Growth, Environment & Transport Cabinet Committee agreed this item on Tuesday 25 February 2025. Below is the council's own wording, with the papers it was decided on.
RESOLVED to endorse the proposed decision, namely: That the Cabinet Member for Highways and Transport agree to: i) Approval to defer the improvement of A228/B2017 junction improvement. ii) Approval to use any surplus S106 funding to progress the feasibility and opportunities for voluntary land acquisition of an alternative A228/B2017 junction improvement for a larger roundabout iii) Approval to progress the amended B2017/B2160 junction improvement as shown indicatively on Drg . No. 60660469-ACM-01-SW-DR-HR-0105 through surveys, design and construction. iv) Approval for the proposed B2017/B2160 junction improvement shown on Drg . No. 60660469- ACM-01-SW-DR-HR-0105 to be used for Land Charge disclosures and development control. v) Approval to take a transfer of land for the B2017/B2160 junction improvement from an adjacent housing development under a section 106 planning obligation and to acquire any other land and rights as necessary. vi) Approval to progress any statutory approvals and ... view the full minutes text for item 11.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Environment & Transport Cabinet Committee, 8 pages
From: Neil Baker – Cabinet Member for Environment & Transport
Haroona Chughtai – Director of Highways & Transportation
To: Environment & Transport Cabinet Committee
25 February 2025
Decision No: 25/00019
Subject: A228/B2017 and B2017/B2160/Mascalls Court Road, Paddock Wood Junction Improvements
Classification: Unrestricted
Past Pathway of Paper: None
Future Pathway of Paper: For Cabinet Member Decision
Electoral Division: Tunbridge Wells Rural – Sarah Hamiliton
Summary: Approval to defer the improvement of the A228/B2017 junction improvement, and approve the amendment of the B2017/B2160 junction improvement; and reaffirming authority to progress the scheme through detailed design and to enter into construction contracts as necessary including any planning and statutory consents required.
Recommendation(s):
The Cabinet Committee is asked to consider and endorse, or make recommendations to the Cabinet Member on, the proposed decisions as follows and as indicated on the proposed decision sheet attached at Appendix A.
i) Approval to defer the improvement of A228/B2017 junction improvement;
ii) Approval to use any surplus S106 funding to progress the feasibility and opportunities for voluntary land acquisition of an alternative A228/B2017 junction improvement for a larger roundabout
iii) Approval to progress the amended B2017/B2160 junction improvement as shown indicatively on Drg. No. 60660469-ACM-01-SW-DR-HR-0105 through surveys, design and construction;
iv) Approval for the proposed B2017/B2160 junction improvement shown on Drg. No. 60660469-ACM-01-SW-DR-HR-0105 to be used for Land Charge disclosures and development control;
v) Approval to take a transfer of land for the B2017/B2160 junction improvement from an adjacent housing development under a section 106 planning obligation and to acquire any other land and rights as necessary; vi) Approval to progress any statutory approvals and consents including Traffic Regulation Orders required for the B2017/B2160 junction improvement scheme including detailed planning consent, drainage and environmental consents and securing temporary use of land for a construction site compound;
vii) Approval to enter into construction contracts as necessary for the delivery of the B2017/B2160 junction improvement scheme subject to any internal approval process required to the proposed procurement strategy; and
viii) Delegate authority to the Corporate Director of Growth, Environment and Transport Approval to take relevant actions, including but not limited to awarding, finalising and entering into the relevant contracts or other legal agreements, as necessary, to implement the decision. 1. Introduction
1.1There are three major housing developments in Paddock Wood that are being implemented and together are delivering nearly 1,000 new homes. The improvement of the A228/B2017 and B2017/B2160 junctions were identified to mitigate the traffic impacts of the new developments as shown on the plans in Appendix B. As three developers were involved, the County Council took responsibility for delivering the schemes using the aggregate section 106 funding and within the land for the B2017/B2160 junction improvement provided for within one section 106 agreement. A report to this Committee and ROD 21/00048 refers.
1.2‘Minor’ and ‘Major’ improvements were identified and the decision was taken to proceed with the major improvements when all three developments were consented. Section 106 contributions with index linking totalling £4.789m were collected from the three developers.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.