Policy and Resources Cabinet Committee, Thursday 9 March 2023 at 10.00am

Minor Works Construction Partnership Framework - Update

Noted Executive 2 papers

Policy and Resources Cabinet Committee noted this item on Thursday 9 March 2023. Below is the council's own wording, with the papers it was decided on.

Item135

Resolved

RESOLVED to note the preferred procurement option and timetable for this activity.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Policy and Resources Cabinet Committee, 8 pages

Recommendation

The Policy and Resources Cabinet Committee is asked to note the preferred procurement option and timetable for this activity.

1. Introduction

1.1The Minor Works programme consists of small individual packages of work traditionally under £1m. The categories of work include general maintenance, roofing, boilers and windows across corporate and educational sites.

1.2Projects valued under £50k within this programme were typically delivered by the Total Facilities Management (TFM) contractors either through their supply chains or for larger value works, through individual competitive competition. The TFM contracts expired on 31 October 2022. Currently these works are in part being delivered through the new Hard Facilities Management (FM) contract recently awarded to Skanska or through individual competition managed by in-house Kent County Council (KCC) minor works team. Where a competition is run the tender list would include nomination of a number of suppliers from KCC’s contractor lists on a rotational basis. The KCC contractor lists, although closed in recent years to new applicants, contain many suppliers.

1.3Total spend between financial years of 19/20 to 21/22 has been circa £40m. This is broken down in Appendix A which has categorised the spend over nine disciplines. The forecasted spend for 22/23 has also been included. 2. Delivery models

2.1Four options for the future provision of these works have been set out below:

Option 1 – Commission these works through the Hard FM Contract Discounted as contract has evolved since TFM and does not include these works within the core delivery.

Option 2 – Competitively tender individual work packages Discounted as this will require substantial administration and does not allow KCC to work with a contained supply chain to deliver its future pipeline.

Option 3 – Use External Frameworks Discounted as unlikely to access Kent based contractors. KCC would pay a margin for the use of other Frameworks.

Option 4 – Minor Works Framework approach Carried Forward

2.2The value of the procurement is above the Public Contract Regulations (PCR 2015) threshold of £213,499 (including VAT) for goods and services, and therefore needs to be procured and advertised in accordance with PCR 2015.

2.3It is proposed to procure a Minor Works Framework. This report sets out the benefits and challenges facing the Council and its partners to implement this strategy, and the planned procurement process to select the Framework suppliers.

3. Minor Works Framework

3.1The spend analysis conducted found that, since the 2019/20 financial year, there have been over 120 different companies commissioned to deliver minor works projects.

3.2It is proposed that KCC develops a Minor Works Framework with fewer contractors to deliver the future work pipeline. If adopted, this will lead to significant change in the way that the Council delivers this programme, allowing greater opportunity to standardise components and streamline processes when appointing and overseeing a contractor undertaking the works.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 8 Appendix B: EQIA: Minor Works FrameworkAppendix 4 pages Download
PDF
Minor Works Construction Partnership Framework: UpdateReport 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. Minor Works Construction Partnership Framework - UpdateThis decision
  2. Proposal SW/07/902 - Creation of a children's centre within existing redundant space and minor internal works including the erection of a canopy in front of Cedar Block at Grove Park Primary School, Hilton Drive, Sittingbourne; KCC Children, Families and Education.Decided

More from Kent Policy and Resources Cabinet Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Minutes of the meeting held on 6 May 2026RESOLVED that the minutes of the meeting held on 6 May 2026 were a correct record and that they be signed by the Chai... Decided Open
2 Jul 2026 Local Outcomes FrameworkRESOLVED that the report be noted. Noted Open
2 Jul 2026 Budget Planning Process 2027-28 and Medium-Term Financial Plan (MTFP) UpdateRESOLVED that the report be noted. Noted Open
2 Jul 2026 26/00032 - Adoption of the KCC Winning for Kent: Procurement with Purpose Policy 2026-2028RESOLVED that the Cabinet Committee endorses the proposed decision to: (a) Approve the adoption and implementation of... Approved Open
2 Jul 2026 Work ProgrammeRESOLVED that the work programme be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies