24/00040 - Proposal to add four classrooms at Whitfield Aspen Primary School (Richmond Way site)

Approved Executive 3 papers

Children, Young People and Education Cabinet Committee approved this item on Thursday 16 May 2024. Below is the council's own wording, with the papers it was decided on.

Item16

Resolved

RESOLVED to endorse the proposed decision that the Cabinet Member for Education and Skills: a) Approve the allocation of up to £2,800,000 of capital funding from the CYPE capital budget to add an eight classroom block at Whitfield Aspen Primary School (Richmond Way site). b) Delegate authority to the Director of Infrastructure in consultation with the Director of Education to enter into any necessary contracts or other legal agreements as required to implement this decision. c) Authorise the Director of Infrastructure to be the nominated Authority Representative within the relevant agreements and to enter into variations as envisaged under the contracts.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Children, Young People and Education Cabinet Committee, 4 pages

EQIA Submission Form Information collected from the EQIA Submission EQIA Submission – ID Number Section A EQIA Title Proposal to add an eight classroom block at Whitfield Aspen Primary School (Richmond Way site) Responsible Officer Lee Round - CY EPA Approved by (Note: approval of this EqIA must be completed within the EqIA App) David Adams - CY EPA Type of Activity Service Change No Service Redesign No Project/Programme Project/Programme Commissioning/Procurement No Strategy/Policy No Details of other Service Activity No Accountability and Responsibility Directorate Children Young People and Education Responsible Service Planning and Access Responsible Head of Service David Adams - CY EPA Responsible Director Christine McInnes - CY EPA Aims and Objectives Aim: The aim of the project is to add 8 classrooms (4 fitted out) to Whitfield Aspen Primary School (Richmond Way site). This will ensure that there is sufficient accommodation to enable the school to expand to 3FE (as has been agreed) whilst continuing to offer the number of specialist places currently available in the specialist resourced provision (SRP).

Context: In 2018 the school was expanded by 1FE (to 3FE) via a second site (Richmond Way) to support the need for additional primary school places within the Whitfield Urban Expansion (WUE). Decisions for issue 16/00032 - Proposal to expand Whitfield Aspen School by 1FE across a split site (kent.gov.uk)

Expansion of the school has been phased. Phase one delivered the core infrastructure required by a 2FE school (library, offices, meeting rooms, food technology etc). Sufficient classroom accommodation was provided to enable the school to grow year on year to 3FE in the mainstream and to offer 112 places in the SRP, the maximum number of specialist places that was required. Phase two was planned to be the addition of a two-storey block of eight additional mainstream classrooms. This was to be added when 4FE of mainstream provision was required.

The rise in EHCPs and the need for specialist primary provision in Dover over a number of years has led to more pupils requiring a place in the SRP then was initially planned. As of January 2024, there were 175 pupils on roll in the SRP across both sites. As noted, the current accommodation (across both school sites) was built to provide for 112 SRP pupils. Having to accommodate c63 additional pupils in the SRP has reduced the number of mainstream classrooms available. At an average of 12 pupils per SRP class base it means 5 of the additional mainstream classrooms are being utilised by the SRP. As things stand, four of these classrooms will be required from September 2025 to enable the school to continue to admit 3FE of mainstream pupils as they are required to do,

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24-00040 EQIA Whitfield AspenReport 4 pages DownloadRead as text
PDF
24-00040 PRoD Whitfield AspenReport 4 pages Download
PDF
24/00040: Proposal to add four classrooms at Whitfield Aspen Primary School (Richmond Way site)Report 6 pages Download

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. 24/00040 - Proposal to add four classrooms at Whitfield Aspen Primary School (Richmond Way site)This decision
  2. 20/00068 - Proposal to provide additional funding to support the provision of a New 2FE Primary School on the Ebbsfleet Green Development, DartfordAgreed
  3. Proposal KCC/GR/0083/2018 - Demolition of existing temporary teaching block and erection of 2-storey extensions to west and east wings of existing Science Block to provide 4 classrooms (a net addition of 2 classrooms) at Mayfield Grammar ScApproved
  4. Proposal GR/18/0930 (KCC/GR/0427/2018) Timber framed extension to provide additional office space at Trosley Country Park, Waterlow Road, Vigo Village, Gravesend; KCC Country ParksDecided
  5. Proposal SE/18/01521/KCCRG3 (KCC/SE/0075/2018) - Erection of a two storey extension to the existing school to provide accommodation for an additional Form of Entry (1FE to 2FE), relocation of existing mobile classroom and the provision of aDecided
  6. Proposal DA/18/659 (KCC/DA/0088/2018) - Temporary application for retention of 3 modular classrooms (permitted under DA/17/1626), provision of a further 3 modular classrooms to accommodate the September 2018 allocation of pupils and 42 addiDecided

More from Kent Children, Young People and Education Cabinet Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 Minutes of the meeting held on 12 May 2026RESOLVED that the minutes of the meeting held on 12 May 2026 were a correct record. Decided Open
14 Jul 2026 Verbal Update by Cabinet MembersRESOLVED that the verbal updates be noted. Noted Open
14 Jul 2026 Performance MonitoringRESOLVED that the report be noted. Noted Open
14 Jul 2026 26/00042 - Proposed Expansion of Oakwood Park Grammar SchoolRESOLVED that the Committee considered and endorsed the proposed decision Decided Open
14 Jul 2026 26/00043 - Expert at Hands (EaH) and Local Authority (LA) Special Education Needs & Disability (SEND) Transformation GrantRESOLVED that the Committee considered and endorsed the proposed decision Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies