Proposal SE/13/132 (KCC/SE/0439/2012) - Demolition of existing swimming pool and erection of a new building to accommodate 3 additional classrooms with associated welfare facilities and extension to existing school hall at Otford Primary School, High Street, Otford; KCC Property and Infrastructure
DecidedPlanning2 papers
Planning Applications Committee decided this item on Wednesday 10 April 2013. Below is the council's own wording, with the papers it was decided on.
RESOLVED that permission be granted to the proposal subject to conditions, including conditions covering the standard time limit; the development being carried out in accordance with the permitted details; the submission of details of all materials to be used externally; details of all external lighting; details of an archaeological watching brief; the submission of a scheme for the disposal of foul and surface waters; land contamination; the submission of a revised School Travel Plan within 6 months of the date of this permission, with initiatives to be developed in liaison with the Parish Council and its Parish Plan Team, and targets for its implementation and ongoing review; tree protection measures; hours of working during construction and demolition being restricted to between 0800 and 1800 on Mondays to Fridays and between the hours of 0900 and 1300 on Saturdays, with no operations on Sundays and Bank Holidays; a construction management plan, including the provision of access, parking and circulation within the site for contractor’s and other vehicles related to construction and demolition operations; details of the use of Warham Road; local consultation on the management of the site access to avoid peak school times; pre- construction and post-construction road condition surveys, and the making good of any damage; and measures to prevent mud and debris being taken onto the public highway.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Planning Applications Committee, 34 pages
SECTION D DEVELOPMENT TO BE CARRIED OUT BY THE COUNTY COUNCIL Background Documents: the deposited documents; views and representations received as referred to in the reports and included in the development proposals dossier for each case; and other documents as might be additionally indicated. Item D1 Demolition of existing swimming pool building and erection erection of a new building to accommodate three additional classrooms at Otford Primary School, High Street, Otford – SE/13/488 (KCC/SE/0439/2012)
A report by Head of Planning Applications Group to Planning Applications Committee on 10 April 2013.
Application by Kent Council Children Property & Infrastructure Support for the demolition of existing swimming pool building and erection of a new building to accommodate three additional classrooms, with associated welfare facilities, and an extension to the school hall, at Otford Primary School, High Street, Otford, Sevenoaks – SE/13/488.
Recommendation: permission be granted subject to conditions.
Local Member: [name removed]: Unrestricted
Members’ Site Visit
1. A group of Planning Application Committee Members visited the application site on the 27 March 2013 to acquaint themselves with the proposals and the issues they raise. See notes in Appendix 1.
Site Description
2. Otford Primary School is located within the centre of Otford village, accessed via the High Street, the main road through the village centre which links the A225 Sevenoaks Road to the east with the A224 London Road to the west. Otford lies approximately 2 miles to the north of Sevenoaks, separated from the town by open countryside, which is intersected by the M26. The centre of the village of Otford is a designated Conservation Area, the boundary of which runs through the school site and immediately to the east of the application site (the application site is not within the Conservation Area). The school playing fields are designated as Metropolitan Green Belt and the whole of the school site is within the Kent Downs Area of Outstanding Natural Beauty. A number of Listed Buildings surround the site.
3. The school site comprises two main single storey buildings, one of traditional brick construction built c1890 located on the site frontage on the High Street, and the other being a 1970’s system build (SEAC), located to the south of the original school building and its associated playground. Two modular classroom units are also located on site, accommodating four additional classrooms in total. A timber frame detached building also provides a single classroom for the school, and an additional room and outdoor play area which accommodates a private pre-school nursery. Playing fields extend to the south west of the site, beyond which lie open countryside. To the immediate south of the 1970s classroom building residential houses in Warham Road back onto the school site.
D1.1 Item D1 Demolition of existing swimming pool building and erection of a new building to accommodate three additional classrooms at Otford Primary School, High Street, Otford – SE/13/488 (KCC/SE/0439/2012)
D1.2 Item D1 Demolition of existing swimming pool building and erection of a new building to accommodate three additional classrooms at Otford Primary School, High Street, Otford – SE/13/488 (KCC/SE/0439/2012)
Existing Site Plan
D1.3 Item D1 Demolition of existing swimming pool building and erection of a new building to accommodate three additional classrooms at Otford Primary School, High Street, Otford – SE/13/488 (KCC/SE/0439/2012)
Proposed Site Plan
D1.4 Item D1 Demolition of existing swimming pool building and erection of a new building to accommodate three additional classrooms at Otford Primary School, High Street, Otford – SE/13/488 (KCC/SE/0439/2012)
Proposed Ground Floor Layout Plans
D1.5 Item D1 Demolition of existing swimming pool building and erection of a new building to accommodate three additional classrooms at Otford Primary School, High Street, Otford – SE/13/488 (KCC/SE/0439/2012)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Proposal SE/13/132 (KCC/SE/0439/2012): Demolition of existing swimming pool and erection of a new building to accommodate 3 additional classrooms with associated welfare facilities and extension to existing school hall at Otford Primary School, High Street, Otford; KCC Property and Infrastructure PReport
27Proposal SE/13/132 (KCC/SE/0439/2012) - Demolition of existing swimming pool and erection of a new building to accommodate 3 additional classrooms with associated welfare facilities and extension to existing school hall at Otford Primary School, High Street, Otford; KCC Property and InfrastructureThis decision
Proposal SE/13/132 (KCC/SE/0439/2012) - Demolition of existing swimming pool and erection of a new building to accommodate 3 additional classrooms with associated welfare facilities and extension to existing school hall at Otford Primary School, High Street, Otford; KCC Property and InfrastructureThis decision
Minutes of the Meeting Held on 17.6.2026RESOLVED that the minutes of the meeting held on 17 June 2026 were correctly recorded and that they be signed by the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.