Review of the Kent Commissioning Plan for Education 2013-2018

Noted Executive 1 paper

Education and Young People's Services Cabinet Committee noted this item on Wednesday 23 July 2014. Below is the council's own wording, with the papers it was decided on.

Item17

Resolved

RESOLVED that:- a) the responses to Members comments and questions be noted; b) a report be submitted to the September meeting of this Cabinet Committee setting out the future commissioning plans for the next five years; and c) the ... view the full minutes text for item 17.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Education and Young People's Services Cabinet Committee, 21 pages

From: Patrick Leeson, Corporate Director for Education and Young People’s Services

Roger Gough, Cabinet Member for Education and Health Reform

To: Education and Young People’s Services Cabinet Committee – 23 July 2014

Subject: Review of the Kent Commissioning Plan for Education 2013-2018

Classification: Unrestricted

Past Pathway of Paper: Education Cabinet Committee – 27 September 2013

Future Pathway of Paper: Cabinet Member decision

Summary: This report informs Members of the progress made in implementing the Kent Commissioning Plan for Education 2013-2018 since its adoption by Cabinet in October 2013.

Recommendation: The Education and Young People’s Services Cabinet Committee is asked to consider the report and note the progress achieved and the issues identified for further development.

1. Introduction

1.1In September 2013 Kent County Council published the latest Kent Commissioning Plan for Education 2013-2018. This sets out our future plans as strategic commissioner of education provision across all types and phases of education. The Plan is updated annually with progress being monitored six to nine months after publication. This report reviews the progress made since September 2013.

1.3This Review of the Plan, attached as an Appendix, covers the following topics:

• Progress in implementing the expansion of school places; • Review of forecasting accuracy; • Progress against our targets; • Progress in implementing the Review of school places for SEN pupils; • The impact of changes to national School Organisation Regulations.

1.4In summary, this Review demonstrates that:

• Commissioning and implementing the planned number of new school places overall for September 2014 has been successful and that targets have been largely met. Delivery of a small number of projects has been adjusted in response to changing contexts during the year and these are set out in paragraph 2.2 below.

• The re-designation and expansion of Special Schools is on track for September 2014 and 2015, including the relocation and rebuilding of three schools.

• The accuracy of our forecasting methodology has remained close to within 1% of accuracy, although the increase in inward migration into Kent during 2013-14 was greater than in previous years and higher than forecast.

• The increase in the school population has reduced the surplus capacity of school places across the Primary School sector – seven out of the 12 Kent districts are now operating at below 5% surplus capacity. Surplus capacity across the Secondary School sector remains high.

2. Progress in Implementing the Expansion of School Place Numbers

2.1The Plan identified the need, by September 2014, for 15.3 permanent new forms of entry in Primary schools and 3 forms of entry in Secondary schools. To date, 12.2 forms of entry have been commissioned in Primary schools ready for September 2014 and 2.85 permanent new forms of entry in secondary schools in September 2014. This variation in delivering the planned numbers has been due to specific local circumstances including highways and planning issues, standards and availability of schools to expand.

2.2An additional 130 temporary school places for Reception aged pupils have been commissioned in the short term to take account of the reduced provision of permanent places. The Plan identified the need to provide 250 temporary places for short-term pressures for Reception age pupils but at March 2014, 380 temporary places had been commissioned. The reasons for this shift from permanent to temporary places are set out below. Much of this variation is the consequence of unresolved highways and planning issues. Significant local variations include:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Review of the Kent Commissioning Plan for Education 2013-2018Report 21 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. Review of the Kent Commissioning Plan for Education 2013-2018This decision
  2. Kent and Medway Domestic Abuse Related Death Review UpdateNoted
  3. Kent and Medway Domestic Abuse Related Death Reviews Funding Arrangements ReportApproved
  4. Kent Community Safety Partnership Terms of Reference ReviewAgreed
  5. Kent and Medway Domestic Abuse Related Death Review UpdateNoted
  6. Kent Community Safety Agreement Review and RefreshAgreed

More from Kent Education and Young People's Services Cabinet Committee

All decisions
MeetingDecisionOutcome
30 Mar 2017 Minutes of the meetings held on 17 January, 1 February and 7 March 2017Resolved that the minutes of the meetings held on 17January, 1 February and 7 March 2017 are now correctly recorded, ... Decided Open
30 Mar 2017 17/00013 Proposal to expand Deal Parochial CE Primary School, by 1FE, from September 2018RESOLVED – That the Cabinet Committee endorsed the proposed decision of the Cabinet Member for Education and Health R... Approved Open
30 Mar 2017 17/00022 - Proposal to permanently expand Mayfield Grammar School, Gravesend, from a PAN of 145 to 180RESOLVED – That the Cabinet Committee endorsed the proposed decision of the Cabinet Member for Education and Health R... Agreed Open
30 Mar 2017 17/00015 -Proposal to increase the physical capacity of Meadowfield (Foundation Special) School from September 2017RESOLVED that the Cabinet Committee endorsed the proposed decision of the Cabinet Member for Education and Health Ref... Agreed Open
30 Mar 2017 16/00139 Proposal to expand Regis Manor Primary (Academy) School, increasing the capacity from 420 school places to 630 school places and increasing the PAN from 60 to 90 for Year R entry in September 2018RESOLVED – That the Cabinet Committee endorsed the proposed decision of the Cabinet Member for Education and Health R... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies