Resolved
RESOLVED that the report be noted.
Scrutiny Committee noted this item on Wednesday 20 July 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the report be noted.
From: Rebecca Spore, Director of Infrastructure
To: Peter Oakford, Deputy Leader and Cabinet Member for Finance, Corporate and Traded Services
Subject: Inflationary Pressures on Capital Construction Programmes
Key Decision: Expenditure or savings of more than £1m and affects more than 2 Electoral Divisions
Classification: UNRESTRICTED
Future Pathway of Paper: Policy and Resources Cabinet Committee
Electoral Division: All
Summary: The national fiscal and economic context is an important consideration for the Council in setting and managing its revenue and capital budgets. The budget report to County Council on 10 February referred to the extraordinary and unexpected challenge to the UK economy and economies across the world arising from the COVID-19 pandemic. Kent County Council (KCC) has a significant Capital Construction Programme, which has been adversely impacted by the inflationary pressures facing the UK construction industry.
This report seeks to ensure that KCC has sufficient capital allocated and effective contractual management arrangements in place to deliver the programmes and projects, with anticipated additional costs as set out in the Medium-Term Financial Plan. A decision is required to implement these in the time available to avoid disruption to front line services and to secure the contractual arrangements for the provision of key infrastructure projects, including the provision of school places to meet KCC’s statutory duties.
Recommendation(s): The Deputy Leader and Cabinet Member for Finance, Corporate and Traded Services is asked to consider and endorse or make recommendations on the proposed decision to:
1. note the £28.8 million estimated impact on capital budget spend in the Medium-Term Financial Plan of £339.3 million across the capital programme for 2022-23, were already approved via key decision or covered by appropriate delegated authority to be funded from the options identified in paragraph 5.9 of this report;
2. consider the use of Fluctuation clauses when deemed necessary to control costs to KCC and alleviate adverse effects to the main contractor supplier of the rise in material costs; and
3. delegate authority to the Director of Infrastructure or the Corporate Director of Growth, Environment and Transport (for Highway Schemes), in consultation with the Corporate Director of Finance and the Deputy Leader and Cabinet Member for Finance, Corporate and Traded Services, to take the necessary actions, including but not limited to entering into contracts and other necessary documentation to enable the delivery of the capital programme taking into account construction and inflation where existing Record of Decisions levels are needed to be adjusted. 1. Introduction
1.1The construction industry, in the past year has experienced acute inflation pressures, long material lead times and sporadic material supply. This has been directly linked to material and labour shortages. The identified key causes of the shortages are the effects of:
COVID-19 Pandemic on; the manufacturing industry; sudden increase in demand on the construction industry post the global lockdown and decreased supply chain due to administrations. Brexit on; supply of construction workers and hauliers to transport the construction material and complying with regulations. Changes in UK Government legislation and Building Regulations and requirement to meet Net Zero targets. Rising cost of wholesale energy. Indirect effects of the Russian invasion of Ukraine.
1.2This report seeks to inform on the impact that cost inflation and the sporadic supply of materials has had, and will continue to have, on KCC’s capital programme budgets and the delivery programme. The report will also suggest mitigation measures to assist in reducing the impact of the cost inflation where possible.
2. Current Position
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Decision Report 22-00050Decisions | 12 pages | DownloadRead as text |
PDF |
Inflationary Pressures on Capital Construction Programmes (Decision 22/00050)Decisions | 1 pages | Download |
PDF |
Record of DecisionDecisions | 2 pages | Download |
Follow Scrutiny Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Aug 2026 | Minutes of the meeting held on 11 June 2026RESOLVED that the minutes of the meeting held on 11 June 2026 were a correct record and they be signed by the Chair. | Decided | Open |
| 3 Aug 2026 | Work ProgrammeIt was agreed that LGR related matters would initially be considered by the relevant Cabinet Committee and could subs... | Agreed | Open |
| 1 Jul 2026 | Minutes of the meeting held on 13 May 2026RESOLVED that the minutes of the meeting held on 13 May 2026 were a correct record and they be signed by the Chair. | Decided | Open |
| 1 Jul 2026 | Work ProgrammeRESOLVED to note the . | Noted | Open |
| 13 May 2026 | Minutes of the meeting held on 3 March and 1 April 2026RESOLVED that the minutes of the meetings held on 3 March and 1 April 2026 were a correct record and they be signed b... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.