 2, which relate to the overall proportion of people attaining and maintaining independence, have been missed.

(2) Commissioned services are running free training events in December for all providers to improve the quality of data that this reported.

Recommendations;

The Commissioning Body is asked to:

1. Note the report

Background Documents None

Melanie Anthony Commissioning and Development Manager 01622 694937 [email protected]

Helen Groombridge Business Analyst 01622 694102 Appendix 1 Contractual Information Appendix 2 Key Performance Indicators Appendix 3 Destination data - Quarter 2 (Jul-Oct 2012) Appendix 1 Contractual Information

Contracted Service Type £ Units Community Alarms 414,591 8955 Extra Care 128,940 254 Floating Support Service 5,766,910 1942 HIA 1,133,507 3243* Long Term Accommodation 4,430,028 550 Sheltered Housing 2,792,873 5695 Short Term Accommodation 10,604451 1126 Total Contracted £25,271,300 21,126 As at Sept 2012

* definition of “unit” in HIA services is subject to variation Appendix 2 Key Performance Indicators

Key Performance Indicator 1 Quarter 2 (July- October 2012)

(1) The programme has missed its revised overall target of 98.2% against Key Performance Indicator 1 (KPI1) in quarter 2 (July-October) of 2012/2013 (Figure 1)

Figure 1 Key Performance indicator 1 – Achieving or maintaining independence Target 98.2%

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarter 2 Performance Management ReportReport 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. Quarter 2 Performance Management ReportThis decision
  2. Quarterly Performance Report, Q1 2026-2027Agreed
  3. Quarterly Performance Report - Year End 2025/26Decided
  4. Public Health Performance Dashboard for Quarter 3Noted
  5. Quarterly Performance Report, Quarter 2, 2025/26Agreed
  6. Commercial and Procurement Performance Report (Quarter 1 and Quarter 2, 2025/2026)Noted

More from Kent Supporting People In Kent Commissioning Body

All decisions
MeetingDecisionOutcome
1 Apr 2015 Minutes of meeting held on 27 January 2015Agreed that the minutes of the previous meeting held on 27 January 2015 be confirmed and were signed by the Chairman. Agreed Open
1 Apr 2015 Future Consultation Arrangements for Housing Related SupportAgreed that: · A recommendation be made to the Cabinet Member for Adult Social Care and Health that the commissioning... Agreed Open
27 Jan 2015 Minutes of meeting held on 7 October 2014Agreed that the minutes of the meeting held on 7 October 2014 be approved as a correct record and were signed by the ... Agreed Open
7 Oct 2014 Minutes of meeting of the Commissioning Body held on 22 July 2014Agreed that the minutes of the meeting held on 22 July 2014 be approved as a correct record and signed by the Chairman. Agreed Open
7 Oct 2014 Minutes of the Core Strategy Group held on 1 September 2014Agreed that the minutes of the Core Strategy Group Workshop held on 1 September 2014 be noted. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies