CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Kent County Council
ACCESS Joint Committee, Monday 9 March 2020 at 11.00am

Business plan, budget & risk summary

Noted Committee 1 paper

ACCESS Joint Committee noted this item on Monday 9 March 2020. Below is the council's own wording, with the papers it was decided on.

Item182

Resolved

RESOLVED that the updated business plan and revised outturn for 2019/20 and the summary risk register be noted.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to ACCESS Joint Committee, 9 pages

Business Plan, Budget & Risk Summary

ACCESS Joint Committee

Date: 9 March 2020

Report by: Officer Working Group

Subject: 2019-20 Business Plan Update and Revised Outturn

Purpose of the To provide an update on the activities undertaken since the last Joint Report: Committee, associated spend and risk summary.

The Committee is asked to note: Recommendations:  the 2019-20 updated Business Plan;  the Revised Outturn; and  Summary Risk Register.

Enquiries to: Name - Kevin McDonald Email - [email removed] 1. Purpose

1.1The Joint Committee is required to make recommendations to the ACCESS Authorities about the Annual Strategic Business Plan for the Pool. The Business Plan for 2019-20 was agreed by the Joint Committee in March 2019 and referred to the relevant ACCESS Authorities.

1.2The Joint Committee also determined the Budget necessary to implement the Business Plan during 2019-20 at their meeting in March 2019 and this has been charged to the relevant ACCESS Authorities.

1.3This report updates the Joint Committee on the work undertaken to date and costs incurred in 2019-20. In addition, a summary of the Risk Register is included.

1.4The JC have subsequently agreed their Annual Strategic Business Plan for the Pool for 2020-21 and this will form the basis of future reporting to the JC.

2. 2019-20 Business Plan Update

2.1The key activities for 2019-20 are as follows:

- ACCESS Support Unit (ASU) recruitment completion - ASU functions transitioned from external advisers to ASU officers and technical leads - Review of the Inter Authority Agreement (IAA) - Tranches 3, 4 and 5 sub funds onboarding - Consideration of non-listed / illiquid assets (including the appointment of bfinance) - Procurement of legal adviser for ACCESS - Consideration of a collective custodian procurement on behalf of ACCESS Authorities - Commencement of the Review of ESG / RI guidelines

2.2The table shows progress against key items delivered since the last Joint Committee as well as the activities in 2020-21 agreed by the JC in December 2019.

2.3Some external advisers have been engaged in relation to the work on the Governance arrangements for the ACCESS Pool, and others have commenced work on the approach towards pooling illiquid assets.

2.4Activities shown in the Business Plan below that are also the subject of separate items on the Committee’s agenda include:

 Governance update  Contract Management update  Risk Register  Engagement with the SAB  Sub-fund implementation  Non listed / alternative assets Change End of Year Position Anticipated from Key Milestone 2019-20 2020-21 previous report Complete Governance Training on Governance Manual delivered to JC in December 2019. Timeline Complete post Change extended to complete IAA Governance Governance Manual to manual update. ensure that there was Work with external opportunity to receive and advisers to reflect decision reflect all feedback from making principles, Monitoring Officers and communication strategy, s151 Officers before policies and procedures, finalising. code of conduct etc in the Governance Manual Will have residual cost relating to training.

Complete Review of Inter Authority At the time of writing it is Complete Agreement expected that an updated execution by Work with external IAA would shortly be participating Change advisers to reflect any circulated to Monitoring Authorities. changes resulting from the Officers. completion of the Governance Manual Agree and establish ASU Officers employed by ACCESS Support Unit Essex as the Host Authority following successful Identify ASU resource recruitment activity requirements, roles and (December 2018 – August responsibilities for 2019). activities, scope and run recruitment activity and ASU functions have been BAU established No change appoint mainly undertaken by ASU Officers and Technical Leads.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Business plan, budget & risk summaryReport 9 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. Business plan, budget & risk summaryThis decision
  2. Governance updates including Draft Business Plan for 2024/25 - 2026/27Noted
  3. Business Plan, Budget and GovernanceNoted
  4. Business Plan, Budget and GovernanceNoted
  5. Business Plan and BudgetNoted
  6. Business plan, Budget & RiskNoted

More from Kent ACCESS Joint Committee

All decisions
MeetingDecisionOutcome
4 Sep 2023 Apologies/SubstitutesRESOLVED that the apologies be noted. Noted Open
4 Sep 2023 Minutes of the meeting held on 5 June 2023RESOLVED that the minutes from the meeting held on 5 June 2023 be signed as a true and accurate record. Decided Open
4 Sep 2023 Chair's remarksRESOLVED that the Chair’s remarks be noted. Noted Open
4 Sep 2023 Business plan, Budget & RiskRESOLVED to note the: a) 2023/24 Business Plan update; b) 2023/24 budget update; and c) risk summary. Motion to Exclu... Noted Open