Resolved
RESOLVED that the outcome of the review and contract award be noted.
Pension Fund Committee noted this item on Friday 28 August 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the outcome of the review and contract award be noted.
Item No C6 By: Chairman Superannuation Fund Committee Corporate Director of Finance and Procurement
To: Superannuation Fund Committee – 28 August 2015
Subject: PENSION FUND CUSTODY SERVICES REVIEW
Classification: Unrestricted
Summary: To update the Committee on the outcome of the custody services review and contract tender FOR INFORMATION
INTRODUCTION
1. At its meeting in August 2014 the Committee was advised that KCC would be undertaking a review of the Pension Fund investments back office function. This review has been completed and, following a procurement process using the LGPS global custody services framework, a contract for custody and accounting services has been awarded to The Northern Trust Company to commence on 2 November 2015.
2. The contract has been issued with a 3 year plus 1+1 year extension periods achieving a significant reduction in future costs compared to the current rate.
SERVICE REVIEW
3. The current value of the Pension Fund is £4.5bn. Custodian services are used for its total segregated funds, which currently stand at £1.9bn. These assets are held by the custodian as the nominee for safekeeping; the custodian also settles all transactions in these assets carried out by the fund managers on our behalf.
4. Currently, Custodian Services are provided by JP Morgan, accounting is undertaken by KCC using the Shareholder system and the WM Company provides performance measurement services. As previously reported to the Committee, this arrangement necessitates separate flows of information, resulting in duplication. This is time consuming, requires several layers of validation, and delays the production of accounting and management information.
5. The review therefore considered the following 2 options:
i) KCC to continue to provide the accounting service and implement an upgraded Shareholder system. Look to transfer all non- Shareholder based recordkeeping onto the upgraded Shareholder and dispense with Excel spreadsheets. Using the LGPS Custody Framework either to continue to use the JPM custody service or engage a new custodian. Continue to use the performance measurement service provided by The WM Company.
ii) Call off the LGPS Custody Framework for one provider of fund custody, accounting and performance measurement services and cease the use of Shareholder and WM other than for league tables.
6. At the outset it was envisaged that option ii) would be pursued due to the advantages it afforded of seamless processes and timely information being available, besides affording staff time to carry out value added functions. Performance measurement services were however left out of the scope of this tender with the option to add to the contract in the future.
PROCUREMENT PROCESS
7. It was agreed to use the LGPS global custody services framework and to invite the 6 banks on the framework to tender for the supply of Custody Services with the option to contract for Accounting Services covering all asset classes of the fund. Quotes were also invited for the Performance Measurement Service for information for future use. These services are included under the National LGPS Global Custody Services Framework.
8. Tenders were received from BNP Paribas Securities Services, BNY Mellon, J.P.Morgan, Northern Trust and State Street. HSBC Securities Services did not tender.
EVALUATION OF TENDER RESPONSES
9. Proposals were evaluated on the following basis:
Weighting Criteria % Quality Offered (Part 1 and 2) 30 Service Fit (Part 1 and 2) 30 Value for Money 40 Total 100
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Custody UpdateReport | 3 pages | DownloadRead as text |
Follow Pension Fund Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jun 2026 | Minutes of the meeting held on 26 March 2026RESOLVED that the minutes of the meeting held on 26 March 2026 were correctly recorded and that they be signed by the... | Decided | Open |
| 23 Jun 2026 | Committee Work Plan and Action LogRESOLVED to note the Committee Work Programme and Action Log. | Noted | Open |
| 23 Jun 2026 | Update from the Pension BoardRESOLVED to note the update. | Noted | Open |
| 23 Jun 2026 | Pensions Administration UpdateRESOLVED to note the report. | Noted | Open |
| 23 Jun 2026 | Fund GovernanceRESOLVED to: a. Delegate responsibility to the Head of Pensions and Treasury to lead the selection process for the In... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.