Growth, Environment & Transport Cabinet Committee, Wednesday 4 May 2016 at 10.00am

LED Street Light Conversion Project Update

Noted Executive 1 paper

Growth, Environment & Transport Cabinet Committee noted this item on Wednesday 4 May 2016. Below is the council's own wording, with the papers it was decided on.

Item180

Resolved

RESOLVED that the comments and responses to questions by Members and the report be noted.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Growth, Environment & Transport Cabinet Committee, 3 pages

Background

1.1Kent County Council is one of the largest lighting authorities in the UK and has 118,000 street lights and some 25,000 lit signs and bollards

1.2The Authority awarded a 15 year contract to Bouygues E & S Infrastructure UK Ltd where all of its street lights will be converted to Light Emitting Diode (LED) products. Additionally a Central Management System (CMS) will be provided and this will enable complete management of street lighting including dimming, switch on/off, fault reporting, metering, etc.

1.3This conversion works will reduce energy and Carbon Reduction Commitment (CRC) costs by 65% and significantly reduce maintenance costs. The conversion works will cost around £40m and deliver a significant savings annually up to £5.2m.

1.4On the 12 February 2016, it was endorsed by the Environment and Transport Cabinet Committee to return to ‘Optimised’ All Night Lighting. This decision was taken by the Cabinet Member for Environment and Transport on the 4 March 2016 (16/00018).

1.5This paper provides an update on the project and outlines the next steps. 2 Mobilisation Period

2.1The contract was awarded on the 14 December 2015 following a successful procurement process.

2.2The mobilisation period was scheduled to take three months to complete. Working with Bouygues during this period the following tasks were completed:

 Programming of the residential phase of the works  Product approval of the lanterns to be used within the residential phase  Project team recruitment  Configuration of ICT systems  Setting up of advance works information

3 Programme

3.1The phasing of the programme was a complex matter, with the stipulation that the contractor could only work within three districts at the same time. This would minimise disruption and centralise their operations to allow them to respond to any faults quickly, maximise their installation output and reduce carbon emissions by not driving all over the county.

3.2The contractors appointed for this work are experts within the industry and have taken into consideration a number of factors when programming this work that including the number, type, age and location of assets

3.3The residential programme is to be completed within 14 months and has been scheduled as follows:

 Phase 1 – Ashford/Shepway/Dover o March to June 2016  Phase 2 – Gravesham/Dartford/Sevenoaks o June to September 2016  Phase 3 – Maidstone/Tonbridge & Malling/Tunbridge Wells o August to November 2016  Phase 4 – Swale/Canterbury/Thanet o October 2016 to May 2017

3.4It is expected that these dates may change throughout the programme. Any changes will be communicated to stakeholders.

3.5The second part of the project will see LED conversions to the main routes and town centres. This will be completed within 25 months and a programme for this is currently being developed and will be communicated once agreed.

4. Progress

4.1Work commenced in rural areas within the Borough of Ashford on the 14 March 2016. 3,629 lanterns have been converted by 22 April.

4.2The default profile of the lanterns is to operate all night. The Authority is working with Bouygues to scope out the ‘Optimised’ All Night Lighting policy. This will include analysing the assets on a street by street level, as each road has its own design specification which will enable different optimal illumination levels.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LED Street Light Conversion Project UpdateReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. LED Street Light Conversion Project UpdateThis decision
  2. Proposed consultation on the revised policy on street lighting post-LED conversionAgreed

More from Kent Growth, Environment & Transport Cabinet Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... Decided Open
5 May 2026 Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... Decided Open
5 May 2026 Winter Service UpdateRESOLVED to note the Winter Service Update . Noted Open
5 May 2026 Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. Noted Open
5 May 2026 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies