19/00061 - Following the amalgamation of the former Murston Infant and Junior Schools to establish Sunny Bank Primary School, relocation of Sunny Bank Infant and Nursery departments to Sunny Bank Junior department site, with infrastructure for an expansion from 1.5FE to 2FE.

Agreed Executive 2 papers

Children, Young People and Education Cabinet Committee agreed this item on Tuesday 1 October 2019. Below is the council's own wording, with the papers it was decided on.

Item15a

Resolved

RESOLVED that the decision proposed to be taken by the Cabinet Member for Children, Young People and Education to: (i) Allocate £4.2M from the Children, Young People and Education Capital budget; (ii) Authorise the Director of Infrastructure in consultation with the General Counsel (Interim) to enter into any necessary contracts/ agreements on behalf of the County Council; and (iii) Authorise the Director of Infrastructure to be the nominated Authority Representative within the relevant agreements and to enter into variations as envisaged under the contracts. Variations to contract value to be no more than 10% above the capital funding agreed by the Cabinet Member without requiring a new Record of Decision, be endorsed, subject to planning agreement.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Children, Young People and Education Cabinet Committee, 5 pages

Summary

This report sets out the proposal to relocate Sunny Bank Primary School’s Infant and Nursery departments onto the Junior Site with the infrastructure for an expansion from 1.5FE to 2FE following the academisation of the School.

Recommendation(s):

The Children’s, Young People and Education Cabinet Committee is asked to CONSIDER and ENDORSE or MAKE RECOMMENDATIONS to the Cabinet Member for Children, Young People and Education on the proposed decision to:

(i) Allocate £4.2M from the Children, Young People and Education Capital budget;

(ii) Authorise the Director of Infrastructure in consultation with the General Counsel (Interim) to enter into any necessary contracts/ agreements on behalf of the County Council; and

(iii) Authorise the Director of Infrastructure to be the nominated Authority Representative within the relevant agreements and to enter into variations as envisaged under the contracts. Variations to contract value to be no more than 10% above the capital funding agreed by the Cabinet Member without requiring a new Record of Decision.

This proposal is also subject to Planning agreement.

1. Introduction 1.1 The KCP 2019-2023 identifies the need for additional places in the Sittingbourne East primary planning area and the expansion of Sunny Bank Primary by 0.5FE was identified to meet this need. A total of 1,409 new dwellings are expected to be built in the Sittingbourne East Planning area from 2019-2030. A full feasibility was commissioned in 2018 to relocate the infant department and Nursery to the junior department site and have the infrastructure to expand by 0.5FE to a 2FE primary school. This ensures that there are adequate places for children from new housing and secures the future finial viability of Sunny Bank.

Background

2.1Sunny Bank Primary School was established on 1 September 2016 when Murston Junior school and Murston Infant School and Maintained Nursery amalgamated. The new primary school opened in the existing accommodation of both schools and it was envisaged that in the longer term the Local Authority will pursue opportunities for future building work that would allow the infant phase to be accommodated on the junior site.

2.2The current infant department was originally established in the 1860s and additional buildings were added over subsequent years. The cost of maintaining the infant school site would require substantial investment to ensure the buildings are fit for purpose as the classrooms are in a poor state of repair. The cost of refurbishment, continual maintenance and ongoing cost of the lease of the site (the site is owned by a Diocesan Trust) is not financially viable. The cost-effective measure is therefore to relocate the infants to the junior site which is adjacent to the Infant site and has adequate space to accommodate the infant and nursery on one site.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
19/00061: Following the amalgamation of the former Murston Infant and Junior Schools to establish Sunny Bank Primary School, relocation of Sunny Bank Infant and Nursery departments to Sunny Bank Junior department site, with infrastructure for an expansion from 1.5FE to 2FE.Report 5 pages DownloadRead as text
PDF
Item 15: Sunny Bank PRODReport 2 pages Download

At this meeting

Whole meeting

More from Kent Children, Young People and Education Cabinet Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 Minutes of the meeting held on 12 May 2026RESOLVED that the minutes of the meeting held on 12 May 2026 were a correct record. Decided Open
14 Jul 2026 Verbal Update by Cabinet MembersRESOLVED that the verbal updates be noted. Noted Open
14 Jul 2026 Performance MonitoringRESOLVED that the report be noted. Noted Open
14 Jul 2026 26/00042 - Proposed Expansion of Oakwood Park Grammar SchoolRESOLVED that the Committee considered and endorsed the proposed decision Decided Open
14 Jul 2026 26/00043 - Expert at Hands (EaH) and Local Authority (LA) Special Education Needs & Disability (SEND) Transformation GrantRESOLVED that the Committee considered and endorsed the proposed decision Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies