Business Plan, budget & risk summary

Noted Committee 3 papers

ACCESS Joint Committee noted this item on Wednesday 13 January 2021. Below is the council's own wording, with the papers it was decided on.

Item236

Resolved

RESOLVED that the Joint Committee: a) Note the 2020/21 updated business plan, the revised outturn and summary risk register. b) recommend the 2021/22 business plan to the ACCESS Authorities; c) accept the recommendation of the s151 Officers from ACCESS Authorities to determine the 2021/22 budget totalling £1.247m to support the proposed business plan.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to ACCESS Joint Committee, 7 pages

2020/21 Business Plan update, revised outturn and Risk Summary

2021/22 Proposed Business Plan and Budget

ACCESS Joint Committee

Date: 13 January 2021

Report by: Officer Working Group

2020/21 Business Plan update, revised outturn and Risk Subject: Summary

2021/22 Proposed Business Plan and Budget

Purpose of the To provide an update on the activities undertaken since the last Report: Joint Committee.

To propose a Business Plan and Budget for 2021/22.

The Committee is asked to note the 2020/21 updated business plan, the revised outturn and summary risk register.

The Committee is also asked to consider the proposed business plan and budget for 2021/22 and

Recommendations:  recommend the 2021/22 business plan to the ACCESS Authorities; and  accepts the recommendation of the s151 Officers from ACCESS Authorities to determine the 2021/22 budget totalling £1.247m to support the proposed business plan.

Kevin McDonald Enquiries to: Email: [email removed] 1. Background 1.1. The Business Plan for 2020/21 was agreed by the Joint Committee (JC) in December 2019 prior to being referred to the ACCESS Authorities.

1.2At that meeting the JC also determined the budget necessary to implement this year’s plan and to be charged to the relevant Authorities.

2. COVID-19 implications 2.1. It is anticipated that meetings will continue be held on a virtual basis.

3. 2020/21 Business Plan – general update 3.1. Activities shown in the Business Plan (Annex A) that are also the subject of separate items on the Committee’s agenda include:

 Environmental, Social Governance (ESG) / Responsible Investment (RI)  Alternative / illiquid assets  Sub-fund implementation  Contract Management  Scheduled BAU evaluation

3.2A workshop on Communications is planned after the JC’s meeting has concluded.

3.3As notified at the JC’s September meeting Authorities are in the process of adopting the revised ACCESS Inter Authority Agreement (IAA). 4. 2020/21 Business Plan – review of size & scope of ACCESS Support Unit 4.1. The 2020/21 Business Plan includes a review of the size and scope of the ACCESS Support Unit (ASU). The key milestones in the review are set out below:

Date Activity 1 October 2020 Discussion paper 1 issued to OWG October & Interim ASU Director undertakes virtual visits to each Authority November Late November Discussion paper 2 issued to OWG 3 December OWG agreement to proposals 11 December S151 officers’ agreement to proposals 13 January 2021 Joint Committee

4.2The first discussion paper noted that the current size of the ASU was based on consideration of a scenario that none of the Authorities had at that time encountered, and itself was a compromise. The strong levels of collaboration and engagement were highlighted along with the high value placed on the work of both Technical Leads in supporting key workstreams and Kent County Council in providing Secretariat service. The increased workload on LGPS Authorities, stemming from pooling, but also other matters (e.g. McCloud) were outlined. The paper noted the growing complexity of workstreams and the lack of resilience within the current ASU structure. Analysis of the existing ASU officer role profiles indicated implicit rather than explicit reference to pool’s most fundamental stakeholders - the ACCESS Authorities. The requirements were noted of both effective contract and supplier relationship and the expanded officer group structure which commenced in September:

Former officer group structure (pre lockdown)

OWG

Onboarding Reporting Governance sub-group sub-group sub-group

New officer group structure (from September 2020)

OWG

Active listed Non listed Reporting Investment ESG/RI task & sub-group sub-group sub-group user group finish group 4.3. Common themes discussed during the virtual visits were:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Business Plan, budget & risk summaryReport 7 pages DownloadRead as text
PDF
Item 5 Business Plan Annex AAppendix 4 pages Download
PDF
Item 5 Business Plan Annex B 2021-22 budgetAppendix 8 pages Download

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. Business Plan, budget & risk summaryThis decision
  2. Governance updates including Draft Business Plan for 2024/25 - 2026/27Noted
  3. Business Plan, Budget and GovernanceNoted
  4. Business Plan, Budget and GovernanceNoted
  5. Business Plan and BudgetNoted
  6. Business plan, Budget & RiskNoted

More from Kent ACCESS Joint Committee

All decisions
MeetingDecisionOutcome
4 Sep 2023 Apologies/SubstitutesRESOLVED that the apologies be noted. Noted Open
4 Sep 2023 Minutes of the meeting held on 5 June 2023RESOLVED that the minutes from the meeting held on 5 June 2023 be signed as a true and accurate record. Decided Open
4 Sep 2023 Chair's remarksRESOLVED that the Chair’s remarks be noted. Noted Open
4 Sep 2023 Business plan, Budget & RiskRESOLVED to note the: a) 2023/24 Business Plan update; b) 2023/24 budget update; and c) risk summary. Motion to Exclu... Noted Open