RESOLVED that; · The business plan be noted · The updated budget be agreed (additional forecast spend) · The Committee agree to delegate authority to approve up 10% overspends, in consultation with the Chairman, on relevant budget lines / workstream costs to the named lead officer responsible.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
1.1The Joint Committee is required to make recommendations to the ACCESS Authorities about the annual strategic business plan for the Pool. The strategic plan was agreed by the Joint Committee in April 2018 and has now been referred to the relevant ACCESS Authorities.
1.2The Joint Committee also agreed the budget necessary to implement the business plan (insofar as the costs will not be paid by ACCESS Authorities direct to the Operator) at their meeting in April 2018 and this will be charged to the relevant ACCESS Authorities.
1.3This report updates the Joint Committee on the work undertaken.
2. Business Plan Update
2.1The table on the following page shows progress against key items anticipated to be delivered since the last Joint Committee. Key Milestone Update Status Consider Legal Entity Completed Consider the benefits and drawback of legal entity model for ACCESS pool. Green Approve Sub-Fund Tranche 1 Completed Ensure initial sub-fund meets Link’s due diligence requirements and ACCESS Green Authorities value for money criteria (including transition activity). FCA Approval for Initial Sub-Fund Completed in August (later than the original Work with Link to submit application to the June 2018 date due to due diligence required FCA for approval of the ACCESS ACS and on the documents supporting the Green initial sub-fund set-up. application to the FCA). Approve Sub-Fund Tranche 2 and Tranche 3 Drafting of relevant Schedules for each sub- Ensure subsequent sub-funds meet fund underway by Link. Operator’s due diligence requirements and Red participating Authorities value for money However FCA application now due 25 criteria (including transition activity). September and FCA approval now due on 23 October and Sub Fund Launch due on 23 January 2019, which is one month behind the original schedule.
Tranche 3 Sub-Funds to be agreed with Link with FCA application to be made by 11 December, FCA approval due on 12 February and Sub Fund Launch due on 10 April 2019, which is two months behind the original schedule.
Status shown as red based on the original Business Plan agreed by the JC. Project Management is now against the revised dates shown above and the status is showing as green against the re-forecasted dates. Determine Phase 2 Sub-Funds Work underway with proposal to be Joint Committee agree sub-fund considered by the Joint Committee requirements for Phase 2 following Officer elsewhere on the agenda relating to global Amber consideration and UK equities.
Please Note: It was original anticipated that the Joint Committee would agree Phase 2 Sub-Funds in November 2018 and Link would apply for FCA approval of the Phase 2 sub-funds in January 2019. The application for Phase 2 sub-funds will follow the completion of Phase 1 Tranche 3 (now planned to be submitted in December 2018). Agree ACCESS Support Unit Agreement by Joint Committee to roles and Identify ASU resource requirements, roles responsibilities and draft role profiles in line and responsibilities for activities and draft with plan (June 2018) and Essex County Amber job description and recruitment process. Council as Host Authority have subsequently determined the recruitment process for the ASU.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.