Resolved
RESOLVED that the Rights of Way Improvement Plan be noted and progression to public consultation, be endorsed.
Growth, Environment & Transport Cabinet Committee noted this item on Tuesday 15 May 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Rights of Way Improvement Plan be noted and progression to public consultation, be endorsed.
From: Mike Hill: Cabinet Member for Community & Regulatory Services
Barbara Cooper, Corporate Director, Growth, Environment and Transport
To: Environment and Transport Cabinet Committee - 15 May 2018
Subject: Revision of the Rights of Way Improvement Plan.
Classification: Unrestricted
Summary There is a statutory requirement to produce a Rights of Way Improvement Plan (ROWIP) and to review the plan within 10 years of its publication. The current ROWIP was adopted in 2008, and therefore a review is required. This report details how the review was undertaken and the main elements of the draft plan.
Recommendation Cabinet Committee is asked to discuss and consider the draft Rights of Way Improvement Plan and to endorse the recommendation to progress to public consultation.
1. Introduction
1.1It is a statutory requirement to produce a Rights of Way Improvement Plan (ROWIP) and to review it within 10 years of publication.
1.2The ROWIP sets the direction and supports the work of the Public Rights of Way Team to make a real difference to the quality of life of Kent residents.
2. The Report
2.1The first Rights of Way Improvement Plan was adopted by the County Council in 2008. Significant investment, improvements and savings to the capital liability for the Public Rights of Way network have been delivered through the objectives set out in the initial Plan.
2.2The County Council is required to review its plan within10 years of its publication. It is imperative that the Plan is kept up to date and is:
a) aligned to current County Council priorities b) reflects the input provided by our customers, c) adapts to the current economic climate, and; d) provides a policy basis for securing new opportunities as they arise.
2.3For these reasons a review of the ROWIP has been undertaken and a draft Plan produced for consultation; provided as Appendix 1.
2.4Preparation of the Plan has involved extensive research, customer surveys and direct customer feedback. This has included; previously completed consultations, research of business and asset management plans, review of KCC and national research and policy, obtaining information from focus groups, Parish Councils, District/Borough Councils and County Members.
2.5As a statutory document there is certain information that must be contained within the Plan. Those requirements are set out in legislation contained within the Countryside and Rights of Way (CROW) Act 2000. The revision therefore contains many of the same elements as the original 2007 and 2013 versions.
2.6The main elements of the Plan including those regulatory requirements are:
a) An assessment of existing and potential use and demand. b) Detailed customer profiling using Market Research, Mosaic and Countryside Access Management System. c) National and local policy context. Attention has been given to aligning the Plan with ‘Increasing Opportunities, Improving Outcomes: Kent County Council’s Strategic Statement (2015-2020)’, Local Transport Plan 4 and the Active Travel Strategy. d) Operational management, asset management and budgetary information. e) How to make the best of new national and local funding opportunities. f) A delivery plan that includes main objectives, actions, benefits and key partners and resource implications.
2.7Statutory pre-consultation is required with district/borough, parish and neighbouring councils. Natural England as the regulating body must also be informed of the proposed update. The consultation must be advertised in two local papers to enable opportunities to comment from all Kent residents and to conform with regulation.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 11: Appendix A: ROWIPAppendix | 21 pages | Download |
PDF |
Revision of the Rights of Way Improvement PlanReport | 4 pages | DownloadRead as text |
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... | Decided | Open |
| 5 May 2026 | Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... | Decided | Open |
| 5 May 2026 | Winter Service UpdateRESOLVED to note the Winter Service Update . | Noted | Open |
| 5 May 2026 | Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. | Noted | Open |
| 5 May 2026 | 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.