Resolved
It was RESOLVED that the current position be noted and that the committee supported the proposed approach and would receive an update on the Project Gigabit Broadband Programme at a future meeting.
Growth, Economic Development and Communities Cabinet Committee noted this item on Wednesday 17 November 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
It was RESOLVED that the current position be noted and that the committee supported the proposed approach and would receive an update on the Project Gigabit Broadband Programme at a future meeting.
From: Derek Murphy, Cabinet Member for Economic Development
Simon Jones, Corporate Director for Growth, Environment & Transport
To: Growth, Economic Development and Communities Cabinet Committee - 17 November 2021
Subject: ‘Project Gigabit’ Broadband Programme
Classification: Unrestricted
Past Pathway of report: None
Future Pathway of report: Publication
Electoral divisions: All
Summary: The purpose of this paper is to update Cabinet Committee Members on:
i) the Government’s new national ‘Project Gigabit’ broadband programme – including the proposal to allocate up to £203 million of new capital funding to improve broadband connectivity across Kent and Medway.
ii) how the Project Gigabit programme will be delivered across Kent.
Recommendation Cabinet Committee Members are asked to note the current position and support the proposed approach.
1. Introduction
1.1On the 2nd of August 2021, the Government published further information on their new ‘Project Gigabit’ broadband programme (formerly known as the ‘Outside-In Programme’).
1.2The Project Gigabit programme seeks to deliver future-proofed gigabit- capable broadband connections across the UK. Gigabit capable connections offer download speeds of at least 1 gigabit-per-second (1 Gbps) or 1000 megabits per second (Mbps) and are usually delivered through full-fibre connections (i.e., fibre-to-the-premise). Increasingly, these faster and higher capacity connections will be required to ensure that Kent’s digital infrastructure is able to meet future demand.
1.3The national targets and objectives for the Project Gigabit Programme, (which is being led by Building Digital UK1 (BDUK)), are as follows:
1 This is part of the Department for Digital, Culture, Media & and Sport (DCMS) 85% of UK premises to have gigabit coverage by 2025 with the aim of achieving ‘near universal coverage as soon as possible’ but before the end of the decade. Commercial investment (i.e., upgrades funded by telecoms providers) to provide gigabit capable connections to 80% of homes and businesses across the UK. The remaining 20% of properties that remain outside the scope of commercial investment to be connected via new government-funded programmes. £5 billion has currently been allocated to fund these connections – and the Government’s intention is for properties that cannot currently access a superfast broadband connection to be prioritised wherever possible within the new programme.
1.4The new Project Gigabit Programme will build upon the work of the Kent BDUK Superfast Project which, since 2013, has connected over 143,000 homes and businesses across Kent with faster broadband connections. As a result of this work, 96% of homes and businesses in Kent now have access to a broadband service of at least 24megabits per second.
2.0Delivering Project Gigabit in Kent.
2.1Under the Government’s current plans, the Project Gigabit programme targets will be delivered via three workstreams. These are explained in more detail below.
Workstream 1: Commercial build programme
2.2BDUK expect the majority of gigabit connections (at least 80%) to be funded by telecoms operators and not require public subsidy. These market-led investments are known as commercial build.
2.3Over the past year, we have seen a significant increase in telecoms providers announcing upgrade programmes across Kent for gigabit capable connections. The availability of gigabit-capable connections across Kent is currently 44.0% (compared to 7.8% in January 2020). Operators such as Trooli, Virgin, City Fibre, Neotomia and Openreach have already announced substantial further investments in Kent.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
'Project Gigabit' Broadband ProgrammeReport | 5 pages | DownloadRead as text |
Follow Growth, Economic Development and Communities Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Nov 2025 | Election of ChairRESOLVED that [name removed] be elected as Chair of the Growth, Economic Development and Communities Cabinet Committee. | Decided | Open |
| 11 Nov 2025 | Minutes of the meeting held on 11 September 2025RESOLVED that the minutes of the meeting held of 11 September 2025 were a correct record and they be signed by the Ch... | Decided | Open |
| 11 Nov 2025 | KMEF- Ambition 2- Widen opportunities and unlock talentRESOLVED to note the report. | Noted | Open |
| 11 Nov 2025 | Regional Energy Strategic PlanRESOLVED to note the report. | Noted | Open |
| 11 Nov 2025 | Decisions taken between Cabinet Committee Meetings- 25/00084It was agreed that consideration would be given to Member involvement in the reinstated Visitor Economy and Inward In... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.