1. INTRODUCTION
1.1The Policy & Resources Cabinet Committee receives regular Corporate Assurance reports to keep Elected Members informed on developments within major change projects and programmes.
1.2This report continues to provide an overview of change activity within KCC’s change portfolios, in addition to analysis on variances to costs, benefits and milestones for major ‘Tier 1’ (business critical) projects and potential project activity.
2.1In September 2013, KCC published “Facing the Challenge: Delivering Better Outcomes” which introduced four change portfolios to help manage an unprecedented level of complex change across the organisation.
2.2The Corporate Assurance function was established in May 2015 to provide oversight, transparency and assurance of major change activity, providing confidence we are ‘doing the right thing’, as well as delivering things well.
2.3Corporate Assurance uses a collaborative, constructive and relationship based approach. It liaises with colleagues who also offer advice, support and assurance for major change activity e.g. the Finance Special Projects Team; Internal Audit; and Strategic Business Development and Intelligence.
2.4It is important, as the recent informal governance arrangements introduced in April 2016 become established, that the Corporate Assurance function continues to evolve to remain relevant, and in particular contribute to both the Strategic Commissioning Board and Budget & Programme Delivery Board in a way that adds value.
2.5As part of the effort to improve project / programme management skills and knowledge across the Authority, the Corporate Assurance Team and Portfolio Delivery Managers from the four change portfolios have been working with colleagues in the Engagement, Organisation Design & Development (EODD) Division to develop a Project and Programme Manager (PPM) Network. This is a monthly forum, facilitated by an independent industry expert, covering core competences such as scheduling, business case development and cost/benefit articulation.
2.6There is also work-in-progress focusing on the critical leadership role of the project, programme and portfolio Senior Responsible Owners (SRO) and Sponsors in ensuring the successful delivery of benefits.
2.7The current ‘tiering’ of projects by financial value provides helpful and objective criteria for prioritisation. However, alternative methods are being explored to take other factors into consideration such as complexity of the delivery environment, including reputational and political considerations for example.
3. KEY FINDINGS – APRIL TO SEPTEMBER 2016
3.1The key findings are taken from the analysis within the Corporate Assurance Report (Appendix 1):
a. 6 new Tier 1 projects have been introduced during the past six months. There are currently 13 Tier 1 projects, with 65 projects within the portfolios overall. 27 projects have stopped or completed this period. Of those 27, 8 are Tier 1 projects that have completed during this period.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Assurance Analysis Bi-annual ReportReport | 33 pages | DownloadRead as text |
Follow Policy and Resources Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of the meeting held on 6 May 2026RESOLVED that the minutes of the meeting held on 6 May 2026 were a correct record and that they be signed by the Chai... | Decided | Open |
| 2 Jul 2026 | Local Outcomes FrameworkRESOLVED that the report be noted. | Noted | Open |
| 2 Jul 2026 | Budget Planning Process 2027-28 and Medium-Term Financial Plan (MTFP) UpdateRESOLVED that the report be noted. | Noted | Open |
| 2 Jul 2026 | 26/00032 - Adoption of the KCC Winning for Kent: Procurement with Purpose Policy 2026-2028RESOLVED that the Cabinet Committee endorses the proposed decision to: (a) Approve the adoption and implementation of... | Approved | Open |
| 2 Jul 2026 | Work ProgrammeRESOLVED that the work programme be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.