Resolved
RESOLVED that the report be noted.
Pension Board noted this item on Wednesday 20 April 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the report be noted.
By: Corporate Director of Finance & Procurement
To: Pension Board – 20 April 2016
Subject: LOCAL GOVERNMENT PENSION SCHEME POOLING
Classification: Unrestricted
Summary: To update on the LGPS pooling work and seek agreement to proposed project costs.
FOR DECISION
INTRODUCTION
1. This report is to update the Board on progress of the LGPS pooling work. The proposals published by the Government in November 2015 present the most radical changes to the management of the LGPS since it was first established.
LGPS INVESTMENT REFORM CRITERIA AND GUIDANCE
2. The main issues are:
(1) Six “British Wealth Funds” (multi asset pools for the purpose of this report) are to be established each with assets of at least £25bn.
(2) There will be governance arrangements at pool level involving members to oversee the pool investments.
(3) The target date for establishing the pools is 1 April 2018. We envisage that existing mandates would transfer and after that date processes would commence over an extended period to move funds into new mandates.
(4) The paper states that “backstop legislation that would require those administering authorities who do not come forward with sufficiently ambitious proposals to pool their assets with others”. This is a very clear statement of intent from Government, that pooling will happen.
(5) There will be some investments such as close ended funds which will not be included in the pooling arrangements.
(6) Direct Property is excluded and this is a major move from DCLG’s initial position and is the right answer from an investment perspective. (7) The proposals leave all the other responsibilities of this Committee unchanged. This Committee will still decide which assets the Fund invests in and all other issues related to the management of the Fund.
(8) Greater investment in Infrastructure.
3. Initial responses are required by 19 February and full costed responses by 15 July.
POOLING OPTIONS
4. The Superannuation Fund Committee agreed that the Head of Financial Services should participate in discussions with other Funds. The Chairman, the Deputy Leader and Cabinet Member for Finance & Procurement and the Corporate Director of Finance and Procurement have been kept fully informed of these discussions. All discussions have emphasized that decisions on the way forward are for this Committee.
5. Hymans Robertson had already facilitated a working group of around 25 non- London funds including the largest LGPS funds and a number of County Council funds. Project Pool had a formal structure and a number of sub-groups and the Head of Financial Services participated in the high level pooling workstream. A report should be published before the Committee meeting and this will represent the group of Funds views on how pooling can best be implemented.
6. This work showed that Funds are coming at the pooling issue from many directions and with many different objectives. In the Hyman’s work frequent reference was made to the need for Funds to be “like minded” and this will be an issue that we return to.
7. In summary the main findings of the Project Pool work are:
(1) Preferred option multi-asset pools formed by region and like-minded group.
(2) For most asset types, regional pools may give sufficient size to get the majority of scale benefits / fee reductions.
(3) Regional or like-minded groupings also give individual funds more involvement in the governance of pools.
(4) For Infrastructure a national pool may be the best answer.
(5) Savings will be exceeded in the early years by the costs of setting up the pools and then by the potentially very large transaction costs. 8. Whilst the Hymans work concentrated on the “what” of pooling individual Funds seem to move very quickly to the “who”. This is not a helpful emphasis and it is one which reflects the different agendas Funds have. The main groupings to emerge are:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 2: Appendix 1: LGPS PoolingAppendix | 2 pages | Download |
PDF |
Item 2: Appendix 2: Draft ACCESS Pool project overview_July submissionAppendix | 1 pages | Download |
PDF |
Item 2: Appendix 2: LGPS PoolingAppendix | 18 pages | Download |
PDF |
Local Government Pension Scheme (LGPS) PoolingReport | 6 pages | DownloadRead as text |
Follow Pension Board at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Jun 2026 | Election of ChairRESOLVED that [name removed] be elected as Chair of the Pension Board. | Decided | Open |
| 4 Jun 2026 | Minutes of the meeting held on 31 March 2026RESOLVED that the minutes of the meeting held on 31 March 2026 are correctly recorded and they be signed by the Chair... | Decided | Open |
| 4 Jun 2026 | Pension Fund Committee Verbal UpdateRESOLVED to note the verbal update. | Noted | Open |
| 4 Jun 2026 | Pensions AdministrationRESOLVED to note the report. | Noted | Open |
| 4 Jun 2026 | Investments UpdateRESOLVED to note the report. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.