Resolved
RESOLVED that the actions taken or contemplated in the report be noted and endorsed.
Regulation Committee noted this item on Tuesday 30 January 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the actions taken or contemplated in the report be noted and endorsed.
Update on Planning Enforcement Issues Item 7
Report by Head of Planning Applications Group to the Regulation Committee on 30th January 2024.
Summary: Update for Members on planning enforcement matters.
Recommendation: To endorse the actions taken or contemplated on respective cases.
Unrestricted
Introduction
1. This report provides an update into events, operational matters and activities of the County Planning Enforcement service, since the 17th October 2023 Regulation Committee.
2. KCC planning enforcement remains under both resourcing and operational pressures, with an increasing caseload and complexity, especially at the priority strategic end of the spectrum. An increase in alleged waste criminal activity to this level, is continuing across the county, often in the context of a mix of planning uses.
3. The County Council regularly works with allied bodies and the police and is actively seeking to incorporate government bodies such as Natural England (NE) and His Majesty’s Revenue and Customs (HMRC) into local enforcement work.
4. Collaboration and sharing of resources are key, particularly given current economic and spending pressures within the public sector and the range of planning uses involved. Joint operational working has shown to be effective in cost and enforcement terms.
Report Format
5. Our reporting to the Regulation Committee on planning enforcement matters comprises of two main parts.
6. The first being this ‘open’ report, summarising in general, our findings and observations relating to enforcement matters, for discussion. In addition, it includes the nature of the alleged unauthorised activities and types of responses, incorporating as much as can be released on operational matters without prejudicing any action that the Council may wish to take, or in relation to team actions with other regulatory bodies. Data security in this field of work is inherently important.
7. The second is the ‘closed’ or ‘exempt’ report (within Item 9 of these papers) containing restricted details on cases. These report the work conducted, in Update on Planning Enforcement Issues Item 7
priority order, with the strategic level cases first (with a County Council interest / remit). These are followed by district referrals, including those where issues of jurisdiction remain, and including ‘cross-over’ work with partner bodies and finally alleged compliance issues at permitted sites.
8. In this way, a more in-depth analysis of alleged unauthorised activities becomes possible, with cross-comparisons between sites and the search for patterns of alleged contravening behaviour. It also enables the confidentiality of the content and strategy of any proposed planning enforcement action to be protected, along with any sensitive gathered evidence.
9. Hearing the details of cases in closed session further allows for uninhibited discussion, in seeking Member endorsement, on our own or joint enforcement strategies with other regulatory authorities (with their own need for confidentiality).
10. As a counter-balance to security restrictions, a list is provided, under paragraph 11 below, of the cases that will be covered in the exempt report. This covers those sites currently active or requiring investigation. Those previously reported and inactive, remain on a ‘holding / monitoring’ database to be brought back to the Committee, should further activity occur, or as an update on site restoration and after-uses. Notwithstanding that, forward momentum still continues in the background, on the restoration of affected sites.
11. Our current and immediate operational workload, qualified by remit and with resource priority (with other cases on a ‘holding’ database) is as follows:
County Matter cases (complete, potential, forming a significant element or as a regulatory group contribution)
01 Hoads Wood, Bethersden, Ashford
02 Swanton Lane, Littlebourne, Canterbury
03 Ancient Woodland Adjacent to Knoxfield Caravan Site, Darenth Wood Road, Dartford
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update on Planning Enforcement IssuesReport | 7 pages | DownloadRead as text |
Follow Regulation Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Oct 2025 | Election of ChairRESOLVED that [name removed] be elected Chair of Regulation Committee. | Decided | Open |
| 16 Oct 2025 | Election of Vice-ChairRESOLVED that [name removed] be elected as Vice-Chair of Regulation Committee. | Decided | Open |
| 16 Oct 2025 | Update from the Public Rights of Way and Access ServiceRESOLVED that the report be noted. | Noted | Open |
| 16 Oct 2025 | Update on Planning Enforcement CasesRESOLVED to note the report and endorse the enforcement strategies outlined in Appendices 1 and 2. | Noted | Open |
| 21 Jan 2025 | MembershipRESOLVED to note that [name removed] had joined the committee. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.