21/00007 Urban Traffic Management and Control (UTMC) Project
ApprovedExecutive3 papers
Growth, Environment & Transport Cabinet Committee approved this item on Tuesday 19 January 2021. Below is the council's own wording, with the papers it was decided on.
RESOLVED to endorse the proposed decision of the Cabinet Member for Highways and Transport to accept the capital grant from Ebbsfleet Development Company, to take the UTMC project through the stages of development and delivery and specifically for approval: (a) for KCC to enter into a funding agreement with EDC subject to the approval of the Corporate Director of Finance, Corporate and Strategic Services; (b) to undertake the design and surveys for the UTMC project. The design work will be undertaken by the KCC Traffic and Network Solutions team; (c) to progress all statutory approvals or consents required for the schemes, including transfer of land and rights; (d) to carry out any additional consultation required for the scheme; (e) to enter into construction contracts as necessary for the delivery and future maintenance of the scheme; (f) for any further decisions required to allow the scheme to proceed through to delivery to be taken by the Corporate Director of Growth, Environment & Transport under the Officer Scheme of Delegations following prior consultation with the Cabinet Member.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Name of decision, policy, procedure, project or service: Upgrade the existing Urban Traffic Management and Control (UTMC) system by ensuring the traffic signal junctions within or adjacent to Ebbsfleet Garden City are utilising the latest control systems and standards.
Brief description of policy, procedure, project or service There is a need to improve the traffic signal infrastructure in the Ebbsfleet Garden City are and provide better network management and control systems. This will be achieved by improving the current highway assets using our existing maintenance service provider as part of our statutory duty to look after equipment and an obligation to ensure informed, reliable journeys by managing traffic flows.
Aims and Objectives The aim of the upgrade works is to enhance the existing Urban Traffic Management and Control (UTMC) system by ensuring the traffic signal junctions within or adjacent to Ebbsfleet Garden City are utilising the latest control systems and standards.
Date Document Updated 18/12/2020 1
This document is available in other formats. Please contact [email protected] or telephone on 03000 415 762 JUDGEMENT The beneficiaries of the upgrade works are the highway users in the Dartford and Gravesham area using the highway network on a daily basis. This includes improved road safety and the provision of safe opportunities for pedestrians to cross highly trafficked roads, as well as more reliable journey times for bus services, including Fastrack. Every traffic signal junctions will be brought up to the latest design standards with more resilient equipment, including: • Dropped, flush kerbs with tactile paving to indicate the crossing location and direction with rotating cones beneath the push button unit to allow those with visual impairments to use the crossing safely. • Red/green man indicators on the near-side posts to provide a visual reference of the safe opportunities to cross and use detection equipment to monitor the pedestrians and adjust the timings to benefit those with mobility issues. • Communications linked back to the central Highway Management Centre systems to offer more dynamic and coordinated network control with remote access to make timing plan changes and fault identification.
These are existing assets on the highway network and the works will maintain full and safe operation of the traffic lights during the improvements.
No consultation has been undertaken as this project will retain the current provision with minimal disruption during construction and the works are in line with our statutory duty to maintain assets on the highway network.
There are no adverse impacts for any of the protected characteristics but there are some benefits to the young, elderly, those with sight and mobility impairments, as well as those from other protected groups.
I have found the Adverse Equality Impact Rating to be Low
Date Document Updated 18/12/2020 2
This document is available in other formats. Please contact [email protected] or telephone on 03000 415 762 GET Document Control Revision History
Version Date Authors Comment
V0.1 14/12/2020 Toby Butler Initial version
V1 (this should be assigned to the version the Director signs off)
Document Sign-Off (this must be both the relevant Head of Service and the relevant Director) Attestation I have read and paid due regard to the Equality Analysis/Impact Assessment. I agree with the actions to mitigate any adverse impact(s) that has /have been identified.
Name Signature Title Date of Issue Tim Read Head of Service 18/12/20
Date Document Updated 18/12/2020 3
This document is available in other formats. Please contact [email protected] or telephone on 03000 415 762 Simon Jones Director 18/12/20
Date Document Updated 18/12/2020 4
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.