Resolved
RESOLVED that subject to the deletion of “container” in Minute 17 (18), the Minutes of the meeting held on 12 November 2018 are correctly recorded and that they be signed by the Chairman.
Kent Flood Risk and Water Management Committee decided this item on Monday 11 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that subject to the deletion of “container” in Minute 17 (18), the Minutes of the meeting held on 12 November 2018 are correctly recorded and that they be signed by the Chairman.
KENT COUNTY COUNCIL
KENT FLOOD RISK MANAGEMENT COMMITTEE
MINUTES of a meeting of the Kent Flood Risk Management Committee held in the Council Chamber - Sessions House on Monday, 12 November 2018.
PRESENT: [name removed] (Chairman), [name removed] (Substitute for [name removed]), [name removed], [name removed], [name removed], [name removed], [name removed], [name removed] (Canterbury CC), [name removed] (Folkestone and Hythe DC), [name removed] (Maidstone BC), [name removed] (Sevenoaks DC), [name removed] (Swale BC), [name removed] (Tonbridge and Malling BC), [name removed] (Tunbridge Wells BC) and [name removed] (KALC)
ALSO PRESENT: [name removed] and [name removed]: [name removed] (Flood and Water Manager), [name removed] (Resilience and Emergency Planning Manager) and [name removed] (Democratic Services Officer)
UNRESTRICTED ITEMS
12. Membership (Item 1)
The Committee noted the appointment of [name removed], [name removed] and [name removed] in place of [name removed] and the two pre-existing vacancies.
13. Minutes of the meeting on 16 July 2018 (Item 4)
14. Dates of future meetings (Item 5)
The Committee noted that its next meetings would be held on:-
Monday, 11 March 2019; Monday, 22 July 2019; Monday, 11 November 2019; and Monday, 20 March 2020.
15. Meeting the Challenge of Highways Drainage - The programme of planned maintenance (Item 7) (1) The Committee agreed that the two presentations set out at items 5 and 6 on the agenda would be considered together. The presentation slides are contained within the electronic agenda papers on the KCC website.
(2) [name removed] (Deputy Cabinet Member for Planning, Highways, Transport and Waste) began his presentation by setting out some of the outcomes that KCC’s programme of planned maintenance aimed to achieve. These were: fewer flooding incidents on Kent’s highways; ensuring that the roads and footways were free from standing water; and building greater resilience against intense rainfall events. The difficulty of achieving this outcome could be gauged by noting that the rainwater goods at St Paul’s Cathedral had overtopped ten times during the year, whereas this had only happened once in the previous ten. This, in turn, would assist in reducing disruption and increase customer satisfaction and confidence.
(3) [name removed] moved on to consider KCC’s assets. The most significant of these were the 250k roadside drains. Road Maintenance generally was undertaken to maintain road safety and to maximise the lifespan of the highway.
(4) [name removed] said that the Drainage Team received over 7,000 enquiries a year, primarily in respect of blocked drains which presented a general risk. An analysis of drainage enquiries received over the previous four years (2014 – 18) showed that the peak periods had not always been during the winter months or, indeed, during the same months each year. For example, the annual peak during the previous three had occurred in June 2016, July and August 2017 and in May 2018.
(5) The budget allocation for drainage maintenance was £2.5m, enabling a response to flooding that posed an immediate risk to highway safety. Drainage hotpots were cleaned every six months and roadside drains on main roads every 12. Other assets were targeted within 2 hours or 90 days, depending on their severity. Other budget allocations were for ironwork repairs, pumping station servicing and repairs and drainage investigations, together with a £3.5 budget for capital work.
(6) [name removed] then said that not all drains were cleaned every year, nor was it always necessary to do so. Another 4,000 jobs were issued to the contractors in response to customer enquiries to clean gullies, jet lines, cleanse soakaways and to generally carry out investigations to reduce surface water on the network.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the meeting on 12 November 2018Minutes | 14 pages | DownloadRead as text |
Follow Kent Flood Risk and Water Management Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Jun 2026 | Minutes of the meeting on 04.03.26RESOLVED that the minutes of the meeting held on 4 March 2026 were an accurate record and that they be signed by the ... | Decided | Open |
| 4 Mar 2026 | Minutes of the meeting on 29.10.2025RESOLVED that the minutes of the meeting held on 29 October 2025 were an accurate record and that they be signed by t... | Decided | Open |
| 4 Mar 2026 | KCC Severe Weather Response Activity ReportRESOLVED to note the verbal update on | Noted | Open |
| 4 Mar 2026 | Met Office- Introduction PresentationRESOLVED to note the Met Office Presentation | Noted | Open |
| 4 Mar 2026 | SGN - Introduction and Water Ingress into the Gas Network PresentationRESOLVED to note the Southern Gas Network (SGN) presentation | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.