RESOLVED that the Minutes of the meeting held on 13 November 2017 are correctly recorded and that they be signed by the Chairman.
KENT COUNTY COUNCIL
KENT FLOOD RISK MANAGEMENT COMMITTEE
MINUTES of a meeting of the Kent Flood Risk Management Committee held in the Council Chamber, Sessions House, County Hall, Maidstone on Monday, 13 November 2017.
PRESENT: [name removed] (Chairman), [name removed], [name removed], [name removed] (Substitute for [name removed]), [name removed] (Substitute for [name removed]), Cllr Ms R Doyle (Canterbury CC), [name removed] (Sevenoaks DC), [name removed], [name removed] (Swale BC), [name removed] (Tonbridge and Malling BC), [name removed] (KALC), [name removed] (KALC), [name removed] and [name removed] (Upper Medway IDB)
ALSO PRESENT: [name removed]: [name removed] (Flood Risk Manager), [name removed] (Principal Resilience Officer) and [name removed] (Democratic Services Officer)
UNRESTRICTED ITEMS
15. [name removed] (Item )
The Committee observed a moment’s silence in memory of [name removed] who had passed away since the previous meeting.
16. Minutes of the meeting on 17 July 2017 (Item 3)
(1) [name removed] informed the Committee in respect of Minute 11 (8) that Southern Water had agreed to accept responsibility for the SuDS Scheme referred to.
(2) RESOLVED that subject to an amendment to Minute 11 (7) setting out that the Gold Commander was the Chair of the SCG, the Minutes of the meeting held on 17 July 2017 are correctly recorded and that they be signed by the Chairman.
17. Medway Estuary and Swale Shoreline Management Strategy - Presentation by John Byne, Environment Agency (Item 4)
(1) John Byne from the Environment Agency gave a presentation. The accompanying slides are contained within the electronic agenda papers on the KCC website. (2) [name removed] said that the Environment Agency was working on the Medway Estuary and Swale Flood and Coastal Risk Strategy in partnership with their consultants, Mott MacDonald.
(3) [name removed] described the area covered by the Strategy. It started at Stoke by the Kingsnorth Power Station, went down the Medway to Allington, extending as far east as Graveney Marshes (Cleve Hill). It also covered the Isle of Sheppey.
(4) [name removed] then described the three tiers of coastal defence planning. The EA had published the Shoreline Management Plans by 2010 and was now working on the strategies which would consider the Plans in greater detail, consider whether their policies were still relevant and establish policies for smaller frontages. The strategies were considering costings for high level options rather than undertaking any scheme design.
(5) [name removed] went on to say that Phase 3 of the Strategy (short list to preferred options) had now been signed off by the Project Board during the summer and Phase 4 had now begun. The Consultants were now completing the reports in preparation for consultation which was due to commence towards the end of winter 2018.
NB: The consultation is now live. The Link is: https://consult.environment- agency.gov.uk/ksles/medway-estuary-and-swale-strategy/
(6) [name removed] turned to the development of the preferred options. It had taken two years to develop the criteria which would enable the Project to consider the best way to manage the various frontages through the coastal area. The main priority was to reduce the risk and the threat of coastal flooding and coastal erosion to people and their property. The second criterion was to deliver the greatest environmental, social and economic benefit. There were a large number of designated areas in the Medway/Swale area which needed to be preserved and protected, including their natural habitats. The EA had worked closely with Natural England on their Coastal Footpath project. The third criterion of working with natural processes aimed to ensure that work on coastal flood protection dovetailed with the protection of natural habitats. The “adapting to future risks” criterion took account of the Strategy’s hundred year duration. Adaption to phenomena such Climate Change and other factors was therefore crucial.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the meeting on 13 November 2017Minutes | 8 pages | DownloadRead as text |
Follow Kent Flood Risk and Water Management Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Jun 2026 | Minutes of the meeting on 04.03.26RESOLVED that the minutes of the meeting held on 4 March 2026 were an accurate record and that they be signed by the ... | Decided | Open |
| 4 Mar 2026 | Minutes of the meeting on 29.10.2025RESOLVED that the minutes of the meeting held on 29 October 2025 were an accurate record and that they be signed by t... | Decided | Open |
| 4 Mar 2026 | KCC Severe Weather Response Activity ReportRESOLVED to note the verbal update on | Noted | Open |
| 4 Mar 2026 | Met Office- Introduction PresentationRESOLVED to note the Met Office Presentation | Noted | Open |
| 4 Mar 2026 | SGN - Introduction and Water Ingress into the Gas Network PresentationRESOLVED to note the Southern Gas Network (SGN) presentation | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.