23/00047 - Cyclopark Operator Agreement (OA) and Funding
ApprovedExecutive3 papers
Growth, Economic Development and Communities Cabinet Committee approved this item on Tuesday 16 May 2023. Below is the council's own wording, with the papers it was decided on.
RESOLVED to: 1. Endorse the decision: (a) to approve a retrospective Deed of Variation to the Operator Agreement between KCC and Cyclopark Trust for the operation of the park and continuation of KCC financial support for the period 27 May 2022 to 26 May 2032 (10 Years) and; (b) that authority be delegated to the Director of Growth and Communities to take appropriate actions in accordance with the terms of the Operator Agreement as necessary to implement this decision. 2. Ask the Cabinet Member for Economic Development to put forward sufficient improvements to security to ensure the safety of the facility.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Economic Development and Communities Cabinet Committee, 10 pages
From: Derek Murphy, Cabinet Member, Economic Development
Simon Jones, Corporate Director of Growth, Environment and Transport
To: Growth, Economic Development & Communities Cabinet Committee - 16 May 2023
Subject: Cyclopark Operator Agreement
Key Decision 23/00047
Classification: Unrestricted
Past Pathway of paper: N/a
Future Pathway of paper: Cabinet Member Decision
Electoral Division: All
Summary: Cyclopark is a unique 43-acre sports and community facility built on redundant land made available because of the realignment of the A2 trunk road south of Gravesend and opened in May 2012 as a legacy project to the London Olympic and Paralympic Games.
The park is owned by KCC and operated on KCC’s behalf by a charitable trust (Cyclopark Trust) specifically established for the purpose. KCC entered into a contractual agreement with Cyclopark Trust, the ‘Operator Agreement,’ covering May 2012 to 26 May 2022 (10 years) which covers lease of the land, commuted sum funding from (the then) Highways Agency and wider funding and operating arrangements.
A new deed of variation (retrospective) is required to extend the agreement for a further 10 years for the Cyclopark Trust to continue to operate the venue on behalf of KCC. This is possible under the Section 31 (31.2) of the Operator Agreement.
Work commenced October 2021 with Invicta Law Limited. A draft Deed of Variation for review was received 29 April 2022 and circulated to Cripps solicitors acting for the Cyclopark Trust. Comments were received back, and a final version was agreed in principle 29 June 2022. It has not been possible to bring this for decision until now during which time KCC continued to support the Trust during 22-23 under the same terms as stated in the original Operator Agreement to ensure continuity of service provision.
Changes to the Operator Agreement require a Deed of Variation to be approved by both parties. Recommendation(s): The Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for Economic Development: (a) to approve a retrospective Deed of Variation to the Operator Agreement between KCC and Cyclopark Trust for the operation of the park and continuation of KCC financial support for the period 27 May 2022 to 26 May 2032 (10 Years) and;
(b) that authority be delegated to the Director of Growth and Communities to take appropriate actions in accordance with the terms of the Operator Agreement as necessary to implement this decision
as shown at Appendix 1.
1. Introduction
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Economic Development and Communities Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.