It was RESOLVED that the proposed decision of the Cabinet Member for Corporate and Democratic Services to: a) Authorise the Director of Infrastructure, in consultation with the General Counsel, to enter into any necessary contracts/agreements on behalf of the County Council; b) Authorise the Director of Infrastructure to ensure the appropriate level of funding was received from the Education Funding Agency to cover the costs of these projects and to ensure that Kent County Council did not incur any unforeseen costs and, in consultation with the Cabinet Member for Education and Health Reform, agree apportionment of ... view the full minutes text for item 102.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
From: Gary Cooke, Cabinet Member for Corporate and Democratic Services
Rebecca Spore, Director of Infrastructure.
To: Property Sub Committee, Policy and Resources Committee
Subject: Delivery of construction projects under the Priority School Building Programme Round 2 at Swadelands School, Lenham and Benenden C of E Primary School, Benenden, on behalf of the Education Funding Agency.
Key decision
Classification: Unrestricted
Past Pathway of Paper: None
Future Pathway of Paper: None
Electoral Division: Jenny Whittle; Maidstone Rural East for Swadelands School Sean Holden; Cranbrook for Benenden C of E Primary School
Summary: The Education Funding Agency (EfA) has asked Kent County Council to deliver construction projects within Kent as part of the Priority Schools Building Programme Round 2. Kent County Council will receive the necessary funding for the construction project at each school and a Project Delivery Grant to cover all appropriate costs to manage the project.
Recommendation(s):
The Cabinet Committee is asked to consider and endorse, or make recommendations to the Cabinet Member for Corporate and Democratic Services on the proposed decision to:
a) Authorise the Director of Infrastructure in Consultation with the General Counsel to enter into any necessary contracts/agreements on behalf of the County Council and
b) Authorise the Director of Infrastructure to ensure that the appropriate level of funding is received from the Education Funding Agency to cover the costs of these projects to ensure the Kent County Council does not incur any unforeseen costs and
c) Authorise the Director of Infrastructure to be the nominated Authority Representative within the relevant contracts/agreements and to enter into variations as envisaged under the contract terms. 1 Introduction
1.1On 1 May 2014, the Minister of State for Schools announced that the Government would fund a further phase of the Priority School Building Programme (PSBP), with a value of around £2 billion. The new phase, known as PSBP2, will be a five year programme operating between 2015 and 2021 and will undertake major rebuilding and refurbishment projects in schools and sixth form colleges in the very worst condition.
1.2The Priority School Building Programme is not intended to replace those wider efforts to support local authorities, dioceses, sixth form colleges, academies and multi-academy trusts in addressing the condition needs of their estates. Rather it will run alongside these in order to address individual projects that are of such a significant scale that it would be difficult to pay for them through regular formulaic maintenance allocations.
1.3On 9 February 2015, The Secretary of State for Education and the Minister of State for Schools, , announced that 277 schools across the Country have been successful in their applications. KCC were successful for 7 of the schools in addition 6 further schools across Kent where Academies bid directly.
1.4This programme and its predecessor PSBP Round 1 was instigated following the demise of the Building Schools for the Future Programme in 2012. The PSBP1 successfully secured investment into 13 schools across Kent, all being delivered directly by the Education Funding Agency (EFA), which in the main are whole school replacement projects.
1.5For PSBP2 the criterion has been amended and does not always replace all of the school’s accommodation. The emphasis is more upon a block replacement and is based on poor condition rather than any other criteria such as suitability or sufficiency. Only in exceptional circumstances will a whole school be replaced.
1.6To allow for KCC to include Basic Need expansion on PSBP schools, where this was appropriate, a budget allocation was set aside for these particular projects. A budget amount of £9.6million has been approved within the Budget Book in total for both the PSBP1 and PSBP2 schemes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.