19/00016 - Procurement and award of contract/s for Highway Arboriculture Programmed Works

Approved Executive 4 papers

Growth, Environment & Transport Cabinet Committee approved this item on Tuesday 19 March 2019. Below is the council's own wording, with the papers it was decided on.

Item168

Resolved

RESOLVED that the proposed decision (19/00016) to be taken by the Cabinet Member for Planning, Highways, Transport and Waste to: (a) approve the procurement of the Arboriculture Programmed Works Contract and in consultation with the Cabinet Member for Planning, Highways, Transportation and Waste delegate authority to the Director of Highways, Transportation and Waste to approve the award of the subsequent contract to the preferred bidder; and (b) in consultation with the Cabinet Member for Planning, Highways, Transportation and Waste delegate authority to the Director of Highways, Transportation and Waste to award extensions of the Arboriculture Programmed Works Contract in accordance with the possible extension clauses within the contract, be endorsed.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Growth, Environment & Transport Cabinet Committee, 5 pages

Summary

This contract will facilitate programmed and ad-hoc tree works for up to a five-year period both on or adjacent to the highway network. The current contract for this service comes to an end on 31st August 2019. A Key Decision is required to award the contract/s for this service as the value of the contract over the term, including optional extensions exceeds £1m.

Recommendation(s):

The Cabinet Committee is asked to consider and endorse, or make recommendations to the Cabinet Member for Planning, Highways, Transport and Waste on the proposed decision to:

(a) approve the procurement of the Arboriculture Programmed Works Contract and in consultation with the Cabinet Member for Planning, Highways, Transportation and Waste delegate authority to the Director of Highways, Transportation and Waste to approve the award of the subsequent contract to the preferred bidder; and

(b) in consultation with the Cabinet Member for Planning, Highways, Transportation and Waste delegate authority to the Director of Highways, Transportation and Waste to award extensions of the Arboriculture Programmed Works Contract in accordance with the possible extension clauses within the contract.

ETCC Report Mar 2019 Version 0.4 1. Introduction

1.1The arboriculture programmed works contract is required to ensure that KCC complies with its ‘Duty of Care’ under the Highway Act 1980 and fulfils its obligations in Common Law as a land and tree owner.

1.2The current contract comes to an end on 31st August 2019 after five years which includes two one-year extensions, no further contract extensions can be made under this contract. In order to ensure continuity of service, new arrangements need to be in place from September 1st, 2019.

2. Report

2.1The contract will provide for:

 Programmed tree works as a result of Tree Safety Audits (TSA).  Removal of dangerous trees and branches on both public and private property.  Removal of tree stumps and replacement tree planting.  Cyclical pollarding and basal growth removal  Management of Ash Dieback

2.2There are currently approximately 38,500 individual tree assets on the urban highway network and 80,000 within groups, there are a further 370,000 trees within tree belts, rural areas and woodland fringes. A conservative application of the industry standard Capital Asset Valuation of Amenity Trees (CAVAT) system estimates the value of the 38,500 individual urban trees at over £371m.

2.3It is important that KCC HTW delivers an effective fit for purpose highway arboriculture works service which operationally delivers, meets our statutory obligations in terms of highway Asset Management and public safety whilst protecting the reputation of the County Council in delivering this part of the Highway service.

2.4Trees are a long-term organic asset and as such poor-quality tree works can have a long-lasting impact on the Soft Landscape asset with limited scope for rectification. This contract, through robust specification, contract management and quality monitoring delivers on this and secures the current tree stock into the future.

2.5The arboriculture works contract requires specialist knowledge by those contractors undertaking the works. They must comply with British Standard BS3998: 2010 Tree Work Recommendations and have the requisite certificates of competence to carry out the works.

3. Commissioning

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
19/00016: Procurement and award of contract/s for Highway Arboriculture Programmed WorksReport 5 pages DownloadRead as text
PDF
Item 16: 1900016: Appendix A: PRODAppendix 2 pages Download
PDF
Item 16: 1900016: Appendix B: Commercial StrategyAppendix 16 pages Download
PDF
Item 16: 1900016: Appendix C: EqIAAppendix 10 pages Download

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. 19/00016 - Procurement and award of contract/s for Highway Arboriculture Programmed WorksThis decision
  2. 23/00118 - Procurement and award of contract/s for Highway Arboriculture Programmed WorksApproved
  3. 20/00081 - Procurement and award of contract/s for Soft Landscape Urban Grass, Shrubs & HedgesDecided
  4. 17/00140 - Procurement and award of contract/s for Soft Landscape Urban Grass, Shrubs & HedgesDecided
  5. 17/00016 Re-procurement and award of contract/s for Soft Landscape Urban Grass, Shrubs & Hedges (Maidstone, Dartford, Canterbury & Thanet).Decided
  6. Re-procurement and award of contract/s for Soft Landscape Rural Swathe and Visibility CuttingDecided

More from Kent Growth, Environment & Transport Cabinet Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... Decided Open
5 May 2026 Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... Decided Open
5 May 2026 Winter Service UpdateRESOLVED to note the Winter Service Update . Noted Open
5 May 2026 Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. Noted Open
5 May 2026 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies