Subject: Reconnect: Kent Children and Young People - Evaluation of Programme
Classification: Unrestricted
Past Pathway of report: Cabinet – 1 December 2022
Future Pathway of report: Scrutiny Committee - 25 January 2023
Electoral Division: All
Summary: This report sets out the achievements of the Reconnect: Kent Children and Young People Programme.
Recommendation(s): County Council is asked to note the report.
1. Introduction
1.1In March 2021, Cabinet approved (21/00035) that work begin to deliver the Reconnect: Kent Children and Young People Programme, as a response to the Covid-19 pandemic. Members from all parties recognised that Kent’s children and young people (C&YP) had all been affected by the pandemic. They agreed it was essential that C&YP be supported to re-engage with activities and opportunities that they had enjoyed before the pandemic, and to try something new.
1.2Formal approval for Reconnect was provided in Key Decision 21/00042 by Cabinet in June 2021. This set out the parameters within which the programme would operate, key of which were:
This would be a KCC led, community-based programme, which sought to engage the whole Kent community in supporting C&YP It aimed to reconnect C&YP to: o Learning missed o Health and happiness o Friends, family and community o Sports, activities and the outdoors o Economic wellbeing o It was to be universal, with something for all C&YP aged 0-19 years (up to 25 for those with SEND) o It would promote existing opportunities for C&YP to connect or reconnect to, fund and empower others to create additional opportunities o It should focus on the future, not dwell on the negatives of the pandemic o The voice of young people would be at the heart of the programme o Funding should be spent equally against each theme if possible o A quarter of the funding would be spent locally, via Local Children’s Partnership Groups
1.3This paper provides a summary of the evaluation of the programme. A full evaluation report is available at: https://www.kent.gov.uk/__data/assets/pdf_file/0006/141909/Reconnect- Evaluation-Report.pdf
1.4The programme was always intended to be fixed-term, ending on 31st August 2022, to provide immediate support post pandemic. Following agreement by Cabinet in July 2022, most activity and the public brand closed as planned, but some further support has been commissioned to run until 31 March 2023. This report covers the activity to 31 August 2022 only.
2. Evaluation - Outcomes and Impact
2.1It was recognised from the outset that the wide-ranging nature of activities and support which would be provided to C&YP would make it challenging to evidence impact, particularly trying to assign a direct causal link to the work of Reconnect; for example, demonstrating Reconnect has improved the achievement of pupils in maths, as opposed to this success being down to staff in schools, the support of parents and the hard work of the C&YP themselves.
2.2The programme’s evaluation findings, conclusions and recommendations are drawn from semi-structured interviews, digital surveys, and data returns (i.e., case studies, quotations and other data providers have submitted). The data included in the findings is a minimum level of achievement. Participation numbers, for example, will be “at least” that reported, because in some cases providers could not count all the children participating (e.g. a family fun day), while in others the data provided by participants hides participation levels (to illustrate, one child minder registered to participate in the Big Summer Challenge, but all 12 of the children she looked after took part), and we have missing data returns.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Reconnect UpdateReport | 29 pages | DownloadRead as text |
Follow County Council at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Minutes of the meeting held on 21 May 2026RESOLVED that the minutes of the Council meeting held on 21 May 2026 were a correct record and they be signed by the ... | Decided | Open |
| 16 Jul 2026 | Corporate Parenting Panel - Minutes for notingRESOLVED that the minutes of the meeting of the Corporate Parenting Panel on 17 February 2026 and 21 April 2026 be no... | Noted | Open |
| 16 Jul 2026 | Chairman's AnnouncementsAgreed unanimously. The Chairman held a one-minute silence in memory of [name removed]. RESOLVED that the Council for... | Agreed | Open |
| 16 Jul 2026 | Kent Minerals Sites PlanRESOLVED that Council: 1. (i) Approves, and publishes, a Pre-Submission Draft of the updated Kent Mineral Sites Plan ... | Approved | Open |
| 16 Jul 2026 | Quarterly Performance Report - Year End 2025/26RESOLVED that Council: NOTES the Performance Report. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.