Resolved
RESOLVED that the proposed amendment of the meeting schedule for 2020/21, the Business Plan update, the current forecast variances against the 2020/21 budget and summary Risk Register be noted.
ACCESS Joint Committee noted this item on Monday 7 September 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the proposed amendment of the meeting schedule for 2020/21, the Business Plan update, the current forecast variances against the 2020/21 budget and summary Risk Register be noted.
Business Plan, Budget & Risk Summary
Quarterly Update
ACCESS Joint Committee
Date: 7 September 2020
Report by: Officer Working Group
Subject: Business Plan, Budget & Risk Summary – Quarterly Update
Purpose of the Report: To provide an update on the activities undertaken since the last Joint Committee, associated spend and risk summary.
The Committee is asked to note:
Recommendations: the proposed amendment of the meeting schedule for 2020/21; the Business Plan update; the current forecast variances against the 2020/21 budget; and summary Risk Register.
Kevin McDonald
Enquiries to: Email: [email removed] 1. Background 1.1. The Business Plan for 2020/21 was agreed by the Joint Committee (JC) in December 2019 prior to being referred to the ACCESS Authorities.
1.2At that meeting the JC also determined the budget necessary to implement this years’ plan and to be charged to the relevant Authorities.
2. COVID-19 and lockdown 2.1. Details of how ACCESS Authorities, ACCESS Support Unit (ASU) and service providers have operated in the light of COVID-19 were highlighted in the Business Plan update provided at the Committee’s last meeting on 17 July 2020. These arrangements broadly continue, and it is anticipated that meetings will be held on a virtual basis for the foreseeable future.
3. Schedule of Joint Committee meetings for the remainder of 2020/21 3.1. The volume of work on a number of milestones within the current years’ Business Plan is significant, which in turn puts a degree of pressure on the size of the agendas being prepared for each of the Committee’s meetings. In view of this, and following dialogue with the Chairman and Vice Chairman, proposals have been developed for a revised schedule for 2020/21 which would see the number of meetings remaining (including 7 September) increase from three to four.
3.2Proposals for the amended meeting schedule, which would increase the total number of meetings in the 2020/21 municipal year from four to five, involve the cancellation of the planned 7 December meeting and the calling of additional meetings in early- mid November and early-mid January. Meeting arrangements will be finalised by the Clerk, in consultation with the Chair and the ASU, and Members will be notified.
4. Business Plan Update 4.1. Activities shown in the Business Plan (at Appendix A to this report) that are also the subject of separate items on the Committee’s agenda include:
Communications Insurance / Sub fund implementation ESG/RI Contract Management update MHCLG pooling submission Scheduled BAU evaluation Risk Register Activities of note not covered elsewhere on the agenda are described below.
Governance theme: operational protocols milestone
4.2Monitoring Officers (MO) from each of the ACCESS Authorities have been sent a copy of the revised Inter Authority Agreement (IAA) in June 2020. At the time of publication, the process of receiving confirmation of agreement from all MOs was being concluded. It is therefore expected that progression to the formal approval of the updated IAA by each Authority will commence shortly. A memo from Clifford Sims at Squire Patton Boggs (ACCESS’s legal advisers) summarising the key changes accompanied by both the revised IAA and a marked up version highlighting the changes since the Committee last saw a draft will be circulated to Joint Committee Members. This memo will also invite individual Authorities to commence their internal governance processes to enable the adoption of the revised IAA. Authorities are asked to liaise with the Clerk of the Joint Committee on progress.
4.3The Officer Working Group has considered the recommendations of the (now ceased) Governance sub-group. Part of this entails work underway developing Terms of Reference for the sub-group structure that supports OWG in delivering key elements of the Business Plan. The Committee will be kept informed of progress.
Alternative / non-listed assets theme: determine approach milestone
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Business Plan and Budget updateReport | 5 pages | DownloadRead as text |
PDF |
Item 5 Appendix 1: Business PlanAppendix | 4 pages | Download |
Follow ACCESS Joint Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Sep 2023 | Apologies/SubstitutesRESOLVED that the apologies be noted. | Noted | Open |
| 4 Sep 2023 | Minutes of the meeting held on 5 June 2023RESOLVED that the minutes from the meeting held on 5 June 2023 be signed as a true and accurate record. | Decided | Open |
| 4 Sep 2023 | Chair's remarksRESOLVED that the Chair’s remarks be noted. | Noted | Open |
| 4 Sep 2023 | Business plan, Budget & RiskRESOLVED to note the: a) 2023/24 Business Plan update; b) 2023/24 budget update; and c) risk summary. Motion to Exclu... | Noted | Open |
| 5 Jun 2023 | Apologies/SubstitutesRESOLVED that the apologies be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.