Resolved
RESOLVED that · the updated business plan and 2018/19 forecast spend be noted; · the business plan be recommended to the administering authorities; and · The 2019/20 budget be agreed.
ACCESS Joint Committee noted this item on Monday 18 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that · the updated business plan and 2018/19 forecast spend be noted; · the business plan be recommended to the administering authorities; and · The 2019/20 budget be agreed.
Business Plan and Budget Quarterly Update
ACCESS Joint Committee
Date: 18 March 2019
Report by: Officer Working Group
Subject: Business Plan and Budget Update
To provide an update on the activities undertaken since the last Joint Purpose of the Report: Committee and associated spend
The Committee is asked to note the updated business plan and 2018/19 Recommendations: forecast spend, and to approve the 2019/20 budget for recommendation to individual ACCESS Authorities
Enquiries to: Alison Mings ([email protected] 03000 416488)
1. Purpose
1.1The Joint Committee is required to make recommendations to the ACCESS Authorities about the annual strategic business plan for the Pool. The strategic plan was agreed by the Joint Committee in April 2018 and has now been referred to the relevant ACCESS Authorities.
1.2The Joint Committee also determined the budget necessary to implement the business plan during 2018/19 (insofar as the costs will not be paid by ACCESS Authorities direct to the Operator) at their meeting in April 2018 and this has been charged to the relevant ACCESS Authorities.
1.3This report updates the Joint Committee on the work undertaken to date and costs incurred in 2018/19.
1.4The Joint Committee is also requested to agree the updated plan which includes activities planned for 2019/20 and determine the 2019/20 budget required to fund these activities.
2. Business Plan Update
2.1The key activities undertaken are as follows: 2018/19 - Access Support Unit (ASU) recruitment in progress - ASU functions mainly undertaken by 3rd parties - Tranches 1 and 2 sub fund onboarding
2019/20 - ASU recruitment completes - ASU functions mainly undertaken by ASU officers and technical leads - Tranches 3, 4 and 5 sub fund onboarding - Consideration of non-listed / illiquid assets
2.2The table below shows progress against key items anticipated to be delivered since the last Joint Committee and due to be completed by end March 2019, as well as the proposed activity in 2019/20.
2.3It should be noted that in 2019/20 ACCESS Support Unit (ASU) Officers employed by Essex as the Host Authority, together with the Technical Leads, will be taking over most of the functions of the ASU from the 3rd party providers.
2.4It is anticipated that external advisors will be engaged in relation to the further work on the Governance arrangements for the ACCESS pool as well as in relation to the set- up of further ACS sub-funds as well as any arrangements for the pooling of illiquid assets.
ACCESS Strategic Business Plan
Key Milestone 2018/19 Anticipated 2019/20
Consider Legal Entity Consider the benefits and drawback of legal Completed N/A entity model for ACCESS pool. Complete Governance Manual Work with external advisers to reflect decision Will have residual cost relating making principles, communication strategy, Substantially Completed to training. policies and procedures, code of conduct etc in the Governance Manual Complete Review of Inter Authority Further redrafting required to Agreement reflect changes; mainly to the Work with external advisers to reflect any Initial redrafting undertaken current operational elements changes resulting from the completion of the of the Pool Governance Manual and review Agree and establish ACCESS Support Unit ASU functions will be mainly Identify ASU resource requirements, roles and Third party providers appointed undertaken by ASU Officers responsibilities for activities, scope and run as interim ASU and Technical Leads recruitment activity and appoint
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2019/20 Business Plan & Budget [11:10: 11:30]Report | 7 pages | DownloadRead as text |
Follow ACCESS Joint Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Sep 2023 | Apologies/SubstitutesRESOLVED that the apologies be noted. | Noted | Open |
| 4 Sep 2023 | Minutes of the meeting held on 5 June 2023RESOLVED that the minutes from the meeting held on 5 June 2023 be signed as a true and accurate record. | Decided | Open |
| 4 Sep 2023 | Chair's remarksRESOLVED that the Chair’s remarks be noted. | Noted | Open |
| 4 Sep 2023 | Business plan, Budget & RiskRESOLVED to note the: a) 2023/24 Business Plan update; b) 2023/24 budget update; and c) risk summary. Motion to Exclu... | Noted | Open |
| 5 Jun 2023 | Apologies/SubstitutesRESOLVED that the apologies be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.