Resolved
RESOLVED that the interim report be noted and that the East Kent CCGs be requested to provide a detailed update, including a timetable, to the Committee in July. 10:30
Health Overview and Scrutiny Committee noted this item on Friday 8 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the interim report be noted and that the East Kent CCGs be requested to provide a detailed update, including a timetable, to the Committee in July. 10:30
East Kent Transformation Programme
Briefing to Chair of HOSC 6 June 2018
Over the last 12 months, the east Kent system has provided a number of updates to the HOSC. These updates have provided an overview of the operational and financial challenges that the system is facing as well as proposals and options for the future delivery of in and out of hospital services. As HOSC is aware, future transformation of services is complex and demands a whole system approach with no single organisation able to deliver the whole scale change alone.
In April 2018, NHS England updated its guidance on the process for assuring and approving significant service reconfiguration proposals ahead of public consultation. The new guidance extends the requirements on the local system that must be fulfilled before the go- ahead can be given for a full public consultation, particularly on an issue as complex as the transformation of health services in east Kent. It sets out a number of key stages of the prescribed assurance process as well as four tests and supplementary conditions that the proposals will need to satisfy.
The east Kent Case to date
As HOSC is aware, by working through a systematic process, we have identified what has been termed as Option 1. Namely: the creation of a major emergency centre with specialist services at the William Harvey in Ashford; an emergency centre at the Queen Elizabeth Queen Mother in Margate; and a GP-led urgent care centre at the Kent and Canterbury. This option would be deemed a relatively low-cost capital option, although work continues to fully assess the capital implications.
The approach from the developer to provide the shell of a hospital at Kent and Canterbury introduced what is termed Option 2. Namely: the creation of a major emergency centre at the Kent and Canterbury; and GP-led urgent care centres at the other two hospitals. Whilst the developer has offered to gift the shell of a hospital to the NHS, there would be a significant capital investment required to fit out the shell.
Both options require significant investment and development to local care including primary care and community services, to enable integrated care across the whole system, which is essential to meet the needs of patients, particularly those with complex health problems and ensure a sustainable local health economy. These dependencies require detailed planning and alignment of clinical service models for in and out of hospital care, financial and activity models that consider shifts in activity and service provision as well as workforce and estates requirements to ensure effective delivery.
The business case that is submitted and considered by NHS England will need to include this detail and provide a compelling case for the proposed changes including why the change is needed and why the proposed model is the one that bests supports local population needs. It will also demonstrate the case for required capital investment in the system as well as the potential source of this capital.
Readiness Assessment by EY
As we progress to drafting the business case ahead of its submission to NHS England, the east Kent system has commissioned management consultants EY to complete an independent assessment of the work to date to transform services, and to prepare the business case. The readiness assessment recognises the considerable amount of work that has been undertaken to reach the current stage and the proposed two options. The assessment also identifies the further work that is required to progress the two options and meet the requirements of the updated NHS England guidance. The insight at this stage allows us to address these gaps, an investment in time now that should benefit us in the later assurance stages.
Timeline to deliver the programme
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 5: CCGs' ReportReport | 3 pages | DownloadRead as text |
PDF |
Transforming Health and Care in East Kent: Verbal UpdateReport | 1 pages | Download |
Follow Health Overview and Scrutiny Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Apr 2026 | Apologies and SubstitutesRESOLVED that the apologies and substitutes be noted. | Noted | Open |
| 2 Apr 2026 | Declarations of Interests by Members in items on the Agenda for this meetingRESOLVED that the declarations of interest be noted. | Noted | Open |
| 2 Apr 2026 | Minutes of the meeting held on 4 February 2026RESOLVED that the minutes of the meeting held on 4 February 2026 were a correct record and that they be signed by the... | Decided | Open |
| 2 Apr 2026 | Children's Cancer Principal Treatment Centre RelocationRESOLVED to note the report. | Noted | Open |
| 2 Apr 2026 | Establishment of a Group between Medway NHS Foundation Trust and Dartford & Gravesham NHS TrustRESOLVED to note the report. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.