RESOLVED that the following be noted: 1. The revised timetable for completion of phase 3 governance deliverables 2. The revised IAA would take effect upon execution by all participating authorities. Completion of the process to be confirmed in writing by the Clerk to the Committee.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
2.1In June 2018 the JC agreed to Phase 3 of the Governance Workstream, which included reviewing the Inter Authority Agreement (IAA) alongside the completion of the Governance Manual, with a primary focus on ensuring consistency and clarity.
2.2In September associated costs for this area of work was presented to the JC and it was agreed to include in the budget plan.
2.3Section 151 Officers have discussed and contributed to the development of this workstream at each of their four meetings between December 2018 and August 2019. An update was also given at their November 2019 meeting.
2.4Squire Patton Boggs held a webinar on 11 June for Monitoring Officers. This enabled the rationale behind proposed changes to the IAA to be explained in detail. It also introduced the Governance Manual. Engagement with Monitoring Officers has continued since.
2.5At the JC meetings on 18 March, 11 June and 9 September, the Committee were advised of the timetable and next steps for the finalisation of the key governance documents.
3. Progress since Joint Committee meeting on 9 September 2019
3.1A re-circulation of the IAA to the Monitoring Officers for approval took place during October and November. At the time of writing one matter required the consideration of further drafting. This matter is limited to ensuring that references to Operator Agreement(s) are generic rather than specific. This is expected to be largely completed by the time of the Committee’s meeting, at which a verbal update will be given.
3.2As a result of the ongoing engagement with Monitoring Officers, the timetable has been redrafted and the execution of the revised IAA is now expected to commence in the new year. The updated timetable is shown below. 4. Revised timetable for completion of the IAA review and finalisation of the Governance Manual
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.