From: Neil Baker Cabinet Member for Highways and Transport
Simon Jones, Corporate Director Growth, Environment and Transport
To: Environment & Transport Cabinet Committee – 14 September 2023
Subject: Drainage Infrastructure Maintenance - Report
Classification: Unrestricted
Electoral Division: Countywide
Summary: This report details the Drainage Infrastructure Maintenance operational activity; (revenue, capital and emergency works), new initiatives and outlines some of the current and future challenges to the service.
Recommendation(s): The Environment and Transport Cabinet Committee is asked to note the report.
1. Introduction
1.1The County Council is responsible for the maintenance of 5,400 miles of public highway including 250,000 road drains and associated drainage systems.
1.2Highway Drainage is the second largest asset group after Road and Footways. The primary objectives of the highway drainage system are:
Removal of highway surface water from the highway to help keep roads safe and minimise problems. prevent damage and make roads last longer through effective drainage. minimise surface water from the highway affecting properties or land.
1.3Highway flooding and drainage issues generate around 9,000 customer enquiries every year. Most drainage enquiries relate to blocked drains, carriageway flooding and flooding to private property. All drainage and flooding enquiries are risk assessed and prioritised on the basis of:
Risk to private property flooding (internal residential or business only) Risk to Strategic and Locally Important Road (impassable flooding or impact to traffic movement) Risk to area of local importance (e.g. Schools, Nurseries, GP Surgeries, Hospital, Health Centre, Residential homes etc, Controlled Pedestrian Crossings) Is the speed limit above 50mph with a risk to aquaplaning or a higher risk location (e.g., bend or approach to busy junction) 1.4 Due to the varied nature of drainage issues dealt with by the County Council, the time taken to resolve a drainage enquiry varies from a few hours to several months.
1.5Since April 2022 we have:
received over 12,610 customer enquiries relating to drainage and flooding. responded to over 574 reports of flooding emergencies (2-hour response) inspected and cleansed over 118,905 drains on the cyclical programme.
1.6The volume of enquiries received is influenced by the weather with peaks in demand during the winter months and flash flooding that occurs during summer months. 1.7 The drainage team currently has 25 staff covering the County. Although the team increased the size in 2019, staffing resources are limited. There is one drainage engineer per district (except Dartford and Gravesham and Thanet and Dover, where one engineer covers each pair of districts). For drainage schemes, there are two engineers covering the entire county.
2. Revenue Funded Drainage Maintenance
2.1We recently adopted a pro-active risk-based approach, following the Well Managed Highway infrastructure and our approach to Asset Management of the Highway. This shift aims to achieve more cleansing activity per public pound by delivering a proactive risk-based service.
2.2Our new approach considers many factors attaining to various risks across the highway network such as road hierarchy, speed limit or whether it is a known flood zone. These factors combined will produce individual risk weightings for every road.
2.3Maintaining over 250,000 highway drains across the county we now aim to cleanse all highway drains on a countywide programme at least every three years with an annual cleansing of our Strategic Network (57000 gullies) and High-Speed Road Network (9000 gullies); with r Minor Network (56000 gullies) adopting a risk-based approach which could involve an annual, bi annualy or triannual check;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Drainage Schemes FY23 24Appendix A | 2 pages | Download |
PDF |
Drainage Infrastructure MaintenanceReport | 7 pages | DownloadRead as text |
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... | Decided | Open |
| 5 May 2026 | Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... | Decided | Open |
| 5 May 2026 | Winter Service UpdateRESOLVED to note the Winter Service Update . | Noted | Open |
| 5 May 2026 | Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. | Noted | Open |
| 5 May 2026 | 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.