RESOLVED (a) That the Better Care Fund Plan be agreed and endorsed for submission to NHS England subject to no objections being received to the proposed re-wording of the public health elements that was to be circulated. (b) That the clear commitment to closer integration across health and social care and the radical transformation evident in the Plan be endorsed resulting in the citizens of Kent being able to expect: • Better access – co-designed integrated teams working 24/7 around GP practices • Increased independence – supported by agencies working together • More control – empowerment for citizens to self-manage • Improved care at home – 15% reduction for acute admissions and long term care placements, rapid community response particularly for people with dementia • To live and die safely at home – supported by anticipatory care plans • No ... view the full minutes text for item 70.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Kent Health and Wellbeing Board, 3 pages
By: [name removed], Chair Integration Pioneer Steering Group
To: Kent Health and Wellbeing Board, 26 March 2014
Subject: The Better Care Fund
Classification: Unrestricted
Summary: This paper presents the final submission of the Kent Better Care Fund Plan and outlines the steps taken following the assurance process.
Recommendations: The Kent Health and Wellbeing Board is asked to:
1. Agree the BCF plan and endorse submission to NHS England.
2. Endorse the clear commitment to closer integration across health and social care to a programme of clear integration and radical transformation evident within the Bertter Care Fund Plan based upon: ● A 15% reduction of hospital admissions by 2016 ● Availability of services on an extended hours basis ● Integrated commissioning of health and social care ● Continued development of enablement services, telecare/teleheatlh, self care and prevention
3. Note the progress made to meet the areas of development in achieving the final submission.
1. Introduction
1.1The Better Care Fund was announced in June as part of the 2013 Spending Round. Its aim is to act as the enabler to take the integration agenda forward at scale and pace. The development of a Better Care Fund plan is also an integral part of developing the CCG 5 year strategic plans – although must be able to be seen as a stand-alone plan.
1.2The draft submission was presented to the HWB on 12 February prior to first submission, an assurance process has taken place and the final plans will be submitted on 4 April 2014.
1.3The Local Government Association identified at the South East Area Health and Social Care Integration workshop on the Better Care Fund the expectation that by September all areas will be expected to provide clarity on ability deliver and the finance and metrics associated with plans.
2. Outcomes of Assurance
2.1On 6 March a joint letter was provided to CCGs and Social Care outlining the outcomes of the initial assurance. The scope of the Kent plan and the strategic aspirations were noted as ‘encouraging’. Further assurance was sought across a number of areas, the table below summarises these and identifies the steps taken to ensure these have been addressed in the final plan.
Key Development Areas Update
Reflects joint responsibility of health and Agreement and discussion on the metrics social care in design of metrics and via the Integration Pioneer Working Group, delivery of outcomes of plan. plans updated to reflect outcomes.
Confirmation of Section 256 schemes, Clearer outcomes and deliverables have outcome measures and health and social been identified and linked to individual care deliverables. schemes.
Present an east, west and north economy Summary provided within Template Part 1 overview. based on care economies.
Confirmation or planned timetable for Majority of metrics identified and included agreement on metrics and outcome within plans. Missing information to be benefits for health and social care. provided by 4 April submission.
Still some further work based on boundary changes required. Agreement this will be in place by Sept 2014.
Confirmation or planned timetable for Governance arrangements identified within formal governance arrangements. plans, further work may be required up to Sept 2014 on ensuring whole system governance across all care economies.
Confirmation or planned timetable for Assurance mechanisms identified within assurance mechanisms. plans – some further work may be required up to Sept 2014, utilising revised governance arrangements.
Confirmation or planned timetable for Safeguards identified within plans. safeguards of non-delivery.
3. Timetable
3.1Following assurance by the Health and Wellbeing Board the plans will be submitted to NHS England on 4 April alongside CCG Commissioning plans.
3.2Further work will then take place within each care economy to develop detailed implementation plans.
4. Conclusion
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies