Resolved
RESOLVED to note the Performance Dashboard.
Growth, Environment & Transport Cabinet Committee noted this item on Wednesday 15 November 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the Performance Dashboard.
Appendix 1
Environment and Transport Performance Dashboard
Financial Year 2023/24 Results up to August / September 2023
Produced by Kent Analytics
1 Appendix 1
Guidance Notes Data is provided with monthly frequency except for Waste Management and Greenhouse Gases where indicators are reported with quarterly frequency and as rolling 12-month figures to remove seasonality.
RAG RATINGS
GREEN Target has been achieved
AMBER Floor Standard* achieved but Target has not been met
RED Floor Standard* has not been achieved
*Floor Standards are the minimum performance expected and if not achieved must result in management action
Activity Indicators
Activity Indicators representing demand levels are also included in the report. They are not given a RAG rating. Instead, they are tracked within an expected range represented by Upper and Lower Thresholds. The Alert provided for Activity Indicators is whether they are within their expected range or not. Results can either be within their expected range (Yes), or Above or Below their expected range.
2 Appendix 1 Key Performance Indicators Summary
Monthly YTD Highways & Transportation RAG RAG Environment & Waste RAG
HT01 : Potholes repaired in 28 calendar days AMBER RED WM01 : Municipal waste recycled and composted AMBER (routine works not programmed) HT02 : Faults reported by the public completed in GREEN AMBER WM02 : Municipal waste converted to energy GREEN 28 calendar days HT04 : Customer satisfaction with service WM01 + WM02 : Municipal waste diverted from AMBER AMBER GREEN delivery (100 Call Back) landfill HT08 : Emergency incidents attended to within 2 WM03 : Waste recycled and composted at GREEN RED AMBER hours HWRCs HT12 : Streetlights, illuminated signs and bollards WM04 : Percentage of HWRC waste recycled GREEN GREEN AMBER repaired in 28 calendar days and wood converted to energy at biomass facility HT14 : Priority (Member) Enquiries completed WM08 : Overall score for mystery shopper RED RED GREEN within 20 working days assessment of HWRCs WM10 : Customer satisfaction with HWRCs GREEN EW2 : Greenhouse Gas emissions from KCC GREEN estate (excluding schools) EW1 : Percentage of statutory planning consultee Digital Take up RAG GREEN responses submitted within 21 days DT01 : Percentage of public enquiries for DT05 : Percentage of HWRC voucher GREEN GREEN Highways Maintenance completed online applications completed online DT03 : Percentage of concessionary bus pass GREEN applications completed online DT04 : Percentage of speed awareness courses GREEN booking completed online
3 Appendix 1 Division Corporate Director Cabinet Member Highways & Transportation Simon Jones Neil Baker
Key Performance Indicators Year Month YTD Prev. Ref Indicator description May-23 Jun-23 Jul-23 Aug-23 to Target Floor RAG RAG Yr Date Potholes repaired in 28 calendar HT01 75% 77% 87% 85% AMBER 79% RED 90% 80% 76% days Faults reported by the public HT02 73% 83% 86% 90% GREEN 81% AMBER 90% 80% 84% completed in 28 calendar days Customer satisfaction with service HT04 89% 90% 87% * AMBER 90% AMBER 95% 85% 94% delivery (100 Call Back) Emergency incidents attended to HT08 92% 93% 95% 99% GREEN 93% RED 98% 95% 94% within 2 hours Streetlights, illuminated signs and HT12 95% 92% 93% N/a GREEN 94% GREEN 90% 80% 95% bollards repaired in 28 calendar days Priority (Member) Enquiries HT14 17% 37% 38% 44% RED 34% RED 85% 75% 74% completed within 20 working days * Agilisys unable to run survey in August due to resourcing issues.
HT01 – The number of potholes requiring repairs between May and August was 5,685, nearly twice as many as the same period last year. The increase in demand has been mainly due to unusual weather events. The Highways Management team and Amey (the term maintenance contractor) are collaboratively working together through a series of workshops and steering groups to ensure performance gets back to the target level.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Performance DashboardReport | 10 pages | DownloadRead as text |
PDF |
Performance DashboardReport | 2 pages | Download |
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... | Decided | Open |
| 5 May 2026 | Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... | Decided | Open |
| 5 May 2026 | Winter Service UpdateRESOLVED to note the Winter Service Update . | Noted | Open |
| 5 May 2026 | Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. | Noted | Open |
| 5 May 2026 | 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.