24/00035 - Contract for Receipt and Treatment of Street Sweepings and Highway Mechanical Arisings

Decided Executive 3 papers

Growth, Environment & Transport Cabinet Committee decided this item on Tuesday 21 May 2024. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED to endorse the recommendations as outlined in the report, subject to the correction above.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Growth, Environment & Transport Cabinet Committee, 5 pages

From: Rob Thomas, Cabinet Member for Environment

Simon Jones, Corporate Director, Growth, Environment and Transport

To: Environment and Transport Cabinet Committee – 21st May 2024

Subject: New Contractual arrangement for the receipt and processing of Street Sweepings and Highway Mechanical Arisings – (SC240015)

Decision Number: 24/00035

Decision Title: Approval to commission and award a new contractual arrangement for the for the receipt and processing of Street Sweepings and Highway Mechanical Arisings – (SC240015)

Classification: Unrestricted

Past Pathway of report: N/A

Future Pathway of report: For Cabinet Member Decision

Electoral Division: all Divisions are affected

Summary: Resource Management and Circular Economy is seeking to enter new contractual arrangements in order to continue to receive and process street sweepings and highway mechanical arisings at the Waste Transfer Stations by all the Waste Collection Authorities across Kent.

This is required in order to fulfil KCC’s Statutory Duty as the Waste Disposal Authority operating under the Environmental Protection Act 1990.

Recommendation(s): The Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for the Environment on the proposed decision to

(i) COMMISSION and award a contract for the receipt and processing of street sweepings and highway mechanical arisings for up to 4 years and

(ii) DELEGATE authority to the Director of Environment and Circular Economy in consultation with the Cabinet Member for Community and Regulatory Services to take relevant actions, including but not limited to, awarding, finalising the terms of and entering into the relevant contracts or other legal agreements, as necessary, to implement the decision as shown at Appendix A.

1. Introduction

1.1This report provides information concerning the option to commission and award a Street Sweeping (SS) and Highway Mechanical Arisings (HMA) contract for materials collected by the Waste Collection Authorities. These materials can be mechanically treated by disaggregation, to produce materials for reuse for civil engineering and restoration schemes.

1.2KCC currently has a contract for the delivery of these services which is due to expire on 31st May 2024. The contract had an option to be extended for a further period of up to 24 months and KCC’s original intention was to extend the contract and had commenced discussions with the incumbent in Sept/October 2023 on that basis.

1.3In December 2023, the incumbent notified KCC of challenges they were experiencing in delivering the services and sought additional compensation and an increase to the contracted costs.

1.4In January 2024, the provider submitted their final extension proposal which included a significant price increase and was beyond that included within the anticipated with the revenue budget.

1.5Furthermore, the incumbent Provider’s extension moved away from a fixed cost and sought to include quarterly price reviews.

1.6In order for KCC to determine next steps, commercial market engagement and benchmarking was undertaken in order to informed whether the increased costs were in line with prevailing market rates and to determine the wider market appetite for this material.

1.7The results suggested that KCC could achieve lower and more affordable prices by running a competitive procurement process.

1.8As a result, KCC is undertaking an accelerated procurement process to ensure there is no gap in service delivery and that the Authority is able to meet its statutory duty as the Waste Disposal Authority in providing facilities for the disposal of waste.

1.9It should be noted that KCC while had hoped to be able to resolve the challenges presented by the incumbent the protracted nature of these discussion means that an accelerated procurement process is required to ensure service continuity.

2. Relevant History

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24/00035: Contract for Receipt and Treatment of Street Sweepings and Highway Mechanical ArisingsReport 5 pages DownloadRead as text
PDF
EQIAReport 4 pages Download
PDF
Proposed Record of DecisionDecisions 2 pages Download

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. 24/00035 - Contract for Receipt and Treatment of Street Sweepings and Highway Mechanical ArisingsThis decision
  2. 25/00090 - Procurement for the Receipt and Processing of Wood Waste Contract Countywide - CN260428Approved
  3. 25/00067 - Procurement for the Receipt and Processing of Paper and Card Waste Contract Countywide - CN260429Agreed
  4. 25/00052 - Receipt and processing of Organic Waste Contract CountywideAgreed
  5. 24/00064 - Contract extension for the receipt and processing of organic waste in south west Kent (including Maidstone green waste) - (GW/2004/01)Decided
  6. 21/00006 Approval to commission and award a new contractual arrangement for the receipt and processing of Dry Mixed Recyclable Waste for Mid and West KentDecided

More from Kent Growth, Environment & Transport Cabinet Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... Decided Open
5 May 2026 Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... Decided Open
5 May 2026 Winter Service UpdateRESOLVED to note the Winter Service Update . Noted Open
5 May 2026 Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. Noted Open
5 May 2026 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... Approved Open