Application DA/14/1259 (KCC/DA/0270/2014) - Operation of an aggregates recycling facility to accept 150k tpa of construction waste including a fixed processing plant to utilise certain fractions of the recovered materials in order to produc
ApprovedPlanning1 paper
Planning Applications Committee approved this item on Wednesday 21 January 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED thatpermission be granted to the application subject to conditions, including conditionscovering a temporary 5year planningpermission; a limit on throughputsto a maximum of 150,000tonnes perannum; h ours ofoperation beingrestricted tobetween thehours of0700 and 17.00 on Mondaysto Fridaysand 0700and 1200 onSaturdays) with noworking on Sundaysor BankHolidays; no morethan 60vehicle movements taking place per operationalday (30in/30out); no more than8 movements(in orout) ofHGVs greaterthan 3.5tonnes taking place between 0745 and 0 845and between1500 and 1600; a ll loads carryingwaste beingcovered; details ofwheel washingfacilities beingsubmitted; details of asurface waterdrainage scheme; nofurther development beingcarried out (without the permission of the County Planning Authority) if (duringdevelopment) contaminationnot previouslyidentified is foundto bepresent at thesite, untilthe developer hassubmitted a remediation strategyto thelocal planningauthority detailinghow thisunsuspected contamination will be dealt with and written approval from the local planning authority for these measures has been obtained.The remediationstrategy is to beimplemented asapproved; mitigation measuresbeing securedas setout insection 8of theecological impact assessmentand drawingnumber 003entitled ‘reptilesafe area’; a restriction of theplant onsite tothat setout inthe planningapplication; the submission for approval of a Traffic Management Plan requiring all traffic associated with the site to keep to the primary route network; and the implementation of the dust control measures specified in Table 7 – 1 of the report.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Planning Applications Committee, 42 pages
SECTION C MINERALS AND WASTE DISPOSAL Background Documents - the deposited documents, views and representations received as referred to in the reports and included in the development proposals dossier for each case and also as might be additionally indicated. Item C1 KCC/DA/0270/2014 (DA/14/1259) – Operation of an aggregates recycling facility to accept 150,000tpa of construction and demolition waste including a fixed processing plant to utilise certain fractions of the recovered materials in order to produce hydraulically bound materials (HBM) at Land to the South of Manor Way, Swanscombe, Kent, DA10 0PP
A report by Head of Planning Applications Group to Planning Applications Committee on 21 January 2015.
This application has been submitted by SLR Consulting on behalf of Sheerness Recycling Ltd for the temporary operation of an aggregates recycling facility to accept 150,000tpa of construction and demolition waste including a fixed processing plant to utilise certain fractions of the recovered materials in order to produce hydraulically bound materials (HBM) at Land to the South of Manor Way, Swanscombe, Kent, DA10 0PP
Recommendation: Permission be granted subject to conditions. Local Member: [name removed] and adjoining Members, [name removed] and [name removed]: Unrestricted
Site Description
1. Planning permission is being sought by Sheerness Recycling Limited (SRL) to use brownfield land at Manor Way Business Park, Swanscombe for a temporary 5 year period to accept construction, demolition and excavation materials from local developments along with crushing and screening, via industry standard processes, into recycled secondary aggregates for re-sale into the local market. The site covers an area of some 2.4 hectares and comprises partly of concreted slabs and areas of other hard-standing. The site has been dormant for several years.
2. The site would also include a fixed processing plant (similar to a small Ready Mixed Concrete batching plant) to utilise certain fractions of the recovered materials in order to produce hydraulically bound materials (HBM) for sale into the local market.
3. A temporary short-term lease of the site has been agreed between the applicant and landowners, (Lafarge) who wish to retain the option to re-lease land as may be required, for future redevelopment of the area. Lafarge are landowners of a significant proportion of the Swanscombe Peninsula including the proposed London Paramount Leisure Resort Site (LPRS). A short term lease arrangement with SRL would therefore ensure the proposed temporary development would not compromise the LPRS scheme. The landowners and applicants lease arrangement is subject to renewal in the event that the LPRS scheme is either delayed or indeed does not go ahead.
C1.1 Item C1 KCC/DA/0270/2014 (DA/14/1259) – Operation of an aggregates recycling facility to accept 150,000tpa of construction and demolition waste including a fixed processing plant to utilise certain fractions of the recovered materials in order to produce hydraulically bound materials (HBM) at Land to the South of Manor Way, Swanscombe, Kent, DA10 0PP
Drawing Number 001: Site Location Plan
C1.2 Item C1 KCC/DA/0270/2014 (DA/14/1259) – Operation of an aggregates recycling facility to accept 150,000tpa of construction and demolition waste including a fixed processing plant to utilise certain fractions of the recovered materials in order to produce hydraulically bound materials (HBM) at Land to the South of Manor Way, Swanscombe, Kent, DA10 0PP
C1.3 Item C1 KCC/DA/0270/2014 (DA/14/1259) – Operation of an aggregates recycling facility to accept 150,000tpa of construction and demolition waste including a fixed processing plant to utilise certain fractions of the recovered materials in order to produce hydraulically bound materials (HBM) at Land to the South of Manor Way, Swanscombe, Kent, DA10 0PP
Planning History
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Application DA/14/1259 (KCC/DA/0270/2014): Operation of an aggregates recycling facility to accept 150k tpa of construction waste including a fixed processing plant to utilise certain fractions of the recovered materials in order to produce hydraulically bound materials (HBM) at Land to the south oReport
4Application DA/14/1259 (KCC/DA/0270/2014) - Operation of an aggregates recycling facility to accept 150k tpa of construction waste including a fixed processing plant to utilise certain fractions of the recovered materials in order to producThis decision
Application DA/14/1259 (KCC/DA/0270/2014) - Operation of an aggregates recycling facility to accept 150k tpa of construction waste including a fixed processing plant to utilise certain fractions of the recovered materials in order to producThis decision
Minutes of the Meeting Held on 17.6.2026RESOLVED that the minutes of the meeting held on 17 June 2026 were correctly recorded and that they be signed by the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.