Folkestone Seafront Regeneration - Local Growth Fund grant

Agreed Executive 1 paper

Growth, Economic Development and Communities Cabinet Committee agreed this item on Tuesday 1 December 2015. Below is the council's own wording, with the papers it was decided on.

Item115

Resolved

RESOLVED that the Cabinet Committee endorsed the decision to be taken by the Cabinet Member for Economic Development to agree the recommendations outlined in the report.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Growth, Economic Development and Communities Cabinet Committee, 9 pages

By: Mark Dance, Cabinet Member for Economic Development

Barbara Cooper, Corporate Director – Growth Environment and Transport

To: Growth, Economic Development and Communities Cabinet Committee - 1 December 2015

Subject: Folkestone Seafront Regeneration: Local Growth Fund Grant

Classification: Unrestricted

Past pathway of paper: None

Future pathway of paper: None

Electoral Division: All Divisions in Shepway (Elham Valley, Folkestone North East, Folkestone South, Folkestone West, Hythe and Romney Marsh)

Summary As part of the South East Local Enterprise Partnership’s Local Growth Fund allocation, the Government has indicatively allocated £5.1 million to deliver capital works in support of the regeneration of Folkestone Seafront. This grant is subject to the completion of a full business case and the confirmation of funding by the Government.

Should the Government confirm its funding, it is proposed that Kent County Council will act as the accountable body for the grant, which it will transfer through a subordinate grant agreement to the developers of the Folkestone Seafront scheme.

This report explains the project for which grant funding is sought, sets out KCC’s role and outlines the process that will be followed to secure the funding. It seeks the support of the Cabinet Committee for KCC to accept Government grant funding and transfer it to the developers, subject to approval of a full business case.

Recommendation: The Growth, Economic Development and Communities Cabinet Committee is asked to consider and endorse or make recommendations on the decision to be taken by the Cabinet Member for Economic Development, to agree that the Council shall (subject to the completion of a full business case, satisfactory appraisal by an Independent Technical Evaluator and approval by the South East Local Enterprise Partnership Accountability Board):

i. Accept Government grant funding of up to £5.1 million capital to deliver a programme of regeneration works at Folkestone Seafront; ii. Enter into a subordinate grant agreement with a private sector organisation for the delivery of the programme; and

iii. Delegate to the Director of Economic Development the authority to conclude arrangements to secure the recovery of administration costs associated with KCC’s management of the grant agreement.

1. Introduction: The Folkestone Seafront project

1.1Folkestone’s prospects for regeneration and growth have been greatly enhanced by improved transport connections via High Speed One and by significant private and public investment in the town’s public realm and cultural infrastructure. Building on this, the redevelopment of Folkestone Seafront will provide a high-quality, mixed use development, consisting of up to 1,000 homes and around 10,000 sq m of commercial floorspace, as well as new sports and leisure facilities and public space.

1.2The spatial strategy for Folkestone Seafront is set out in Shepway District Council’s adopted Core Strategy Local Plan and the project is recognised as a priority investment within the South East Local Enterprise Partnership’s Strategic Economic Plan. Following a master plan developed in 2009, an outline planning application for the development was submitted by Folkestone Harbour Group and was approved in January 20151.

2. Proposal for grant funding

2.1While the development will be largely privately financed, there is a high level of upfront investment required in infrastructure and site preparation works. The Development Viability Assessment completed in November 2014 stated that it would not be possible through normal market channels to raise the funding for this investment.

2.2Last year, Folkestone Harbour Group submitted an expression of interest to the South East LEP for funding from the Government’s Local Growth Fund. This resulted in the following indicative allocation:

2016/17: £4.0 million 2017/18: £1.1 million

Total: £5.1 million

2.3Specifically, it was proposed that this funding would be used for:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Folkestone Seafront Regeneration: Local Growth Fund grantReport 9 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 22 attended
AW
Andrew WickhamChairman, apologies, sent representative
SH
Seán HoldenVice-Chairman in the Chair, present
MB
Mike BaldockSpokesperson, present
AB
Andrew BowlesCommittee Member, present
DB
David BrazierCommittee Member, present
SC
Susan CareyCommittee Member, present
BC
Brian ClarkSpokesperson, present
MC
Margaret CrabtreeCommittee Member, present as substitute
JK
Jeremy Kite, MBECommittee Member, present
GL
Geoff LymerCommittee Member, present
FM
Frank McKennaCommittee Member, present
ER
Eileen RowbothamCommittee Member, present

All 22 on the meeting page

More from Kent Growth, Economic Development and Communities Cabinet Committee

All decisions
MeetingDecisionOutcome
11 Nov 2025 Election of ChairRESOLVED that [name removed] be elected as Chair of the Growth, Economic Development and Communities Cabinet Committee. Decided Open
11 Nov 2025 Minutes of the meeting held on 11 September 2025RESOLVED that the minutes of the meeting held of 11 September 2025 were a correct record and they be signed by the Ch... Decided Open
11 Nov 2025 KMEF- Ambition 2- Widen opportunities and unlock talentRESOLVED to note the report. Noted Open
11 Nov 2025 Regional Energy Strategic PlanRESOLVED to note the report. Noted Open
11 Nov 2025 Decisions taken between Cabinet Committee Meetings- 25/00084It was agreed that consideration would be given to Member involvement in the reinstated Visitor Economy and Inward In... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies