Resolved
RESOLVED that the award of contracts to the preferred tenderers following the completion of a procurement process for the provision of waste treatment and/or final disposal contract/s be noted.
Growth, Environment & Transport Cabinet Committee noted this item on Wednesday 14 January 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the award of contracts to the preferred tenderers following the completion of a procurement process for the provision of waste treatment and/or final disposal contract/s be noted.
To advise Cabinet Committee of the forthcoming procurement and award of Waste treatment and/or final disposal contract/s in accordance with chosen evaluation, methodology which will be stated in the relevant published Invitation to Tender, and to seek comments from Members.
Recommendation(s):
That the Environment and Transport Cabinet Committee note and comment on Kent County Council awarding contracts to the preferred tenderers following the completion of a procurement process for the provision of Waste treatment and/or final disposal contract/s.
1. Introduction
1.1This report provides information concerning a procurement which will be undertaken by KCC Waste Management to identify providers to receive, process and/or dispose of residual waste (i.e. waste which cannot be recycled or composted) which is either unsuitable for the Allington Energy from Waste (EfW) plant, or which is diverted from Allington during periods of shut down due to maintenance.
1.2At present approximately 58,668 tonnes of residual waste per annum is unsuitable for the Allington EfW per virtue of its bulky nature, e.g. mattresses, large hard plastic items etc, and typically a further 43,815 tonnes is diverted over the course of a year due to maintenance of the plant. The new contracts for Household Waste Recycling Centres (HWRCs) and Waste Transfer stations do require the provider to use innovative techniques to ensure that little or no material which can be recycled or composted is left within the mass of such residual waste.
1.3Whilst to date all waste unsuitable for the Allington EfW has been landfilled, it is the aspiration of the Waste Management team to engage with the market to develop solutions which make use of such waste as a resource, and in doing so make a significant stride toward zero waste to landfill. Landfill does, however, remain an option should more innovative solutions prove unaffordable.
1.4The proposed contract/s are required to fulfil the Council’s statutory duty as a Waste Disposal Authority to dispose of residual waste arising from both district council kerbside collection and HWRCs. 1.5 The proposed contract/s would be required to commence in September 2015 for a proposed initial term of five years, which would enable co-termination with existing contracts for the majority of HWRCs and Waste Transfer Stations.
2.1The estimated contract spend by KCC will be approximately £47m over the initial period of five years, with a possible extension of up to a further two years based on performance.
2.2There may be some potential to secure financial savings through these new contracts, depending upon the solution emanating from the market, although such savings are likely to be modest.
3. The Report
3.1The proposed contracts are required to be procured in a manner which is in full compliance with relevant procurement regulations.
3.2A market engagement process will be undertaken to explore ways in which to maximise value and minimise environmental impact, and a transparent and accountable procurement processes will be undertaken to select providers for these services.
3.3KCC has a statutory responsibility as the Waste Disposal Authority for the disposal of household waste and as such the contracts subject to this report are a fundamental requirement to ensure residual waste can be managed cost effectively and via environmentally sound methods.
3.4An Equalities Impact Assessment will be undertaken to ensure that no protected characteristics will be impacted upon either positively or negatively as a result of these contracts. This will take into account the fact that the contracts will be delivering a noncustomer facing service.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
15/00001 Waste treatment and/or final disposal contract/sReport | 3 pages | DownloadRead as text |
PDF |
Procurement PlanAppendix 1 | 8 pages | Download |
PDF |
Proposed Record of DecisionAppendix 2 | 1 pages | Download |
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... | Decided | Open |
| 5 May 2026 | Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... | Decided | Open |
| 5 May 2026 | Winter Service UpdateRESOLVED to note the Winter Service Update . | Noted | Open |
| 5 May 2026 | Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. | Noted | Open |
| 5 May 2026 | 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.