RESOLVED to endorse the proposed decision of the Cabinet Member for Highways and Transport to: a) Approve all acts required to carry out and complete the Dover Fastrack scheme; b) approve all acts required to acquire the land and rights for the carrying out and completion of the Dover Fastrack scheme, including by means of a compulsory purchase order; c) approve the delegation to the Interim/Corporate Director of Growth, Environment & Transport under the Officer Scheme of Delegations following prior consultation with the Cabinet Member, any further or other decisions as may be appropriate to deliver the Dover Fastrack scheme; d) approve the delegation to the Interim/Corporate Director of Growth, Environment & Transport under the Officer Scheme of Delegations following prior consultation with the Cabinet Member, any further or other decisions as may be appropriate to deliver the Dover Fastrack scheme; and e) confirm that other decisions in Record of Decision 19/00053 remain extant.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Environment & Transport Cabinet Committee, 7 pages
From: David Brazier – Cabinet Member for Environment & Transport
Simon Jones – Interim Corporate Director of Growth, Environment & Transport
To: Environment & Transport Cabinet Committee – 29 June 2021
Decision No: 21/00047
Subject: Dover Fastrack – Compulsory Purchase Order
Classification: Unrestricted
Past Pathway of Paper: None
Future Pathway of Paper: None
Electoral Division: Dover West, Dover North, and Dover Town
Summary: Approval to use of compulsory purchase to secure the land and rights required for the scheme and to give programme certainty.
Recommendation(s):
The Environment and Transport Cabinet Committee is asked to consider and endorse, or make recommendations to the Cabinet Member for Highways and Transport on, the proposed decision as follows and as indicated on the proposed decision sheet attached at Appendix D.
i) to approve all acts required to carry out and complete the Dover Fastrack scheme;
ii) to approve all acts required to acquire the land and rights for the carrying out and completion of the Dover Fastrack scheme, including by means of a compulsory purchase order;
iii) to approve the delegation to the Interim/Corporate Director of Growth, Environment & Transport under the Officer Scheme of Delegations following prior consultation with the Cabinet Member, any further or other decisions as may be appropriate to deliver the Dover Fastrack scheme;
iv) to confirm that other decisions in Record of Decision 19/00053 remain extant.
1. Introduction
1.1Dover Fastrack will provide a high quality and reliable public transport service for 5,750 new homes that are part of the Whitfield Urban Expansion, the White Cliffs Business Park, and other housing development at Connaught Barracks, to link with Dover Town Centre and the high-speed rail services at Dover Priory Station. 1.2 Previously known as Dover Bus Rapid Transport, the project has been renamed Dover Fastrack as it will form a key part of the Fastrack service building on the successful system operating in north Kent. Fastrack is a key component of Kent’s Bus Strategy.
1.3Dover Fastrack will provide essential transport infrastructure to support the delivery of Whitfield Urban Expansion identified in Dover District’s Local Plan Core Strategy 2010 that identified the need to provide 14,000 new homes across the District. The continuing need for this infrastructure is endorsed in the current review of the Local Plan that covers the period up to 2040.
1.4Housing build out has been slower than expected but development is underway for Phase 1 of the Whitfield Urban Expansion and planning permission has recently been granted for 300 homes at Connaught Barracks.
1.5The overall Fastrack route will mainly be delivered through provision of new roads within the housing developments. Part of the route will utilise the existing highway network. Junction improvements at Castle Hill Road will be delivered as part of the proposed Connaught Barracks Development which is owned by Homes England. However, new infrastructure specific to the scheme will also be required as follows:
a) New A2 overbridge for bus/ pedestrian and cycle access. b) New dedicated bus link through White Cliffs Business Park to Dover Road. c) Localised widening of Dover Road.
1.6Dover District Council carried out extensive public engagement to raise public awareness when the Local Plan was developed which includes policies specific to Whitfield Urban Expansion. They also recently consulted on a proposed revision to the Local Plan. There was specific public engagement on the Dover Fastrack scheme in summer 2020, in advance of submitting the planning application, and as part of that process an overview of the project was given in a leaflet that is included in Appendix A.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.