Emergency Active Travel Programme

Noted Executive 2 papers

Cabinet noted this item on Monday 12 October 2020. Below is the council's own wording, with the papers it was decided on.

Item175

Resolved

Resolved that the report be noted
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Cabinet, 5 pages

From: Michael Payne Cabinet Member, Highways & Transport

Barbara Cooper Corporate Director, Growth, Environment and Transport

To: Cabinet 12 October 2020

Subject: Emergency Active Travel Programme

Non-Key decision

Classification: Unrestricted

Past Pathway of report: Environment and Transport Cabinet Committee – 17 July 2020 and Scrutiny committee – 23 June 2020

Future Pathway of report: n/a

Electoral Division: Countywide

Summary: This paper provides an update on the Department for Transport’s (DfT) Emergency Active Travel Fund.

Recommendation: Cabinet is asked to note the contents of the report.

1. Introduction

1.1This report provides detail of and progress on the Emergency Active Travel Fund (EATF) trials in Kent.

2. Emergency Active Travel Fund

2.1To help local authorities to restart local transport as part of the Government’s Covid-19 recovery roadmap, the Department for Transport (DfT) announced a £250 million Emergency Active Travel Fund.

2.2On 23rd May 2020, the Secretary of State for Transport announced indicative funding allocations for local transport authorities to implement emergency active travel measures supporting cycling and walking facilities.

2.3The funding was provided in 2 tranches, whereby tranche 1 supported the installation of temporary projects for the COVID-19 pandemic. Tranche 2 is for the creation of longer-term projects

2.4The two key aims of the funding were to enable more people to walk and cycle, where possible, and support safe social distancing in areas where people congregate. The suggested measures included:

 implementing road closures  widening footways  installing pop up cycle lanes  provision of temporary cycle parking  addition of social distancing signage.

2.5The requirements on how to submit a proposal were provided on 28th May, with the date for submission some 6 days later.

2.6A compliant proposal was submitted on 5th June. This proposal recognised that the county was in full lockdown, schools remained closed and that people were working from home. The proposal sought to exploit the prevailing traffic conditions insofar as volumes were circa 25% normal levels and cycling use had increased by around 300%.

2.7KCC commissioned a YouGov survey which also highlighted that around 75% of residents in Kent wanted to see active travel schemes to assist them with their travel choices.

2.8Due to the urgency expressed by DfT it was expected that funding would be confirmed and released quickly. However, this did not happen until early July.

2.9Kent was one of only a few authorities to receive 100% of the available allocated funding.

2.10Despite this delay, and in order to meet DfT strict deadlines, officers dedicated significant time and effort, maximising all the time available, to ensure works started within the stipulated 4 weeks and completed within the mandated 8 weeks (25th September).

2.11This unfortunately meant that it was not possible to undertake the extensive consultation and engagement that would normally accompany such schemes. Post project reviews have identified that this is the most significant criticism of the EATF tranche 1 programme nationally.

2.12In the time available officers attempted to develop a variety of schemes and tried to discuss concepts and ideas with local stakeholders and elected members.

2.13Whilst the trials were also shared with each District Leader and Chief Executive, our experience suggests that it would have been beneficial to have had more time to share the scheme information to a wider audience and for a longer period of time.

3. Tranche 1 Trials

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Emergency Active Travel ProgrammeReport 5 pages DownloadRead as text
PDF
Supplementary report Active Travel Cabinet Report 30.9.20 v5Supplementary 5 pages Download

At this meeting

Whole meeting

More from Kent Cabinet

All decisions
MeetingDecisionOutcome
1 Oct 2026 Minutes of the Meeting held on 22 July 2026RESOLVED that the minutes of the meeting held on 22 July 2026 were approved as a correct record. Approved Open
1 Oct 2026 26/00055 - Revenue and Capital Budget Monitoring Report - Q1 2026-27It was RESOLVED that Cabinet agreed to: a) NOTE the revenue and ... view the full minutes text for item 153. Agreed Open
1 Oct 2026 Quarterly Performance Report, Q1 2026-2027It was RESOLVED that Cabinet agreed to note the Quarter 1 Performance Report and the actions being taken to address a... Agreed Open
22 Jul 2026 Minutes of the Meeting held on 25 June 2026RESOLVED that the minutes of the meeting on 25 th June 2026 were a correct record and that they be signed by the Chair. Decided Open
22 Jul 2026 26/00031 - Adoption of the Delivery of Local Government Efficiency (DOLGE) StrategyIt was RESOLVED that Cabinet: (a) Approved and adopted the Delivery of Local Government Efficiency (DOLGE) Strategy ;... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies