1.1Kent County Council is one of the largest lighting authorities in the UK and has 118,000 street lights and some 25,000 lit signs and bollards
1.2The Authority awarded a 15 year contract to Bouygues E & S Infrastructure UK Ltd where all of its street lights will be converted to Light Emitting Diode (LED) products. Additionally a Central Management System (CMS) will be provided and this will enable complete management of street lighting including dimming, switch on/off, fault reporting, metering, etc.
1.3This conversion works will reduce energy and Carbon Reduction Commitment (CRC) costs by 65% and significantly reduce maintenance costs. The conversion works will cost around £40m and deliver a significant savings annually up to £5.2m.
1.4On the 12 February 2016, it was endorsed by the Environment and Transport Cabinet Committee to return to ‘Optimised’ All Night Lighting. This decision was taken by the Cabinet Member for Environment and Transport on the 4 March 2016 (16/00018).
1.5This paper provides an update on the project and outlines the next steps. 2 Mobilisation Period
2.1The contract was awarded on the 14 December 2015 following a successful procurement process.
2.2The mobilisation period was scheduled to take three months to complete. Working with Bouygues during this period the following tasks were completed:
Programming of the residential phase of the works Product approval of the lanterns to be used within the residential phase Project team recruitment Configuration of ICT systems Setting up of advance works information
3 Programme
3.1The phasing of the programme was a complex matter, with the stipulation that the contractor could only work within three districts at the same time. This would minimise disruption and centralise their operations to allow them to respond to any faults quickly, maximise their installation output and reduce carbon emissions by not driving all over the county.
3.2The contractors appointed for this work are experts within the industry and have taken into consideration a number of factors when programming this work that including the number, type, age and location of assets
3.3The residential programme is to be completed within 14 months and has been scheduled as follows:
Phase 1 – Ashford/Shepway/Dover o March to June 2016 Phase 2 – Gravesham/Dartford/Sevenoaks o June to September 2016 Phase 3 – Maidstone/Tonbridge & Malling/Tunbridge Wells o August to November 2016 Phase 4 – Swale/Canterbury/Thanet o October 2016 to May 2017
3.4It is expected that these dates may change throughout the programme. Any changes will be communicated to stakeholders.
3.5The second part of the project will see LED conversions to the main routes and town centres. This will be completed within 25 months and a programme for this is currently being developed and will be communicated once agreed.
4. Progress
4.1Work commenced in rural areas within the Borough of Ashford on the 14 March 2016. 3,629 lanterns have been converted by 22 April.
4.2The default profile of the lanterns is to operate all night. The Authority is working with Bouygues to scope out the ‘Optimised’ All Night Lighting policy. This will include analysing the assets on a street by street level, as each road has its own design specification which will enable different optimal illumination levels.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
LED Street Light Conversion Project UpdateReport | 3 pages | DownloadRead as text |
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... | Decided | Open |
| 5 May 2026 | Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... | Decided | Open |
| 5 May 2026 | Winter Service UpdateRESOLVED to note the Winter Service Update . | Noted | Open |
| 5 May 2026 | Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. | Noted | Open |
| 5 May 2026 | 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.