19/00065 - Public Rights of Way Asset Management Plan 2019
AgreedExecutive4 papers
Growth, Environment & Transport Cabinet Committee agreed this item on Thursday 10 October 2019. Below is the council's own wording, with the papers it was decided on.
It was RESOLVED that the proposed decision (19/00065) to be taken by the Cabinet Member for Community and Regulatory services to agree: (a) The Public Rights of Way and Access Service Asset Management Plan, (b) The approach taken to managing the risks associated with not fully funding the maintenance of the PRoW network in line with asset management principles; and (c) The proposed Service Level Risk Assessments which set out our approach to the management of risk on the PRoW network, be endorsed.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Environment & Transport Cabinet Committee, 6 pages
From: Mike Hill, Cabinet Member for Community and Regulatory Services
Katie Stewart, Director of Environment, Planning and Enforcement
To: Environment and Transport Cabinet Committee – 10 October 2019
Decision Number: 19/00065
Subject: Public Rights of Way Asset Management Plan 2019
Classification: Unrestricted
Past pathway of paper: N/A
Future pathway of paper: For Cabinet Member Decision
Summary: This paper provides an overview of the Public Rights of Way (PRoW) asset management plan 2019.
The Public Rights of Way and Access Service adopted asset management principles for the maintenance of the PROW network in 2007. This approach has brought benefits in targeting investment in the network, managing risk and evaluating new products and materials where they may help reduce long term expenditure. The approach has also enabled the service to lever in additional investment. The plan has now been reviewed and updated.
Recommendation(s):
The Environment and Transport Cabinet Committee is asked to comment and endorse or make recommendations to the Cabinet Member for Community and Regulatory Services on:
(i) The Public Rights of Way and Access Service Asset Management Plan
(ii) The approach taken to managing the risks associated with not fully funding the maintenance of the PRoW network in line with asset management principles.
(iii) The proposed Service Level Risk Assessments which set out our approach to the management of risk on the PRoW network.
As shown at Appendix A. 1. Introduction
1.1Kent’s Public Rights of Way (PRoW) network extends to 6900Km the overwhelming majority of which is maintainable public highway (Kent’s highway network, excluding PRoW, extends to 8700Km). The County Council has a statutory obligation to maintain the highway in a condition that is safe and passable by the ordinary traffic of the area at all times of the year particularly having regard to the needs of those with a disability.
1.2In 2007 the County Council’s PRoW and Access Service adopted asset management principles for the maintenance of the PRoW network. The Asset Management Plan was informed by a whole network survey completed between 2004 and 2007. The survey provided a detailed picture of the PRoW asset and its condition. The asset information is captured in the Countryside Access Management System and is updated following inspections by officers and volunteers and in response to public reports. The Public Rights of Way Asset Management Plan 2019 is included as Appendix B.
1.3The investment required to maintain the network is calculated on the basis of a series of assumptions that have been refined over time. These assumptions relate to expected asset life and measured performance in the field. The assumptions are further amended to reflect the County Council’s obligations in respect of shared assets such as gates and stiles where only a proportion of the maintenance cost is borne by the authority. The value of the asset is currently calculated at £107M with an annual investment requirement of £2.4M to maintain the asset in a steady state. The County Council currently spends £1.3M annually on maintaining the asset, £1.1M below the level calculated as required to maintain the asset in a steady state.
1.4The Asset Management Plan identifies a backlog of £2.4M. In effect this reflects the current backlog of work relating to assets that have deteriorated to a point where they require replacement. Most significant in terms of investment required to close the performance gap are the network of mainly urban tarmacadam paths and heavily used bridleways and byways open to all traffic in areas of clay soils.
1.5In addition to the £2.4M backlog a further £2.2M of investment is identified as being required to improve unsurfaced routes up to a standard that meets modern requirements.
2 Financial Implications and Risk
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.