Introduction of a pre-application charging scheme for sustainable urban drainage advice
DecidedExecutive3 papers
Growth, Environment & Transport Cabinet Committee decided this item on Thursday 17 November 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the decision proposed to be taken by the Cabinet Member for Environment and Transport to introduce a pre-application charging service for sustainable urban drainage advice to developers, as set out at Appendix A in the report for engagement with representatives from the development industry via the Kent Developers Group, be endorsed and for the scheme to be reviewed as part of the wider GET charging review.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Environment & Transport Cabinet Committee, 8 pages
Recommendation
The Cabinet Committee is asked to consider and endorse, or make recommendations to the Cabinet Member for Environment & Transport on a proposed decision to introduce a pre-application charging service for sustainable urban drainage advice to developers as set out at Appendix A to this report for engagement with representatives from the development industry via the Kent Developers Group.
1. Introduction
1.1This report seeks the introduction of a chargeable pre-application advice service for sustainable urban drainage (SuDs) advice to developers promoting applications that are determined by the borough and district planning authorities.
2. Context
2.1In 2015, the County Council became a statutory consultee to the planning authorities in Kent responsible for providing technical advice on surface water management including sustainable drainage matters. This includes consultation for full and outline applications as well as secondary consultation in relation to reserved matters, discharge of conditions and variations. This advice is considered as part of the determination of planning applications. 2.2 As a result of the new consultee role, a number of ‘potential developers’ are seeking pre-application advice from the County Council on SuDs matters prior to the submission of a planning application to the borough and district councils.
2.3This discretionary engagement provides an opportunity to shape development at an early part of the development process and can lead to quicker decision making and higher quality development. Developments that are unlikely to be successful during the planning process can also be discouraged, resulting in potentially expensive consultancy and survey work being avoided for the developer.
2.4Providing this service will obviously cost the authority in staff time and other resource. Unlike other parts of the GET Directorate and other local authorities, the cost of this pre-application advice is currently not met by the developer. However, with current financial pressures on the public purse, it is proposed that the service seeks to recover its costs.
3. The Service
3.1The Flood and Water Management Team currently receive consultations with respect to:
a) enquiries to support preparation of flood risk assessments required for major developments and some minor developments (Flood Risk Assessment enquiries), b) enquiries to inform drainage strategies to support a planning application (pre-application enquiries), c) consultations in relation to the preferred approach to define detailed drainage strategies (after planning permission is granted but prior to any further subsequent planning submissions), d) consultations in relation to discharge to the ground and ordinary watercourses; and e) consultations for minor development which may have a drainage issue.
3.2These consultations are received from consultants, house builders, Local Planning Authorities and the general public. The enquiries may result in a written response, meetings in our offices, at local planning authority offices or site meetings to clarify the issues at hand.
3.3An indication of the demand for the service is provided by an assessment of requests over the last year which records some 100 consultations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.